Buyer’s Report
Understand this project
Find homes to consider, with advice on light, layout, privacy and surroundings.
₹4,999
Builder’s RERA records,
explained for buyers.
The builder’s RERA record, explained
SHIVMUDRA ENTERPRISES · P52100003198
For AMRUTVEL (P52100003198), 14 of 125 entries were marked unsold in the MahaRERA home list dated 18 July 2026 (saved-file date).
MahaRERA · per-home inventory · saved-file date 18 July 2026
For AMRUTVEL, ₹4,911 per sq ft of carpet area is the median rate across 58 sold or booked entries with prices in the MahaRERA home list dated 18 July 2026 (saved-file date). These are historical agreement values, not current asking prices.
MahaRERA · per-home inventory · saved-file date 18 July 2026
These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.
Builder’s completion target
The builder reported this target date. It is not a confirmed handover date.
Status shown on RERA
This is the status shown on RERA. It does not confirm an occupancy certificate or today’s construction progress.
Prices reported to RERA
₹4,911/ sq ft carpet area
Across 58 sold or booked entries with reported prices. The middle 80% of rates fall between ₹3,702 and ₹5,426.
MahaRERA · per-home inventory · saved-file date 18 July 2026
For each sold or booked entry, we divide the reported agreement value by its carpet area in square feet. The median is the middle rate when these rates are put in order. We show it only when at least five entries have prices. We exclude valuations of unsold homes and government reference rates. The figures may include different sizes and property types. They are historical agreement values, not current asking prices or the total cost including extra charges.
Sales Report
Compare reported agreement values by building, size and floor. See which homes were marked unsold on the date shown.
Inside this registered phase
125 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.
MahaRERA · per-home inventory · saved-file date 18 July 2026
Scroll sideways to see all columns.
| Filed building | Entries | Sold | Booked | Marked unsold | Other / unstated status | Recorded carpet-area range |
|---|---|---|---|---|---|---|
| AMRUTVEL | 125 | 58 | 0 | 14 | 53 | 9.10–55.19 sq m≈ 98–594 sq ft |
Different sizes are not necessarily different bedroom types. How we read and summarise the filing →
Unit Report
Understand its light, privacy, layout and surroundings. See how it compares with similar homes and other options in this project.
Didn’t help you decide? Full refund — no questions asked.
The same home number may appear in more than one building. Check both before choosing.
MahaRERA · per-home inventory · saved-file date 18 July 2026
| Home / building | Floor in the record | Carpet area | Reported status | Agreement value | Assess |
|---|---|---|---|---|---|
| Flat No.01AMRUTVEL | 202 | 29.84 sq m≈ 321 sq ft | Not for sale | Not stated | |
| Flat No.02AMRUTVEL | 202 | 45.3 sq m≈ 488 sq ft | Not for sale | Not stated | |
| Flat No.03AMRUTVEL | 202 | 45.3 sq m≈ 488 sq ft | Not for sale | Not stated | |
| Flat No.04AMRUTVEL | 202 | 55.19 sq m≈ 594 sq ft | Sold | ₹2,806,500 | |
| Flat No.05AMRUTVEL | 202 | 55.19 sq m≈ 594 sq ft | Sold | ₹2,247,000 | |
| Flat No.06AMRUTVEL | 202 | 45.3 sq m≈ 488 sq ft | Marked unsold | Not stated | |
| Flat No.07AMRUTVEL | 202 | 45.6 sq m≈ 491 sq ft | Marked unsold | Not stated | |
| Flat No.08AMRUTVEL | 202 | 29.84 sq m≈ 321 sq ft | Not for sale | Not stated | |
| Flat No.1001AMRUTVEL | 10 | 44.46 sq m≈ 479 sq ft | Not for sale | Not stated | |
| Flat No.1002AMRUTVEL | 10 | 45.3 sq m≈ 488 sq ft | Marked unsold | Not stated | |
| Flat No.1003AMRUTVEL | 10 | 45.3 sq m≈ 488 sq ft | Sold | ₹2,501,500 | |
| Flat No.1004AMRUTVEL | 10 | 55.19 sq m≈ 594 sq ft | Not for sale | Not stated |
Read every entry in one table: Read the complete saved home list.
Choose the home you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.
More from the RERA documents
₹137,500,000 of an estimated ₹140,000,000 was reported as incurred (98.2%). This percentage is about costs. It does not show how much construction is complete.
