Buyer’s Report
Understand this project
Find homes to consider, with advice on light, layout, privacy and surroundings.
₹4,999
Builder’s RERA records,
explained for buyers.
The builder’s RERA record, explained
VARDAAN LIFESTYLE LIMITED · P52100003050
For CLEVELAND PARK (P52100003050), 31 of 92 entries were marked unsold in the MahaRERA home list dated 18 July 2026 (saved-file date).
MahaRERA · per-home inventory · saved-file date 18 July 2026
For CLEVELAND PARK, ₹8,050 per sq ft of carpet area is the median rate across 61 sold or booked entries with prices in the MahaRERA home list dated 18 July 2026 (saved-file date). These are historical agreement values, not current asking prices.
MahaRERA · per-home inventory · saved-file date 18 July 2026
These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.
Builder’s completion target
This target date has passed. The record shown here does not confirm whether the project is complete or has received more time.
Status shown on RERA
This is the status shown on RERA. It does not confirm an occupancy certificate or today’s construction progress.
Prices reported to RERA
₹8,050/ sq ft carpet area
Across 61 sold or booked entries with reported prices. The middle 80% of rates fall between ₹7,191 and ₹9,384.
MahaRERA · per-home inventory · saved-file date 18 July 2026
For each sold or booked entry, we divide the reported agreement value by its carpet area in square feet. The median is the middle rate when these rates are put in order. We show it only when at least five entries have prices. We exclude valuations of unsold homes and government reference rates. The figures may include different sizes and property types. They are historical agreement values, not current asking prices or the total cost including extra charges.
Sales Report
Compare reported agreement values by building, size and floor. See which homes were marked unsold on the date shown.
Inside this registered phase
92 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.
MahaRERA · per-home inventory · saved-file date 18 July 2026
Scroll sideways to see all columns.
| Filed building | Entries | Sold | Booked | Marked unsold | Other / unstated status | Recorded carpet-area range |
|---|---|---|---|---|---|---|
| WING A | 46 | 18 | 0 | 28 | 0 | 58.80–88.35 sq m≈ 633–951 sq ft |
| WING B | 46 | 43 | 0 | 3 | 0 | 53.01–88.35 sq m≈ 571–951 sq ft |
Different sizes are not necessarily different bedroom types. How we read and summarise the filing →
Unit Report
Understand its light, privacy, layout and surroundings. See how it compares with similar homes and other options in this project.
Didn’t help you decide? Full refund — no questions asked.
The same home number may appear in more than one building. Check both before choosing.
MahaRERA · per-home inventory · saved-file date 18 July 2026
| Home / building | Floor in the record | Carpet area | Reported status | Agreement value | Assess |
|---|---|---|---|---|---|
| A-1001WING A | 10 | 59.45 sq m≈ 640 sq ft | Sold | ₹5,351,125 | |
| A-1002WING A | 10 | 59.75 sq m≈ 643 sq ft | Sold | ₹5,242,500 | |
| A-1003WING A | 10 | 63.47 sq m≈ 683 sq ft | Marked unsold | Not stated | |
| A-1004WING A | 10 | 59.45 sq m≈ 640 sq ft | Marked unsold | Not stated | |
| A-101WING A | 1 | 63.09 sq m≈ 679 sq ft | Sold | ₹5,111,000 | |
| A-102WING A | 1 | 60.08 sq m≈ 647 sq ft | Marked unsold | Not stated | |
| A-1101WING A | 11 | 58.88 sq m≈ 634 sq ft | Marked unsold | Not stated | |
| A-1102WING A | 11 | 58.89 sq m≈ 634 sq ft | Marked unsold | Not stated | |
| A-1103WING A | 11 | 62.4 sq m≈ 672 sq ft | Marked unsold | Not stated | |
| A-1104WING A | 11 | 58.8 sq m≈ 633 sq ft | Marked unsold | Not stated | |
| A-201WING A | 2 | 61.22 sq m≈ 659 sq ft | Marked unsold | Not stated | |
| A-202WING A | 2 | 61.83 sq m≈ 666 sq ft | Marked unsold | Not stated |
Read every entry in one table: Read the complete saved home list.
Choose the home you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.
More from the RERA documents
₹45,452,584 of an estimated ₹45,452,584 was reported as incurred (100.0%). This percentage is about costs. It does not show how much construction is complete.
