GAGAN LIFESPACE · P52100002941
For GAGAN NULIFE PHASE 2 (P52100002941), 29 of 129 entries were marked unsold in the MahaRERA home list dated 18 July 2026 (saved-file date).
MahaRERA · per-home inventory · saved-file date 18 July 2026
For GAGAN NULIFE PHASE 2, ₹7,407 per sq ft of carpet area is the median rate across 100 sold or booked entries with prices in the MahaRERA home list dated 18 July 2026 (saved-file date). These are historical agreement values, not current asking prices.
MahaRERA · per-home inventory · saved-file date 18 July 2026
These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.
Builder’s completion target
This target date has passed. The record shown here does not confirm whether the project is complete or has received more time.
Status shown on RERA
This is the status shown on RERA. It does not confirm an occupancy certificate or today’s construction progress.
Prices reported to RERA
₹7,407/ sq ft carpet area
Across 100 sold or booked entries with reported prices. The middle 80% of rates fall between ₹5,780 and ₹8,614.
MahaRERA · per-home inventory · saved-file date 18 July 2026
For each sold or booked entry, we divide the reported agreement value by its carpet area in square feet. The median is the middle rate when these rates are put in order. We show it only when at least five entries have prices. We exclude valuations of unsold homes and government reference rates. The figures may include different sizes and property types. They are historical agreement values, not current asking prices or the total cost including extra charges.
Sales Report
Compare reported agreement values by building, size and floor. See which homes were marked unsold on the date shown.
Inside this registered phase
129 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.
MahaRERA · per-home inventory · saved-file date 18 July 2026
Scroll sideways to see all columns.
| Filed building | Entries | Sold | Booked | Marked unsold | Other / unstated status | Recorded carpet-area range |
|---|---|---|---|---|---|---|
| C BUILDING | 129 | 92 | 8 | 29 | 0 | 35.45–37.64 sq m≈ 382–405 sq ft |
Different sizes are not necessarily different bedroom types. How we read and summarise the filing →
Unit Report
Understand its light, privacy, layout and surroundings. See how it compares with similar homes and other options in this project.
Didn’t help you decide? Full refund — no questions asked.
The same home number may appear in more than one building. Check both before choosing.
MahaRERA · per-home inventory · saved-file date 18 July 2026
| Home / building | Floor in the record | Carpet area | Reported status | Agreement value | Assess |
|---|---|---|---|---|---|
| 1001C BUILDING | 10 | 37.08 sq m≈ 399 sq ft | Booked | ₹2,785,446 | |
| 1002C BUILDING | 10 | 37.01 sq m≈ 398 sq ft | Sold | ₹3,372,800 | |
| 1003C BUILDING | 10 | 35.69 sq m≈ 384 sq ft | Booked | ₹3,343,392 | |
| 1004C BUILDING | 10 | 35.77 sq m≈ 385 sq ft | Sold | ₹2,383,680 | |
| 1005C BUILDING | 10 | 35.76 sq m≈ 385 sq ft | Sold | ₹2,383,680 | |
| 1006C BUILDING | 10 | 36.17 sq m≈ 389 sq ft | Sold | ₹2,433,600 | |
| 1007C BUILDING | 10 | 35.86 sq m≈ 386 sq ft | Sold | ₹1,928,784 | |
| 1008C BUILDING | 10 | 36.59 sq m≈ 394 sq ft | Marked unsold | Not stated | |
| 1009C BUILDING | 10 | 35.81 sq m≈ 385 sq ft | Marked unsold | Not stated | |
| 101C BUILDING | 1 | 37.09 sq m≈ 399 sq ft | Marked unsold | Not stated | |
| 1010C BUILDING | 10 | 37.58 sq m≈ 405 sq ft | Sold | ₹2,899,865 | |
| 1011C BUILDING | 10 | 37.64 sq m≈ 405 sq ft | Sold | ₹3,683,122 |
Read every entry in one table: Read the complete saved home list.
Choose the home you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.
