The builder’s RERA record, explained
LANDSCAPE REALITY · P52100006401
For ANANTSRISHTI PHASE I (P52100006401), 1 of 123 entries were marked unsold in the MahaRERA home list read 19 July 2026.
These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.
Builder’s completion target
This target date has passed. The record shown here does not confirm whether the project is complete or has received more time.
Status shown on RERA
This is the status shown on RERA. It does not confirm an occupancy certificate or today’s construction progress.
Inside this registered phase
123 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.
MahaRERA · per-home inventory · read 19 July 2026
Scroll sideways to see all columns.
| Filed building | Entries | Sold | Booked | Marked unsold | Other / unstated status | Recorded carpet-area range |
|---|---|---|---|---|---|---|
| NA plots | 123 | 122 | 0 | 1 | 0 | 66.15–171.34 sq m≈ 712–1,844 sq ft |
Different sizes are not necessarily different bedroom types. How we read and summarise the filing →
Unit Report
Understand its light, privacy, layout and surroundings. See how it compares with similar homes and other options in this project.
Didn’t help you decide? Full refund — no questions asked.
The same home number may appear in more than one building. Check both before choosing.
MahaRERA · per-home inventory · read 19 July 2026
| Home / building | Floor in the record | Carpet area | Reported status | Agreement value | Assess |
|---|---|---|---|---|---|
| NA plots | 102.76 sq m≈ 1,106 sq ft | Sold | Not stated | ||
| NA plots | 82.35 sq m≈ 886 sq ft | Sold | Not stated | ||
| NA plots | 66.15 sq m≈ 712 sq ft | Sold | Not stated | ||
| NA plots | 102.76 sq m≈ 1,106 sq ft | Sold | Not stated | ||
| NA plots | 82.35 sq m≈ 886 sq ft | Sold | Not stated | ||
| NA plots | 66.15 sq m≈ 712 sq ft | Sold | Not stated | ||
| NA plots | 102.76 sq m≈ 1,106 sq ft | Sold | Not stated | ||
| NA plots | 82.35 sq m≈ 886 sq ft | Sold | Not stated | ||
| NA plots | 66.15 sq m≈ 712 sq ft | Sold | Not stated | ||
| NA plots | 171.34 sq m≈ 1,844 sq ft | Sold | Not stated | ||
| NA plots | 102.76 sq m≈ 1,106 sq ft | Sold | Not stated | ||
| NA plots | 82.35 sq m≈ 886 sq ft | Sold | Not stated |
Read every entry in one table: Read the complete saved home list.
Choose the home you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.
More from the RERA documents
Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.
| Building | Activity | Reported |
|---|---|---|
| H WING | Excavation | 100.0% |
| H WING | Basement (if any) | 100.0% |
| H WING | Podiums (if any) | 100.0% |
| H WING | Plinth | 100.0% |
| H WING | Stilt Floor | 100.0% |
| H WING | Slabs of Super Structure | 100.0% |
| H WING | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100.0% |
| H WING | Sanitary Fittings within the flats / premises | 100.0% |
| H WING | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100.0% |
| H WING | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100.0% |
| H WING | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100.0% |
| I WING | Excavation | 100.0% |
| I WING | Basement (if any) | 100.0% |
| I WING | Podiums (if any) | 100.0% |
| I WING | Plinth | 100.0% |
| I WING | Stilt Floor | 100.0% |
| I WING | Slabs of Super Structure | 100.0% |
| I WING | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100.0% |
| I WING | Sanitary Fittings within the flats / premises | 100.0% |
| I WING | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100.0% |
| I WING | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100.0% |
| I WING | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100.0% |
| J WING | Excavation | 100.0% |
| J WING | Basement (if any) | 100.0% |
| J WING | Podiums (if any) | 100.0% |
| J WING | Plinth | 100.0% |
| J WING | Stilt Floor | 100.0% |
| J WING | Slabs of Super Structure | 100.0% |
| J WING | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100.0% |
| J WING | Sanitary Fittings within the flats / premises | 100.0% |
| J WING | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100.0% |
| J WING | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100.0% |
| J WING | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100.0% |
| Q WING | Excavation | 100.0% |
| Q WING | Basement (if any) | 100.0% |
| Q WING | Podiums (if any) | 100.0% |
| Q WING | Plinth | 100.0% |
| Q WING | Stilt Floor | 100.0% |
| Q WING | Slabs of Super Structure | 100.0% |
| Q WING | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100.0% |
| Q WING | Sanitary Fittings within the flats / premises | 100.0% |
| Q WING | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100.0% |
| Q WING | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100.0% |
| Q WING | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100.0% |
| K WING | Excavation | 100.0% |
| K WING | Basement (if any) | 100.0% |
| K WING | Podiums (if any) | 100.0% |
| K WING | Plinth | 100.0% |
| K WING | Stilt Floor | 100.0% |
| K WING | Slabs of Super Structure | 100.0% |
| K WING | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100.0% |
| K WING | Sanitary Fittings within the flats / premises | 100.0% |
