The builder’s RERA record, explained

Royal Oak

Lifestyle Developments · P52100001837

MahaRERA · registration record · read 12 July 2026

Choose a report ↓

What does the RERA record show?

For Royal Oak (P52100001837), 6 of 321 entries were marked unsold in the MahaRERA home list dated 18 July 2026 (saved-file date).

MahaRERA · per-home inventory · saved-file date 18 July 2026

For Royal Oak, ₹8,686 per sq ft of carpet area is the median rate across 295 sold or booked entries with prices in the MahaRERA home list dated 18 July 2026 (saved-file date). These are historical agreement values, not current asking prices.

MahaRERA · per-home inventory · saved-file date 18 July 2026

These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.

What would help you decide?

Buyer’s Report

Understand this project

Find homes to consider, with advice on light, layout, privacy and surroundings.

₹4,999

Unit Report

Check a particular home

See its advantages, drawbacks and how it compares with other homes in this project.

₹3,999

Project Comparison Report

Choose between projects

Compare two or three projects and get recommended homes in order, with reasons for each choice.

From ₹7,999

Choose projects →

Project status and completion date.

Prices reported to RERA

What prices have been reported?

₹8,686/ sq ft carpet area

Across 295 sold or booked entries with reported prices. The middle 80% of rates fall between ₹6,323 and ₹9,710.

MahaRERA · per-home inventory · saved-file date 18 July 2026

How is this calculated?

For each sold or booked entry, we divide the reported agreement value by its carpet area in square feet. The median is the middle rate when these rates are put in order. We show it only when at least five entries have prices. We exclude valuations of unsold homes and government reference rates. The figures may include different sizes and property types. They are historical agreement values, not current asking prices or the total cost including extra charges.

Sales Report

What did similar homes sell for?

Compare reported agreement values by building, size and floor. See which homes were marked unsold on the date shown.

₹2,999 · delivered on payment

Inside this registered phase

How do the buildings compare in the record?

321 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.

MahaRERA · per-home inventory · saved-file date 18 July 2026

Scroll sideways to see all columns.

Building names, sale status and carpet areas — not current availability
Filed buildingEntriesSoldBookedMarked unsoldOther / unstated statusRecorded carpet-area range
B1B26350001348.77–48.93 sq m≈ 525–527 sq ft
Building A1757000532.25–36.05 sq m≈ 347–388 sq ft
Building A2A315114504253.53–73.19 sq m≈ 576–788 sq ft
Mhada Proposed but not Sanctioned323002026.21–232.46 sq m≈ 282–2,502 sq ft

Different sizes are not necessarily different bedroom types. How we read and summarise the filing →

Unit Report

Is this the right
home for you?

Understand its light, privacy, layout and surroundings. See how it compares with similar homes and other options in this project.

₹3,999 · 1 working day

Didn’t help you decide? Full refund — no questions asked.

Find your home in the RERA list.

The same home number may appear in more than one building. Check both before choosing.

321 listed entries

MahaRERA · per-home inventory · saved-file date 18 July 2026

RERA home list, not current availability
Home / buildingFloor in the recordCarpet areaReported statusAgreement valueAssess
B1-101B1B2148.8 sq m≈ 525 sq ftSold₹4,241,000
B1-102B1B2148.77 sq m≈ 525 sq ftReservedNot stated
B1-103B1B2148.77 sq m≈ 525 sq ftSold₹4,330,000
B1-104B1B2148.8 sq m≈ 525 sq ftSold₹4,263,000
B1-201B1B2148.92 sq m≈ 527 sq ftNot for saleNot stated
B1-202B1B2248.93 sq m≈ 527 sq ftNot for saleNot stated
B1-203B1B2248.93 sq m≈ 527 sq ftNot for saleNot stated
B1-204B1B2248.92 sq m≈ 527 sq ftSold₹4,343,500
B1-301B1B2348.77 sq m≈ 525 sq ftSold₹4,714,000
B1-302B1B2348.77 sq m≈ 525 sq ftSold₹4,711,500
B1-303B1B2348.77 sq m≈ 525 sq ftSold₹4,536,000
B1-304B1B2348.77 sq m≈ 525 sq ftSold₹4,480,700

Read every entry in one table: Read the complete saved home list.

Choose the home you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.

More from the RERA documents

Construction progress and project documents.

Cost reported as incurred

₹644,269,360 of an estimated ₹774,494,353 was reported as incurred (83.2%). This percentage is about costs. It does not show how much construction is complete.

MahaRERA project filing · read 18 July 2026 · registration P52100001837

Work reported, by building

Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.