MahaRERA project filing · read 18 July 2026 · registration P52100003050
Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.
| Building | Activity | Reported |
|---|---|---|
| WING A | Excavation | 100.0% |
| WING A | Basement (if any) | 100.0% |
| WING A | Podiums (if any) | 0.0% |
| WING A | Plinth | 100.0% |
| WING A | Stilt Floor | 100.0% |
| WING A | Slabs of Super Structure | 100.0% |
| WING A | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100.0% |
| WING A | Sanitary Fittings within the flats / premises | 100.0% |
| WING A | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100.0% |
| WING A | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100.0% |
| WING A | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100.0% |
| WING B | Excavation | 100.0% |
| WING B | Basement (if any) | 100.0% |
| WING B | Podiums (if any) | 0.0% |
| WING B | Plinth | 100.0% |
| WING B | Stilt Floor | 100.0% |
| WING B | Slabs of Super Structure | 100.0% |
| WING B | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100.0% |
| WING B | Sanitary Fittings within the flats / premises | 100.0% |
| WING B | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100.0% |
| WING B | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100.0% |
| WING B | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100.0% |
MahaRERA project filing · read 18 July 2026 · registration P52100003050
| Revised target | Reason given by the builder |
|---|---|
| 30 December 2023 | We would like to bring to your notice that all the work for the project is completed. We have also obtained the various NOCs required for the application of the Occupation Certificate. We had applied for the Occupancy Certificate to the authorities. However, the same is not yet obtained and is still in the process. Due to this we are in dilemma we will not be able to obtain the Certificate before 31st December, 2022. Kindly grant extension till 30th December, 2023 |
| 16 October 2025 | We, Vardaan Lifestyle Limited, Promoter of the project “CLEVELAND PARK” bearing MahaRERA Registration No. P52100003050, respectfully submit this Explanatory Note in support of our application for extension of the project registration. We are pleased to inform the Authority that construction of Wing A and Wing B has been successfully completed in all respects. Further, we have obtained a Full Occupancy Certificate on 16-10-2025 from the competent Planning Authority It is important to clarify that although the Planning Authority has issued a Part OC for the larger layout, the same constitutes a Full OC for Wing A and Wing B, as these two wings form an integral part of a larger sanctioned layout comprising multiple buildings to be constructed in phases. The Part OC granted for the larger layout explicitly covers and certifies full completion and occupancy permission for Wing A and Wing B. Accordingly, Wing A and Wing B are fully completed and are deemed to have received Full OC. Consent from Allottees: We have obtained consent from 100% of the allottees, indicating their support for the extension request and the continuation of the project towards timely completion. Reason for Delay: The delay in completion has been due to unforeseen challenges, Despite these hurdles, we have maintained steady progress and are now in the final stages of the project. Request for Extension: In view of the above, we respectfully request an extension of the project completion timeline to ensure a smooth transition and timely delivery to our valued allottees. This extension will enable us to complete our project closure work on MahaRERA. |
MahaRERA project filing · read 18 July 2026 · registration P52100003050
RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.
| Filing | Own funds | Borrowing | Payments from buyers | Total |
|---|---|---|---|---|
| Estimated plan | ₹114,751,128 | ₹0 | ₹224,039,683 | ₹338,790,811 |
| Actual raised | ₹114,751,128 | ₹0 | ₹224,039,683 | ₹338,790,811 |
MahaRERA project filing · read 18 July 2026 · registration P52100003050
34 elapsed quarterly periods in the captured compliance schedule. No active quarterly default was recorded in this snapshot.
MahaRERA project filing · read 18 July 2026 · registration P52100003050
A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.
MahaRERA project filing · read 18 July 2026 · registration P52100003050
Builder and past records
Projects registered under this company
2Pune registrations
These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.
MahaRERA Pune registration records · read 2 July 2026 – 12 July 2026
Past records of sales and unsold homes
21 September 2026
31 marked unsold · 61 sold · 0 booked.
Saved MahaRERA home list
13 September 2026
31 marked unsold · 61 sold · 0 booked.
Saved MahaRERA home list
4 September 2026
31 marked unsold · 61 sold · 0 booked.
Saved MahaRERA home list
18 July 2026
31 marked unsold · 61 sold · 0 booked.
Saved MahaRERA home list
These dates show when the records were saved, not when homes were sold. Sales may have changed since then, even if the saved counts are the same.
More projects to explore
These projects list the same locality. They may differ in exact location, home type and price.
Mohammadwadi · Pune
P52100045561
11 of 162 entries marked unsold
MahaRERA · per-home inventory · read 9 September 2026
View project details →Mohammadwadi · Pune
P52100079657
93 of 93 entries marked unsold
MahaRERA · per-home inventory · saved-file date 18 July 2026
View project details →Mohammadwadi · Pune
P52100054947
13 of 98 entries marked unsold
MahaRERA · per-home inventory · read 11 September 2026
View project details →Project Comparison Report
Compare up to three projects. We read their plans and RERA documents, recommend homes in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.
2 projects · ₹7,999
3 projects · ₹9,999
Within 1 working day
Didn’t help you decide? Full refund — no questions asked.
Compare project details for free →MahaRERA · registration record · read 12 July 2026
MahaRERA · per-home inventory · saved-file date 18 July 2026
This is a past RERA home list, not current availability. It does not give the date each home was sold.
The home-list date is based on the saved file’s details.
Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.
Open MahaRERA · search P52100003050 ↗