Buyer’s Report
Understand this project
Find homes to consider, with advice on light, layout, privacy and surroundings.
₹4,999
Builder’s RERA records,
explained for buyers.
The builder’s RERA record, explained
Kakade Vtp Associates · P52100001269
For Urban Life Phase 1 (P52100001269), 135 of 343 entries were marked unsold in the MahaRERA home list dated 18 July 2026 (saved-file date).
MahaRERA · per-home inventory · saved-file date 18 July 2026
For Urban Life Phase 1, ₹5,806 per sq ft of carpet area is the median rate across 207 sold or booked entries with prices in the MahaRERA home list dated 18 July 2026 (saved-file date). These are historical agreement values, not current asking prices.
MahaRERA · per-home inventory · saved-file date 18 July 2026
These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.
Builder’s completion target
The builder reported this target date. It is not a confirmed handover date.
Status shown on RERA
This is the status shown on RERA. It does not confirm an occupancy certificate or today’s construction progress.
Prices reported to RERA
₹5,806/ sq ft carpet area
Across 207 sold or booked entries with reported prices. The middle 80% of rates fall between ₹5,060 and ₹6,643.
MahaRERA · per-home inventory · saved-file date 18 July 2026
For each sold or booked entry, we divide the reported agreement value by its carpet area in square feet. The median is the middle rate when these rates are put in order. We show it only when at least five entries have prices. We exclude valuations of unsold homes and government reference rates. The figures may include different sizes and property types. They are historical agreement values, not current asking prices or the total cost including extra charges.
Sales Report
Compare reported agreement values by building, size and floor. See which homes were marked unsold on the date shown.
Inside this registered phase
343 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.
MahaRERA · per-home inventory · saved-file date 18 July 2026
Scroll sideways to see all columns.
| Filed building | Entries | Sold | Booked | Marked unsold | Other / unstated status | Recorded carpet-area range |
|---|---|---|---|---|---|---|
| C wing | 84 | 56 | 5 | 23 | 0 | 33.08–68.85 sq m≈ 356–741 sq ft |
| D Wing | 84 | 76 | 1 | 7 | 0 | 33.23–56.17 sq m≈ 358–605 sq ft |
| H Wing | 70 | 2 | 0 | 68 | 0 | 32.36–56.82 sq m≈ 348–612 sq ft |
| I Wing | 105 | 45 | 23 | 37 | 0 | 32.47–57.40 sq m≈ 350–618 sq ft |
Different sizes are not necessarily different bedroom types. How we read and summarise the filing →
Unit Report
Understand its light, privacy, layout and surroundings. See how it compares with similar homes and other options in this project.
Didn’t help you decide? Full refund — no questions asked.
The same home number may appear in more than one building. Check both before choosing.
MahaRERA · per-home inventory · saved-file date 18 July 2026
| Home / building | Floor in the record | Carpet area | Reported status | Agreement value | Assess |
|---|---|---|---|---|---|
| 1001C wing | 10 | 67.51 sq m≈ 727 sq ft | Marked unsold | Not stated | |
| 1002C wing | 10 | 67.51 sq m≈ 727 sq ft | Sold | ₹4,128,300 | |
| 1003C wing | 10 | 67.44 sq m≈ 726 sq ft | Sold | ₹4,026,000 | |
| 1004C wing | 10 | 67.51 sq m≈ 727 sq ft | Marked unsold | Not stated | |
| 1005C wing | 10 | 67.51 sq m≈ 727 sq ft | Marked unsold | Not stated | |
| 1006C wing | 10 | 33.08 sq m≈ 356 sq ft | Sold | ₹2,206,850 | |
| 1007C wing | 10 | 33.29 sq m≈ 358 sq ft | Sold | ₹2,206,850 | |
| 101C wing | 1 | 64.6 sq m≈ 695 sq ft | Booked | ₹4,122,641 | |
| 102C wing | 1 | 68.85 sq m≈ 741 sq ft | Booked | ₹4,122,641 | |
| 103C wing | 1 | 67.32 sq m≈ 725 sq ft | Marked unsold | Not stated | |
| 104C wing | 1 | 40.28 sq m≈ 434 sq ft | Marked unsold | Not stated | |
| 105C wing | 1 | 40.28 sq m≈ 434 sq ft | Sold | ₹2,194,000 |
Read every entry in one table: Read the complete saved home list.