MahaRERA project filing · read 18 July 2026 · registration P52100003198
Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.
| Building | Activity | Reported |
|---|---|---|
| AMRUTVEL | Excavation | 100.0% |
| AMRUTVEL | Basement (if any) | 100.0% |
| AMRUTVEL | Podiums (if any) | 0.0% |
| AMRUTVEL | Plinth | 100.0% |
| AMRUTVEL | Stilt Floor | 100.0% |
| AMRUTVEL | Slabs of Super Structure | 100.0% |
| AMRUTVEL | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100.0% |
| AMRUTVEL | Sanitary Fittings within the flats / premises | 100.0% |
| AMRUTVEL | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100.0% |
| AMRUTVEL | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100.0% |
| AMRUTVEL | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100.0% |
MahaRERA project filing · read 18 July 2026 · registration P52100003198
| Revised target | Reason given by the builder |
|---|---|
| 31 March 2025 | Due to Covid and other issues, and also change in plans, the project need extension to complete. |
| 31 March 2026 | Dear Sir / madam, We are applying for Extension of project because some more time will required to complete the project because some legal issues took more time. |
| 31 March 2027 | 1. Justification for the Extension Request Majority of the construction work has been completed, Some work activities are pending and details are provided PERT Chart Below. The following events have severely hampered our construction workflow: a) Stop Work Circular Issued by Pimpri Chinchwad Municipal Corporation Due to Air Pollution (2 months Delay) The PCMC issued an official circular restricting construction activities during the month of November 2023 due to rising air pollution. This directive halted work on-site for a prolonged period, further affecting our project schedule, due to this daily wage workers went to their native villages as there was no clarity when the work would resume. b) Stone Crusher Association Strike (2 months delay). Due to a strike by the Stone Crusher Association during the month of June 2024, there has been a severe shortage of essential raw materials such as sand and aggregates, which are crucial for construction activities. The disruption in the supply chain has resulted in significant delays resulting in unavailability of ready mix concrete for our slab work. c) Dengue Outbreak at out site. (4 months delay) A widespread dengue outbreak at our site led to an alarming number of laborers falling ill. As a result, a large section of our workforce left for their hometowns as they could not afford treatment here, causing a severe labor shortage and slowing down progress considerably. Some workers had to be admitted to hospitals. d) Road Widening Issues: Part of our project land was impacted by road widening, leading to delays in obtaining final sanctions. The government issued Transferable Development Rights (TDR) as compensation for the land acquired for road widening. We utilized the TDR and subsequently applied for full/revised sanction, which took approximately six months to complete. This procedural delay further impacted the project's timeline. |
MahaRERA project filing · read 18 July 2026 · registration P52100003198
RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.
| Filing | Own funds | Borrowing | Payments from buyers | Total |
|---|---|---|---|---|
| Estimated plan | ₹89,950,000 | ₹0 | ₹0 | ₹89,950,000 |
| Actual raised | ₹27,273,191 | ₹0 | ₹133,407,266 | ₹160,680,457 |
MahaRERA project filing · read 18 July 2026 · registration P52100003198
35 elapsed quarterly periods in the captured compliance schedule. No active quarterly default was recorded in this snapshot.
MahaRERA project filing · read 18 July 2026 · registration P52100003198
A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.
MahaRERA project filing · read 18 July 2026 · registration P52100003198
Builder and past records
Projects registered under this company
1Pune registrations
These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.
MahaRERA Pune registration records · read 12 July 2026
Past records of sales and unsold homes
21 September 2026
14 marked unsold · 58 sold · 0 booked.
Saved MahaRERA home list
13 September 2026
14 marked unsold · 58 sold · 0 booked.
Saved MahaRERA home list
4 September 2026
14 marked unsold · 58 sold · 0 booked.
Saved MahaRERA home list
18 July 2026
14 marked unsold · 58 sold · 0 booked.
Saved MahaRERA home list
These dates show when the records were saved, not when homes were sold. Sales may have changed since then, even if the saved counts are the same.
Project Comparison Report
Compare up to three projects. We read their plans and RERA documents, recommend homes in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.
2 projects · ₹7,999
3 projects · ₹9,999
Within 1 working day
Didn’t help you decide? Full refund — no questions asked.
Compare project details for free →MahaRERA · registration record · read 12 July 2026
MahaRERA · per-home inventory · saved-file date 18 July 2026
This is a past RERA home list, not current availability. It does not give the date each home was sold.
The home-list date is based on the saved file’s details.
Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.
Open MahaRERA · search P52100003198 ↗