| K WING | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100.0% |
| K WING | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100.0% |
| K WING | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100.0% |
| P WING | Excavation | 100.0% |
| P WING | Basement (if any) | 100.0% |
| P WING | Podiums (if any) | 100.0% |
| P WING | Plinth | 100.0% |
| P WING | Stilt Floor | 100.0% |
| P WING | Slabs of Super Structure | 100.0% |
| P WING | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100.0% |
| P WING | Sanitary Fittings within the flats / premises | 100.0% |
| P WING | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100.0% |
| P WING | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100.0% |
| P WING | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100.0% |
| C TYPE ROW HOUSE | Excavation | 100.0% |
| C TYPE ROW HOUSE | Basement (if any) | 100.0% |
| C TYPE ROW HOUSE | Podiums (if any) | 100.0% |
| C TYPE ROW HOUSE | Plinth | 100.0% |
| C TYPE ROW HOUSE | Stilt Floor | 100.0% |
| C TYPE ROW HOUSE | Slabs of Super Structure | 100.0% |
| C TYPE ROW HOUSE | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100.0% |
| C TYPE ROW HOUSE | Sanitary Fittings within the flats / premises | 100.0% |
| C TYPE ROW HOUSE | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100.0% |
| C TYPE ROW HOUSE | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100.0% |
| C TYPE ROW HOUSE | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100.0% |
| D TYPE ROW HOUSE | Excavation | 100.0% |
| D TYPE ROW HOUSE | Basement (if any) | 100.0% |
| D TYPE ROW HOUSE | Podiums (if any) | 100.0% |
| D TYPE ROW HOUSE | Plinth | 100.0% |
| D TYPE ROW HOUSE | Stilt Floor | 100.0% |
| D TYPE ROW HOUSE | Slabs of Super Structure | 100.0% |
| D TYPE ROW HOUSE | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100.0% |
| D TYPE ROW HOUSE | Sanitary Fittings within the flats / premises | 100.0% |
| D TYPE ROW HOUSE | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100.0% |
| D TYPE ROW HOUSE | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100.0% |
| D TYPE ROW HOUSE | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100.0% |
MahaRERA project filing · read 19 July 2026 · registration P52100006401
| Revised target | Reason given by the builder |
|---|---|
| 30 March 2020 | Dear Sir / Madam, We, landscape Realty are developing residential and commercial project, Anantsrishti at village Jambhul, Gat no. 404 and 387, Taluka Maval, District Pune, PMRDA, Pune 412106 and we were due to complete the project on 31st March 2019. We hereby submit that since last 4-5 months we were not getting adequate labour on our site mentioned above. Due to shortage of required labour we were not able to attain expected construction within time as a result of which our project was delayed. We hereby state that we are now overcoming the difficulty and have resumed construction activity in the said project. We are however worried that we will not be able to complete the project and obtain completion certificate from appropriate authority till agreed date of completion of project. Therefore, we request you to extend the date of completion of said project from 31st March 2019 to 15th March 2020 therefrom. We will be handing over the possession to Flat Buyers once the Occupancy certificate is received. Hence, we request you to kindly allow us an extension of 11 months 15 days till 15thMarch 2020 for completion of the project. |
MahaRERA project filing · read 19 July 2026 · registration P52100006401
13 elapsed quarterly periods in the captured compliance schedule. No active quarterly default was recorded in this snapshot.
MahaRERA project filing · read 19 July 2026 · registration P52100006401
A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.
MahaRERA project filing · read 19 July 2026 · registration P52100006401
Builder and past records
Projects registered under this company
3Pune registrations
These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.
MahaRERA Pune registration records · read 12 July 2026
Past records of sales and unsold homes
19 July 2026
1 marked unsold · 122 sold · 0 booked.
Saved MahaRERA home list
These dates show when the records were saved, not when homes were sold. Sales may have changed since then, even if the saved counts are the same.
More projects to explore
These projects list the same locality. They may differ in exact location, home type and price.
Jambhul · Pune
PP1261012500744
227 of 227 entries marked unsold
MahaRERA · per-home inventory · read 19 July 2026
View project details →Project Comparison Report
Compare up to three projects. We read their plans and RERA documents, recommend homes in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.
2 projects · ₹7,999
3 projects · ₹9,999
Within 1 working day
Didn’t help you decide? Full refund — no questions asked.
Compare project details for free →MahaRERA · registration record · read 12 July 2026
MahaRERA · per-home inventory · read 19 July 2026
This is a past RERA home list, not current availability. It does not give the date each home was sold.
Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.
Open MahaRERA · search P52100006401 ↗