Choose the home you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.
More from the RERA documents
₹478,200,000 of an estimated ₹622,200,000 was reported as incurred (76.9%). This percentage is about costs. It does not show how much construction is complete.
MahaRERA project filing · read 18 July 2026 · registration P52100001269
Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.
| Building | Activity | Reported |
|---|---|---|
| C wing | Excavation | 100.0% |
| C wing | Basement (if any) | 100.0% |
| C wing | Podiums (if any) | 0.0% |
| C wing | Plinth | 100.0% |
| C wing | Stilt Floor | 100.0% |
| C wing | Slabs of Super Structure | 100.0% |
| C wing | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100.0% |
| C wing | Sanitary Fittings within the flats / premises | 100.0% |
| C wing | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100.0% |
| C wing | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100.0% |
| C wing | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100.0% |
| D Wing | Excavation | 100.0% |
| D Wing | Basement (if any) | 100.0% |
| D Wing | Podiums (if any) | 0.0% |
| D Wing | Plinth | 100.0% |
| D Wing | Stilt Floor | 100.0% |
| D Wing | Slabs of Super Structure | 100.0% |
| D Wing | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100.0% |
| D Wing | Sanitary Fittings within the flats / premises | 100.0% |
| D Wing | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100.0% |
| D Wing | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100.0% |
| D Wing | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100.0% |
| H Wing | Excavation | 0.0% |
| H Wing | Basement (if any) | 0.0% |
| H Wing | Podiums (if any) | 0.0% |
| H Wing | Plinth | 0.0% |
| H Wing | Stilt Floor | 0.0% |
| H Wing | Slabs of Super Structure | 0.0% |
| H Wing | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0.0% |
| H Wing | Sanitary Fittings within the flats / premises | 0.0% |
| H Wing | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0.0% |
| H Wing | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0.0% |
| H Wing | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0.0% |
| I Wing | Excavation | 100.0% |
| I Wing | Basement (if any) | 100.0% |
| I Wing | Podiums (if any) | 0.0% |
| I Wing | Plinth | 100.0% |
| I Wing | Stilt Floor | 100.0% |
| I Wing | Slabs of Super Structure | 100.0% |
| I Wing | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100.0% |
| I Wing | Sanitary Fittings within the flats / premises | 100.0% |
| I Wing | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100.0% |
| I Wing | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100.0% |
| I Wing | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100.0% |
MahaRERA project filing · read 18 July 2026 · registration P52100001269
| Revised target | Reason given by the builder |
|---|---|
| 30 December 2022 | Migration of project from PMRDA to nagar panchayat .Due to this project sanction and progress delayed |
| 31 December 2024 | The project is delayed due to (1) the Land under project was moved from Pune Metropolitan Region Development Authority (PMRDA) to Vadagon Nagara Panchayat and later further moved to Vadagaon Maval Nagar Panchayat, this transition delayed procedural aspect in approvals (2) Due to Pandemic COVID-19, the operations of the project were substantially affected in the absence of material and unavailability of labour, hence the operations were severally affected for long time, hence the construction activities were affected and delayed the completion of project (3) The Occupancy Certificate for Tower C & D have already been granted by Vadgaon Maval Nagar Panchayat and remaining development is in progress. |
