Buyer’s Report
Understand this project
Find homes to consider, with advice on light, layout, privacy and surroundings.
₹4,999
Builder’s RERA records,
explained for buyers.
The builder’s RERA record, explained
SSG REALTY AND INFRA LLP · P52100002391
For SUBURBIA ESTATE PHASE 1 (P52100002391), 65 of 430 entries were marked unsold in the MahaRERA home list dated 18 July 2026 (saved-file date).
MahaRERA · per-home inventory · saved-file date 18 July 2026
For SUBURBIA ESTATE PHASE 1, ₹4,175 per sq ft of carpet area is the median rate across 264 sold or booked entries with prices in the MahaRERA home list dated 18 July 2026 (saved-file date). These are historical agreement values, not current asking prices.
MahaRERA · per-home inventory · saved-file date 18 July 2026
These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.
Builder’s completion target
The builder reported this target date. It is not a confirmed handover date.
Status shown on RERA
This is the status shown on RERA. It does not confirm an occupancy certificate or today’s construction progress.
Prices reported to RERA
₹4,175/ sq ft carpet area
Across 264 sold or booked entries with reported prices. The middle 80% of rates fall between ₹3,486 and ₹4,774.
MahaRERA · per-home inventory · saved-file date 18 July 2026
For each sold or booked entry, we divide the reported agreement value by its carpet area in square feet. The median is the middle rate when these rates are put in order. We show it only when at least five entries have prices. We exclude valuations of unsold homes and government reference rates. The figures may include different sizes and property types. They are historical agreement values, not current asking prices or the total cost including extra charges.
Sales Report
Compare reported agreement values by building, size and floor. See which homes were marked unsold on the date shown.
Inside this registered phase
430 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.
MahaRERA · per-home inventory · saved-file date 18 July 2026
Scroll sideways to see all columns.
| Filed building | Entries | Sold | Booked | Marked unsold | Other / unstated status | Recorded carpet-area range |
|---|---|---|---|---|---|---|
| BUILDING A | 143 | 76 | 0 | 18 | 49 | 38.83–55.46 sq m≈ 418–597 sq ft |
| BUILDING B | 96 | 75 | 0 | 8 | 13 | 42.64–73.76 sq m≈ 459–794 sq ft |
| BUILDING C | 96 | 57 | 0 | 21 | 18 | 42.64–73.76 sq m≈ 459–794 sq ft |
| BUILDING D | 95 | 56 | 0 | 18 | 21 | 38.38–55.56 sq m≈ 413–598 sq ft |
Different sizes are not necessarily different bedroom types. How we read and summarise the filing →
Unit Report
Understand its light, privacy, layout and surroundings. See how it compares with similar homes and other options in this project.
Didn’t help you decide? Full refund — no questions asked.
The same home number may appear in more than one building. Check both before choosing.
MahaRERA · per-home inventory · saved-file date 18 July 2026
| Home / building | Floor in the record | Carpet area | Reported status | Agreement value | Assess |
|---|---|---|---|---|---|
| A 412BUILDING A | 4 | 53.79 sq m≈ 579 sq ft | Sold | ₹2,637,000 | |
| A 1001BUILDING A | 10 | 55.28 sq m≈ 595 sq ft | Marked unsold | Not stated | |
| A 1002BUILDING A | 10 | 39.39 sq m≈ 424 sq ft | Sold | ₹1,817,426 | |
| A 1003BUILDING A | 10 | 39.39 sq m≈ 424 sq ft | Sold | ₹1,817,426 | |
| A 1004BUILDING A | 10 | 39.39 sq m≈ 424 sq ft | Not for sale | Not stated | |
| A 1005BUILDING A | 10 | 39.39 sq m≈ 424 sq ft | Not for sale | Not stated | |
| A 1006BUILDING A | 10 | 55.28 sq m≈ 595 sq ft | Sold | ₹2,095,000 | |
| A 1007BUILDING A | 10 | 55.28 sq m≈ 595 sq ft | Not for sale | Not stated | |
| A 1008BUILDING A | 10 | 39.39 sq m≈ 424 sq ft | Sold | ₹1,590,930 | |
| A 1009BUILDING A | 10 | 39.39 sq m≈ 424 sq ft | Sold | ₹1,590,930 | |
| A 101BUILDING A | 1 | 55.46 sq m≈ 597 sq ft | Not for sale | Not stated | |
| A 1010BUILDING A | 10 | 39.39 sq m≈ 424 sq ft | Sold | ₹1,590,796 |
Read every entry in one table: Read the complete saved home list.
Choose the home you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.
More from the RERA documents
₹360,000,000 of an estimated ₹665,815,295 was reported as incurred (54.1%). This percentage is about costs. It does not show how much construction is complete.
