Buyer’s Report
Understand this project
Find homes to consider, with advice on light, layout, privacy and surroundings.
₹4,999
Builder’s RERA records,
explained for buyers.
The builder’s RERA record, explained
Akash Developers · P52100003510
For GAGAN SOUTHCODE (P52100003510), 104 of 137 entries were marked unsold in the MahaRERA home list dated 18 July 2026 (saved-file date).
MahaRERA · per-home inventory · saved-file date 18 July 2026
For GAGAN SOUTHCODE, ₹10,936 per sq ft of carpet area is the median rate across 33 sold or booked entries with prices in the MahaRERA home list dated 18 July 2026 (saved-file date). These are historical agreement values, not current asking prices.
MahaRERA · per-home inventory · saved-file date 18 July 2026
These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.
Builder’s completion target
This target date has passed. The record shown here does not confirm whether the project is complete or has received more time.
Status shown on RERA
This is the status shown on RERA. It does not confirm an occupancy certificate or today’s construction progress.
Prices reported to RERA
₹10,936/ sq ft carpet area
Across 33 sold or booked entries with reported prices. The middle 80% of rates fall between ₹6,747 and ₹19,145.
MahaRERA · per-home inventory · saved-file date 18 July 2026
For each sold or booked entry, we divide the reported agreement value by its carpet area in square feet. The median is the middle rate when these rates are put in order. We show it only when at least five entries have prices. We exclude valuations of unsold homes and government reference rates. The figures may include different sizes and property types. They are historical agreement values, not current asking prices or the total cost including extra charges.
Sales Report
Compare reported agreement values by building, size and floor. See which homes were marked unsold on the date shown.
Inside this registered phase
137 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.
MahaRERA · per-home inventory · saved-file date 18 July 2026
Scroll sideways to see all columns.
| Filed building | Entries | Sold | Booked | Marked unsold | Other / unstated status | Recorded carpet-area range |
|---|---|---|---|---|---|---|
| GAGAN SOUTHCODE | 137 | 0 | 33 | 104 | 0 | 14.34–119.66 sq m≈ 154–1,288 sq ft |
Different sizes are not necessarily different bedroom types. How we read and summarise the filing →
Unit Report
Understand its light, privacy, layout and surroundings. See how it compares with similar homes and other options in this project.
Didn’t help you decide? Full refund — no questions asked.
The same home number may appear in more than one building. Check both before choosing.
MahaRERA · per-home inventory · saved-file date 18 July 2026
| Home / building | Floor in the record | Carpet area | Reported status | Agreement value | Assess |
|---|---|---|---|---|---|
| 1GAGAN SOUTHCODE | 205 | 44.31 sq m≈ 477 sq ft | Booked | ₹4,776,517 | |
| 10GAGAN SOUTHCODE | 205 | 27.38 sq m≈ 295 sq ft | Marked unsold | Not stated | |
| 101GAGAN SOUTHCODE | 1 | 61.86 sq m≈ 666 sq ft | Marked unsold | Not stated | |
| 102GAGAN SOUTHCODE | 1 | 27.38 sq m≈ 295 sq ft | Marked unsold | Not stated | |
| 103GAGAN SOUTHCODE | 1 | 27.38 sq m≈ 295 sq ft | Marked unsold | Not stated | |
| 104GAGAN SOUTHCODE | 1 | 27.38 sq m≈ 295 sq ft | Marked unsold | Not stated | |
| 105GAGAN SOUTHCODE | 1 | 27.38 sq m≈ 295 sq ft | Marked unsold | Not stated | |
| 106GAGAN SOUTHCODE | 1 | 27.38 sq m≈ 295 sq ft | Marked unsold | Not stated | |
| 107GAGAN SOUTHCODE | 1 | 27.38 sq m≈ 295 sq ft | Marked unsold | Not stated | |
| 108GAGAN SOUTHCODE | 1 | 26.25 sq m≈ 283 sq ft | Marked unsold | Not stated | |
| 109GAGAN SOUTHCODE | 1 | 55.88 sq m≈ 601 sq ft | Marked unsold | Not stated | |
| 11GAGAN SOUTHCODE | 205 | 32.51 sq m≈ 350 sq ft | Booked | ₹4,875,000 |
Read every entry in one table: Read the complete saved home list.
Choose the home you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.
