The builder’s RERA record, explained

Astonia Classic Phase II - A5 Building

AMIT ENTERPRISES HOUSING LIMITED · P52100001359

MahaRERA · registration record · read 12 July 2026

Choose a report ↓

What does the RERA record show?

For Astonia Classic Phase II - A5 Building (P52100001359), 48 of 96 entries were marked unsold in the MahaRERA home list dated 18 July 2026 (saved-file date).

MahaRERA · per-home inventory · saved-file date 18 July 2026

For Astonia Classic Phase II - A5 Building, ₹7,002 per sq ft of carpet area is the median rate across 48 sold or booked entries with prices in the MahaRERA home list dated 18 July 2026 (saved-file date). These are historical agreement values, not current asking prices.

MahaRERA · per-home inventory · saved-file date 18 July 2026

These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.

What would help you decide?

Buyer’s Report

Understand this project

Find homes to consider, with advice on light, layout, privacy and surroundings.

₹4,999

Unit Report

Check a particular home

See its advantages, drawbacks and how it compares with other homes in this project.

₹3,999

Project Comparison Report

Choose between projects

Compare two or three projects and get recommended homes in order, with reasons for each choice.

From ₹7,999

Choose projects →

Project status and completion date.

Prices reported to RERA

What prices have been reported?

₹7,002/ sq ft carpet area

Across 48 sold or booked entries with reported prices. The middle 80% of rates fall between ₹6,326 and ₹8,450.

MahaRERA · per-home inventory · saved-file date 18 July 2026

How is this calculated?

For each sold or booked entry, we divide the reported agreement value by its carpet area in square feet. The median is the middle rate when these rates are put in order. We show it only when at least five entries have prices. We exclude valuations of unsold homes and government reference rates. The figures may include different sizes and property types. They are historical agreement values, not current asking prices or the total cost including extra charges.

Sales Report

What did similar homes sell for?

Compare reported agreement values by building, size and floor. See which homes were marked unsold on the date shown.

₹2,999 · delivered on payment

Inside this registered phase

How do the buildings compare in the record?

96 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.

MahaRERA · per-home inventory · saved-file date 18 July 2026

Scroll sideways to see all columns.

Building names, sale status and carpet areas — not current availability
Filed buildingEntriesSoldBookedMarked unsoldOther / unstated statusRecorded carpet-area range
Building A596361248049.58–50.54 sq m≈ 534–544 sq ft

Different sizes are not necessarily different bedroom types. How we read and summarise the filing →

Unit Report

Is this the right
home for you?

Understand its light, privacy, layout and surroundings. See how it compares with similar homes and other options in this project.

₹3,999 · 1 working day

Didn’t help you decide? Full refund — no questions asked.

Find your home in the RERA list.

The same home number may appear in more than one building. Check both before choosing.

96 listed entries

MahaRERA · per-home inventory · saved-file date 18 July 2026

RERA home list, not current availability
Home / buildingFloor in the recordCarpet areaReported statusAgreement valueAssess
1001Building A51049.58 sq m≈ 534 sq ftMarked unsoldNot stated
1002Building A51049.58 sq m≈ 534 sq ftSold₹3,353,930
1003Building A51049.58 sq m≈ 534 sq ftSold₹4,910,700
1004Building A51049.58 sq m≈ 534 sq ftMarked unsoldNot stated
1005Building A51049.58 sq m≈ 534 sq ftSold₹4,231,586
1006Building A51049.58 sq m≈ 534 sq ftMarked unsoldNot stated
1007Building A51049.58 sq m≈ 534 sq ftMarked unsoldNot stated
1008Building A51049.58 sq m≈ 534 sq ftMarked unsoldNot stated
101Building A5150.54 sq m≈ 544 sq ftSold₹4,381,340
102Building A5150.54 sq m≈ 544 sq ftMarked unsoldNot stated
103Building A5150.54 sq m≈ 544 sq ftMarked unsoldNot stated
104Building A5150.54 sq m≈ 544 sq ftBooked₹3,678,128

Read every entry in one table: Read the complete saved home list.

Choose the home you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.

More from the RERA documents

Construction progress and project documents.

Cost reported as incurred

₹173,000,000 of an estimated ₹241,249,360 was reported as incurred (71.7%). This percentage is about costs. It does not show how much construction is complete.

MahaRERA project filing · read 18 July 2026 · registration P52100001359

Work reported, by building

Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.

See all reported activities
BuildingActivityReported
Building A5Excavation100.0%
Building A5Basement (if any)100.0%
Building A5Podiums (if any) 100.0%
Building A5Plinth100.0%
Building A5Stilt Floor 100.0%
Building A5Slabs of Super Structure100.0%
Building A5Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises92.0%
Building A5Sanitary Fittings within the flats / premises55.0%
Building A5Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks94.0%
Building A5External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90.0%
Building A5Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.70.0%