MahaRERA project filing · read 18 July 2026 · registration P52100002391
Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.
| Building | Activity | Reported |
|---|---|---|
| BUILDING A | Excavation | 100.0% |
| BUILDING A | Basement (if any) | 100.0% |
| BUILDING A | Podiums (if any) | 100.0% |
| BUILDING A | Plinth | 100.0% |
| BUILDING A | Stilt Floor | 100.0% |
| BUILDING A | Slabs of Super Structure | 100.0% |
| BUILDING A | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 60.0% |
| BUILDING A | Sanitary Fittings within the flats / premises | 15.0% |
| BUILDING A | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90.0% |
| BUILDING A | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 40.0% |
| BUILDING A | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0.0% |
| BUILDING B | Excavation | 100.0% |
| BUILDING B | Basement (if any) | 100.0% |
| BUILDING B | Podiums (if any) | 100.0% |
| BUILDING B | Plinth | 100.0% |
| BUILDING B | Stilt Floor | 100.0% |
| BUILDING B | Slabs of Super Structure | 100.0% |
| BUILDING B | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 70.0% |
| BUILDING B | Sanitary Fittings within the flats / premises | 15.0% |
| BUILDING B | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 85.0% |
| BUILDING B | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 45.0% |
| BUILDING B | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0.0% |
| BUILDING C | Excavation | 100.0% |
| BUILDING C | Basement (if any) | 100.0% |
| BUILDING C | Podiums (if any) | 100.0% |
| BUILDING C | Plinth | 100.0% |
| BUILDING C | Stilt Floor | 100.0% |
| BUILDING C | Slabs of Super Structure | 85.0% |
| BUILDING C | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 40.0% |
| BUILDING C | Sanitary Fittings within the flats / premises | 10.0% |
| BUILDING C | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 70.0% |
| BUILDING C | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 30.0% |
| BUILDING C | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0.0% |
| BUILDING D | Excavation | 100.0% |
| BUILDING D | Basement (if any) | 100.0% |
| BUILDING D | Podiums (if any) | 100.0% |
| BUILDING D | Plinth | 100.0% |
| BUILDING D | Stilt Floor | 100.0% |
| BUILDING D | Slabs of Super Structure | 100.0% |
| BUILDING D | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 55.0% |
| BUILDING D | Sanitary Fittings within the flats / premises | 90.0% |
| BUILDING D | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 15.0% |
| BUILDING D | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 45.0% |
| BUILDING D | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0.0% |
MahaRERA project filing · read 18 July 2026 · registration P52100002391
| Revised target | Reason given by the builder |
|---|---|
| 9 August 2020 | To Chairman, Maharashtra Real Estate Regulatory Authority 10th August, 2019, Bandra, Mumbai. Subject: Application for Extension for Project Completion Date. Respected Sir/Ma’am, I, Pranay Shingi, Designated Partner in SSG Realty and Infra LLP, and promoter of Suburbia Estate Phase 1 having RERA registration No P52100002391, hereby apply for revision in project completion date. The erstwhile project completion date was 10th August, 2019, however the same seems to be unachievable due to reasons beyond our control such as: • Insufficient Cash Flow and shortage of Funds due to default in payments by Allottees of the project. • Non availability of Requisite Material. • Non availability of Skilled Labour. Further, as on date, the project is 50 % Complete (Appended is the Architect Certificate) We request that the revision in project completion date be made from 10th August, 2019 to 10th August, 2020. We assure that, we shall complete the project latest by 10th August, 2020, if not earlier. |
| 30 April 2023 | THE CONSTRUCTION WORK OF THE PROJECT IS 90% COMPLETED. ONLY FEW WORK IS PENDING DUE TO FORCE MAJEURE CIRCUMSTANCES. HENCE THE EXTENSION IS SOUGHT ONLY FOR 10 MONTHS TO COMPLETE THE PROJECT. |
| 22 February 2027 | 1. CONSTRUCTION OF THE SAID PROJECT IS 75% COMPLETED. WE NEED EXTENSION TO COMPLETE THE REMAINING CONSTRUCTION. 2. Extension applied till 22/02/2028 with 24.07% consent 3. Completion within 14 months already recorded & approved by HC (Order dt. 22/12/2025) 4. Present application is in compliance with HC order and RERA provisions |
MahaRERA project filing · read 18 July 2026 · registration P52100002391
RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.
| Filing | Own funds | Borrowing | Payments from buyers | Total |
|---|---|---|---|---|
| Estimated plan | ₹1,000,000 | ₹0 | ₹838,389,387 | ₹839,389,387 |
| Actual raised | ₹1,000,000 | ₹0 | ₹523,228,466 | ₹524,228,466 |
MahaRERA project filing · read 18 July 2026 · registration P52100002391
36 elapsed quarterly periods in the captured compliance schedule. Active default was recorded for FY 2025-2026.
MahaRERA project filing · read 18 July 2026 · registration P52100002391
A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.
MahaRERA project filing · read 18 July 2026 · registration P52100002391
Builder and past records
Projects registered under this company
2Pune registrations
These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.
MahaRERA Pune registration records · read 12 July 2026
Past records of sales and unsold homes
21 September 2026
65 marked unsold · 264 sold · 0 booked.
Saved MahaRERA home list
12 September 2026
65 marked unsold · 264 sold · 0 booked.
Saved MahaRERA home list
4 September 2026
65 marked unsold · 264 sold · 0 booked.
Saved MahaRERA home list
18 July 2026
65 marked unsold · 264 sold · 0 booked.
Saved MahaRERA home list
These dates show when the records were saved, not when homes were sold. Sales may have changed since then, even if the saved counts are the same.
Project Comparison Report
Compare up to three projects. We read their plans and RERA documents, recommend homes in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.
2 projects · ₹7,999
3 projects · ₹9,999
Within 1 working day
Didn’t help you decide? Full refund — no questions asked.
Compare project details for free →MahaRERA · registration record · read 12 July 2026
MahaRERA · per-home inventory · saved-file date 18 July 2026
This is a past RERA home list, not current availability. It does not give the date each home was sold.
The home-list date is based on the saved file’s details.
Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.
Open MahaRERA · search P52100002391 ↗