More from the RERA documents
Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.
| Building | Activity | Reported |
|---|---|---|
| C BUILDING | Excavation | 100.0% |
| C BUILDING | Basement (if any) | 100.0% |
| C BUILDING | Podiums (if any) | 0.0% |
| C BUILDING | Plinth | 100.0% |
| C BUILDING | Stilt Floor | 100.0% |
| C BUILDING | Slabs of Super Structure | 100.0% |
| C BUILDING | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80.0% |
| C BUILDING | Sanitary Fittings within the flats / premises | 30.0% |
| C BUILDING | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90.0% |
| C BUILDING | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 95.0% |
| C BUILDING | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 20.0% |
MahaRERA project filing · read 18 July 2026 · registration P52100002941
| Revised target | Reason given by the builder |
|---|---|
| 31 December 2020 | Dear Sir, The project Gagan Nulife Phase 2 is registered with RERA Authority under Registration no P52100002941 on 04/10/2017 wherein, the date of completion of Gagan Nulife Phase 2 is declared as 31st December 2019. We have initiated booking in the said project in the month of August 2015 and proposes the customers to book the units in pre-launch offer. At the time of Launch, we got remarkable response from the customers wherein about 73 units were booked out of total 128 units. Looking to amazing response we registered the said project with RERA Authority & declared the date of completion as 31st December 2019 thereafter due to bad market conditions & diverse situations the customers were not keen to come forward for execution & registration of unit agreements, resulting till date we have registered only 29 unit Agreements. The result is that we being the Builder / Promoter facing huge financial problems therefore we are unable to Speed up the construction work on site. In addition to that we are in process to arrange our own funding for construction & completion of project which process will be time consuming therefore request you to grant us a reasonable extension for a period of one year & also request you to please accept our new completion date as 30th December 2020 |
| 31 March 2022 | The project is delayed due to Covid Pandemic & lockdown. The project is a senior Citizen project wherein all flats are allotted to only customers who are above 50 years of Age, As phase one is completed wherein around 200 families are residing & to take care of their safety precautions stay of labors on site was not allowed until there vaccinations drive was not carried out. This resulted in delay of construction activity of Phase 2 so now we are applying for extension upto 31/03/2022 with consent letters of Allottees |
| 30 June 2027 | The project is delayed due to Covid Pandemic & lockdown. The project is a senior Citizen project wherein all flats are allotted to only customers who are above 50 years of Age, As phase one is completed wherein around 200 families are residing & to take care of their safety precautions stay of labors on site was not allowed until there vaccinations drive was not carried out. This resulted in delay of construction activity of Phase 2 so now we are applying for extension upto 30/06/2027 with consent letters of Allottees |
MahaRERA project filing · read 18 July 2026 · registration P52100002941
RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.
| Filing | Own funds | Borrowing | Payments from buyers | Total |
|---|---|---|---|---|
| Estimated plan | ₹100,000,000 | ₹0 | ₹243,264,195 | ₹343,264,195 |
| Actual raised | ₹86,990,572 | ₹0 | ₹177,604,062 | ₹264,594,634 |
MahaRERA project filing · read 18 July 2026 · registration P52100002941
40 elapsed quarterly periods in the captured compliance schedule. Active default was recorded for FY 2025-2026.
MahaRERA project filing · read 18 July 2026 · registration P52100002941
A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.
MahaRERA project filing · read 18 July 2026 · registration P52100002941
Builder and past records
Projects registered under this company
5Pune registrations
These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.
MahaRERA Pune registration records · read 12 July 2026
Past records of sales and unsold homes
21 September 2026
29 marked unsold · 92 sold · 8 booked.
Saved MahaRERA home list
13 September 2026
29 marked unsold · 92 sold · 8 booked.
Saved MahaRERA home list
4 September 2026
29 marked unsold · 92 sold · 8 booked.
Saved MahaRERA home list
18 July 2026
29 marked unsold · 92 sold · 8 booked.
Saved MahaRERA home list
These dates show when the records were saved, not when homes were sold. Sales may have changed since then, even if the saved counts are the same.
Project Comparison Report
Compare up to three projects. We read their plans and RERA documents, recommend homes in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.
2 projects · ₹7,999
3 projects · ₹9,999
Within 1 working day
Didn’t help you decide? Full refund — no questions asked.
Compare project details for free →MahaRERA · registration record · read 12 July 2026
MahaRERA · per-home inventory · saved-file date 18 July 2026
This is a past RERA home list, not current availability. It does not give the date each home was sold.
The home-list date is based on the saved file’s details.
Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.
Open MahaRERA · search P52100002941 ↗