| 31 December 2025 | 1. Project Details: The promoter has registered the project ‘Urban Life Phase 1’ with the Maharashtra Real Estate Regulatory Authority vide no P52100001269. 2. The project is delayed due to: i)There is huge unsold stock in the project for which sale and banking, extension is required ii) The Land under project was moved from Pune Metropolitan Region Development Authority (PMRDA) to Vadagon Nagara Panchayat and later further moved to Vadagaon Maval Nagar Panchayat, this transition delayed procedural aspect in approvals. iii) Delay Due to Pandemic: The COVID-19 pandemic significantly disrupted the project's operations, primarily due to material shortages and labor unavailability. As a result, construction activities were severely impacted, leading to prolonged delays in the project's completion. iv) Concrete and Raw Material Strike: A district-wide strike by the Pune District Mining and Crusher Industries in December 2022 and again in 2024, led to significant delays in the project. The strikes resulted in severe shortage of concrete and other essential raw materials, further compounding the delays and disrupting the construction schedule. The Promoter will not be able to sell the unsold plots, as a result of which the project may suffer significantly, hence the extension is sought. The promoter has also uploaded PERT Chart along with this application. In view of above, we humbly request you to grant us extension for the project till 31.12.2025. |
| 31 December 2026 | 1. The project stands at 95% completion. 2. The consent of 58.99% of allottees has been uploaded in support of this extension application. 3. Form B uploaded. 4. PERT for the remaining completion work is uploaded in the Application. 5. The Project got delayed due to following reasons:- The delay in completion of the project is primarily due to the pending Part Occupancy Certificate for the balance portion of the project. The Promoter has already obtained Part Occupancy Certificate dated 09/01/2026 from Vadgaon Maval Nagar Panchayat for C, D & I Wings, and possession of the respective units has been handed over to the concerned allottees. Further, pursuant to the revised sanctioned plan, certain correction and rectification works are required to be carried out in the remaining portion of the project. Due to these works, the pending Part Occupancy Certificate could not be obtained within the stipulated timeline. 6. The revised date of completion is now 31/12/2026. 7. We hereby assure the Hon’ble Authority that the project shall be fully completed within this stipulated time and the OC will be obtained. 8. We humbly request your kind approval of the extension to enable us to complete the project and honour all commitments to our allottees. |
MahaRERA project filing · read 18 July 2026 · registration P52100001269
RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.
| Filing | Own funds | Borrowing | Payments from buyers | Total |
|---|---|---|---|---|
| Estimated plan | ₹0 | ₹0 | ₹936,781,494 | ₹1,115,701,052 |
| Actual raised | ₹650,292,722 | ₹0 | ₹399,703,314 | ₹1,049,996,036 |
MahaRERA project filing · read 18 July 2026 · registration P52100001269
34 elapsed quarterly periods in the captured compliance schedule. No active quarterly default was recorded in this snapshot.
MahaRERA project filing · read 18 July 2026 · registration P52100001269
A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.
MahaRERA project filing · read 18 July 2026 · registration P52100001269
Builder and past records
Projects registered under this company
2Pune registrations
These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.
MahaRERA Pune registration records · read 12 July 2026
Past records of sales and unsold homes
21 September 2026
135 marked unsold · 179 sold · 29 booked.
Saved MahaRERA home list
12 September 2026
135 marked unsold · 179 sold · 29 booked.
Saved MahaRERA home list
4 September 2026
135 marked unsold · 179 sold · 29 booked.
Saved MahaRERA home list
18 July 2026
135 marked unsold · 179 sold · 29 booked.
Saved MahaRERA home list
These dates show when the records were saved, not when homes were sold. Sales may have changed since then, even if the saved counts are the same.
Project Comparison Report
Compare up to three projects. We read their plans and RERA documents, recommend homes in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.
2 projects · ₹7,999
3 projects · ₹9,999
Within 1 working day
Didn’t help you decide? Full refund — no questions asked.
Compare project details for free →MahaRERA · registration record · read 12 July 2026
MahaRERA · per-home inventory · saved-file date 18 July 2026
This is a past RERA home list, not current availability. It does not give the date each home was sold.
The home-list date is based on the saved file’s details.
Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.
Open MahaRERA · search P52100001269 ↗