More from the RERA documents
Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.
| Building | Activity | Reported |
|---|---|---|
| GAGAN SOUTHCODE | Excavation | 92.0% |
| GAGAN SOUTHCODE | Basement (if any) | 70.0% |
| GAGAN SOUTHCODE | Podiums (if any) | 0.0% |
| GAGAN SOUTHCODE | Plinth | 70.0% |
| GAGAN SOUTHCODE | Stilt Floor | 50.0% |
| GAGAN SOUTHCODE | Slabs of Super Structure | 80.0% |
| GAGAN SOUTHCODE | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 74.0% |
| GAGAN SOUTHCODE | Sanitary Fittings within the flats / premises | 0.0% |
| GAGAN SOUTHCODE | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 15.0% |
| GAGAN SOUTHCODE | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 50.0% |
| GAGAN SOUTHCODE | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 25.0% |
MahaRERA project filing · read 18 July 2026 · registration P52100003510
| Revised target | Reason given by the builder |
|---|---|
| 30 March 2021 | On Account of varied reasons at different points of time during the tenure of the project such as: a. Non- availability or limited supply of steel, other building material, water or electric supply. b. Any notice, order, rule, notification of the Government and/or other public or competent authority/court c. Delay in grant of any NOC/permission/license connection installation of any services such as lifts, electricity & water connections & meters to the scheme/unit/road NOC or completion certificate from Appropriate Authority the Owners/Promoters having complied with all requirements. d. Delay by local authority in issuing or granting necessary plinth checking completion or Occupation Certificate, the Owners/Promoters having complied with all requirements. e. Force majeure causes or other reasons beyond the control of the Promoters. |
| 31 March 2024 | Reason for Extension: On Account of varied reasons at different points of time during the tenure of the project such as: a. Non- availability or limited supply of steel, other building material, water or electric supply. b. Delay on the part of the Local Authority or any other Public Body or Authority including the M.S.E.D.C.L, in issuing or granting necessary Certificates / Noc’s / Permissions / Licenses / Connections of any service such as Electricity, Drains and Water Connections and Meters to the said Project under construction by the Promoters on the said Land. c. Compliances with the changes by the Rules & Regulations of Competent Authority and obtaining certificates relating thereto and compliance of the same. d. Delay or default in payment of dues by some of the Allottee’s. e. Force majeure causes or other reasons beyond the control of the Promoters. f. Due to Govt Restrictions/ Stoppage of work due to Covid 19 Pandemic. |
MahaRERA project filing · read 18 July 2026 · registration P52100003510
RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.
| Filing | Own funds | Borrowing | Payments from buyers | Total |
|---|---|---|---|---|
| Estimated plan | ₹100,000,000 | ₹0 | ₹157,787,000 | ₹257,787,000 |
| Actual raised | ₹123,189,197 | ₹0 | ₹128,950,350 | ₹252,139,547 |
MahaRERA project filing · read 18 July 2026 · registration P52100003510
27 elapsed quarterly periods in the captured compliance schedule. No active quarterly default was recorded in this snapshot.
MahaRERA project filing · read 18 July 2026 · registration P52100003510
A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.
MahaRERA project filing · read 18 July 2026 · registration P52100003510
Builder and past records
Projects registered under this company
1Pune registrations
These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.
MahaRERA Pune registration records · read 12 July 2026
Past records of sales and unsold homes
21 September 2026
104 marked unsold · 0 sold · 33 booked.
Saved MahaRERA home list
13 September 2026
104 marked unsold · 0 sold · 33 booked.
Saved MahaRERA home list
4 September 2026
104 marked unsold · 0 sold · 33 booked.
Saved MahaRERA home list
18 July 2026
104 marked unsold · 0 sold · 33 booked.
Saved MahaRERA home list
These dates show when the records were saved, not when homes were sold. Sales may have changed since then, even if the saved counts are the same.
More projects to explore
These projects list the same locality. They may differ in exact location, home type and price.
Kondhwa · Pune
P52100005703
112 of 168 entries marked unsold
MahaRERA · per-home inventory · saved-file date 18 July 2026
View project details →Kondhwa · Pune
P52100052556
79 of 318 entries marked unsold
MahaRERA · per-home inventory · saved-file date 18 July 2026
View project details →Kondhwa · Pune
P52100023863
19 of 104 entries marked unsold
MahaRERA · per-home inventory · saved-file date 18 July 2026
View project details →Project Comparison Report
Compare up to three projects. We read their plans and RERA documents, recommend homes in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.
2 projects · ₹7,999
3 projects · ₹9,999
Within 1 working day
Didn’t help you decide? Full refund — no questions asked.
Compare project details for free →MahaRERA · registration record · read 12 July 2026
MahaRERA · per-home inventory · saved-file date 18 July 2026
This is a past RERA home list, not current availability. It does not give the date each home was sold.
The home-list date is based on the saved file’s details.
Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.
Open MahaRERA · search P52100003510 ↗