MahaRERA project filing · read 18 July 2026 · registration P52100001359

Reported deadline extensions

Revised targetReason given by the builder
30 December 2021Acute economic crisis in the real estate market.
31 December 2023The slow market condition and a slump in the real estate market during the period created acute economic crises which ultimately slowed down the sale transactions. However, somehow we were managing and pulling ourselves to complete the project in the scheduled time. The market conditions were getting better but due to the emergence of the Covid 19 outbreak, we faced a massive downfall affecting the project. We are committed to providing our customers with what was promised to them with the utmost standard. Therefore, we request you kindly grant us an extension of registration for 1 year to complete the said project. The customers believe in us and hence provided their consent for the same.
31 December 2024We encountered significant challenges in completing the project within the stipulated timeline, primarily due to sluggish market conditions and a downturn in the real estate sector. The economic crises resulting from these factors impeded the progress of sale transactions, creating a substantial impact on the project's cash flow. Just as market conditions were showing signs of improvement, the emergence of the COVID-19 outbreak led to a massive downturn, further disrupting the project's financial stability. Consequently, the construction project experienced a considerable delay, causing monetary distress. Transparent communication with our customers was crucial, and fortunately, they have demonstrated confidence in our commitment. They have provided their consent for an extension, acknowledging the unforeseen challenges we faced. Therefore, we request you to kindly grant us an extension of registration to complete the said project.
31 December 2025Amit Enterprises Housing Ltd and its group entities have faced considerable pressure due to several external factors which have ultimately caused the delay in the construction of the project. COVID-19 Pandemic: The COVID-19 pandemic severely impacted the project's stability, causing significant delays primarily due to labour shortages from migrant workers returning to their native states and disruptions in the supply chain for materials and equipment. These challenges exacerbated construction delays and complicated efforts to get the project back on track. The increased costs of labour and the sluggish market conditions further impeded progress, with the downturn in the real estate sector affecting sale transactions and cash flow, ultimately leading to a considerable delay in the project's completion. Proactive Measures Taken: Despite these challenges, we have taken several proactive steps to mitigate their impact. We have renegotiated supplier contracts, implemented cost-saving measures, and worked closely with our labour force to expedite their return under safe working conditions. These measures have helped us resume construction activities, currently the construction of the project is in full swing. Looking at the progress the customers too have provided the consent for the extension.
31 December 20261. The project stands at 70% completion 2. The consent of 68.75% of allottees has been uploaded in support of this extension application. 3. Revised Form B uploaded 4. PERT for the remaining completion work is uploaded in the Application. 5. The Project got delayed due to following reasons: a. The sector experienced subdued buyer demand and slow absorption, impacting sales, cash flows, and construction timelines. b. Funding constraints and cash flow interruptions caused delays in material procurement and site operations. c. Shortage of skilled labour and delays in the supply of key materials further affected project progress. d. Construction resumption was impacted by significant cost escalation, particularly labour costs, which increased sharply post-pandemic. e. The increased costs exerted financial pressure while maintaining project continuity and meeting financial commitments. f. Unseasonal and extreme weather conditions during critical construction phases resulted in additional schedule delays. 6. The revised date of completion is now 31/12/2026. 7. We hereby assure the Hon’ble Authority that the project shall be fully completed within this stipulated time and the OC will be obtained. 8. We humbly request your kind approval of the extension to enable us to complete the project and honour all commitments to our allottees.

MahaRERA project filing · read 18 July 2026 · registration P52100001359

Where the project funding comes from

RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.

FilingOwn fundsBorrowingPayments from buyersTotal
Estimated plan₹0₹145,209,532₹233,045,664₹378,255,196
Actual raised₹0₹19,117,162₹86,203,064₹105,320,226

MahaRERA project filing · read 18 July 2026 · registration P52100001359

Quarterly filing record

36 elapsed quarterly periods in the captured compliance schedule. No active quarterly default was recorded in this snapshot.

MahaRERA project filing · read 18 July 2026 · registration P52100001359

Documents named in the filing

  • Promoter PAN · 1 listed
  • Form 1 — Architect's certificate · 4 listed
  • Form 3 — CA certificate · 5 listed
  • Form 2 — Engineer's certificate · 4 listed
  • Form B — Promoter declaration · 3 listed
  • Title / search report · 1 listed
  • Sanctioned layout plan · 1 listed
  • Sanctioned building plan · 1 listed

A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.

MahaRERA project filing · read 18 July 2026 · registration P52100001359

Builder and past records

What else does the record show?

Projects registered under this company

AMIT ENTERPRISES HOUSING LIMITED

6Pune registrations

These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.

MahaRERA Pune registration records · read 12 July 2026

Explore other registrations

Past records of sales and unsold homes

  1. 21 September 2026

    48 marked unsold · 36 sold · 12 booked.

    Saved MahaRERA home list

  2. 13 September 2026

    48 marked unsold · 36 sold · 12 booked.

    Saved MahaRERA home list

  3. 4 September 2026

    48 marked unsold · 36 sold · 12 booked.

    Saved MahaRERA home list

  4. 18 July 2026

    48 marked unsold · 36 sold · 12 booked.

    Saved MahaRERA home list

These dates show when the records were saved, not when homes were sold. Sales may have changed since then, even if the saved counts are the same.

More projects to explore

Other projects in this locality.

These projects list the same locality. They may differ in exact location, home type and price.

Project Comparison Report

Which project should you buy in?
And which home?

Compare up to three projects. We read their plans and RERA documents, recommend homes in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.

Create my Comparison Report →

2 projects · ₹7,999
3 projects · ₹9,999

Within 1 working day

Didn’t help you decide? Full refund — no questions asked.

Compare project details for free →

Sources and dates.

MahaRERA · registration record · read 12 July 2026

MahaRERA · per-home inventory · saved-file date 18 July 2026

This is a past RERA home list, not current availability. It does not give the date each home was sold.

The home-list date is based on the saved file’s details.

Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.

Open MahaRERA · search P52100001359 ↗