See all reported activities
BuildingActivityReported
B1B2Excavation100.0%
B1B2Basement (if any)100.0%
B1B2Podiums (if any) 100.0%
B1B2Plinth100.0%
B1B2Stilt Floor 100.0%
B1B2Slabs of Super Structure100.0%
B1B2Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100.0%
B1B2Sanitary Fittings within the flats / premises100.0%
B1B2Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100.0%
B1B2External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100.0%
B1B2Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100.0%
Building A1Excavation100.0%
Building A1Basement (if any)100.0%
Building A1Podiums (if any) 100.0%
Building A1Plinth100.0%
Building A1Stilt Floor 100.0%
Building A1Slabs of Super Structure100.0%
Building A1Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100.0%
Building A1Sanitary Fittings within the flats / premises100.0%
Building A1Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100.0%
Building A1External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100.0%
Building A1Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100.0%
Building A2A3Excavation100.0%
Building A2A3Basement (if any)100.0%
Building A2A3Podiums (if any) 100.0%
Building A2A3Plinth100.0%
Building A2A3Stilt Floor 100.0%
Building A2A3Slabs of Super Structure100.0%
Building A2A3Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100.0%
Building A2A3Sanitary Fittings within the flats / premises100.0%
Building A2A3Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100.0%
Building A2A3External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100.0%
Building A2A3Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100.0%
Mhada Proposed but not SanctionedExcavation100.0%
Mhada Proposed but not SanctionedBasement (if any)0.0%
Mhada Proposed but not SanctionedPodiums (if any) 100.0%
Mhada Proposed but not SanctionedPlinth100.0%
Mhada Proposed but not SanctionedStilt Floor 100.0%
Mhada Proposed but not SanctionedSlabs of Super Structure100.0%
Mhada Proposed but not SanctionedInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100.0%
Mhada Proposed but not SanctionedSanitary Fittings within the flats / premises100.0%
Mhada Proposed but not SanctionedStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100.0%
Mhada Proposed but not SanctionedExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100.0%
Mhada Proposed but not SanctionedInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100.0%

MahaRERA project filing · read 18 July 2026 · registration P52100001837

Reported deadline extensions

Revised targetReason given by the builder
31 December 2026The project has experienced delays primarily due to unfavorable market conditions and a legal issues.

MahaRERA project filing · read 18 July 2026 · registration P52100001837

Where the project funding comes from

RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.

FilingOwn fundsBorrowingPayments from buyersTotal
Estimated plan₹119,898,217₹40,000,000₹882,976,772₹1,073,958,258
Actual raised₹42,298,319₹335,635₹964,471,259₹1,020,349,979

MahaRERA project filing · read 18 July 2026 · registration P52100001837

Quarterly filing record

36 elapsed quarterly periods in the captured compliance schedule. No active quarterly default was recorded in this snapshot.

MahaRERA project filing · read 18 July 2026 · registration P52100001837

Documents named in the filing

  • Promoter PAN · 1 listed
  • Form 1 — Architect's certificate · 1 listed
  • Form 3 — CA certificate · 1 listed
  • Form 2 — Engineer's certificate · 1 listed
  • Title / search report · 1 listed
  • Form B — Promoter declaration · 1 listed
  • Sanctioned building plan · 50 listed
  • Sanctioned layout plan · 5 listed

A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.

MahaRERA project filing · read 18 July 2026 · registration P52100001837

Builder and past records

What else does the record show?

Projects registered under this company

Lifestyle Developments

1Pune registrations

These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.

MahaRERA Pune registration records · read 12 July 2026

Explore other registrations

    Past records of sales and unsold homes

    1. 21 September 2026

      6 marked unsold · 295 sold · 0 booked.

      Saved MahaRERA home list

    2. 13 September 2026

      6 marked unsold · 295 sold · 0 booked.

      Saved MahaRERA home list

    3. 4 September 2026

      6 marked unsold · 295 sold · 0 booked.

      Saved MahaRERA home list

    4. 18 July 2026

      6 marked unsold · 295 sold · 0 booked.

      Saved MahaRERA home list

    These dates show when the records were saved, not when homes were sold. Sales may have changed since then, even if the saved counts are the same.

    More projects to explore

    Other projects in this locality.

    These projects list the same locality. They may differ in exact location, home type and price.

    Project Comparison Report

    Which project should you buy in?
    And which home?

    Compare up to three projects. We read their plans and RERA documents, recommend homes in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.

    Create my Comparison Report →

    2 projects · ₹7,999
    3 projects · ₹9,999

    Within 1 working day

    Didn’t help you decide? Full refund — no questions asked.

    Compare project details for free →

    Sources and dates.

    MahaRERA · registration record · read 12 July 2026

    MahaRERA · per-home inventory · saved-file date 18 July 2026

    This is a past RERA home list, not current availability. It does not give the date each home was sold.

    The home-list date is based on the saved file’s details.

    Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.