The builder’s RERA record, explained
AKASH ENTERPRISES · P52100007353
For SUNRISE CITY (P52100007353), 111 of 196 entries were marked unsold in the MahaRERA home list dated 18 July 2026 (saved-file date).
MahaRERA · per-home inventory · saved-file date 18 July 2026
For SUNRISE CITY, ₹4,010 per sq ft of carpet area is the median rate across 85 sold or booked entries with prices in the MahaRERA home list dated 18 July 2026 (saved-file date). These are historical agreement values, not current asking prices.
MahaRERA · per-home inventory · saved-file date 18 July 2026
These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.
Builder’s completion target
This target date has passed. The record shown here does not confirm whether the project is complete or has received more time.
Status shown on RERA
This is the status shown on RERA. It does not confirm an occupancy certificate or today’s construction progress.
Prices reported to RERA
₹4,010/ sq ft carpet area
Across 85 sold or booked entries with reported prices. The middle 80% of rates fall between ₹3,090 and ₹7,026.
MahaRERA · per-home inventory · saved-file date 18 July 2026
For each sold or booked entry, we divide the reported agreement value by its carpet area in square feet. The median is the middle rate when these rates are put in order. We show it only when at least five entries have prices. We exclude valuations of unsold homes and government reference rates. The figures may include different sizes and property types. They are historical agreement values, not current asking prices or the total cost including extra charges.
Sales Report
Compare reported agreement values by building, size and floor. See which homes were marked unsold on the date shown.
Inside this registered phase
196 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.
MahaRERA · per-home inventory · saved-file date 18 July 2026
Scroll sideways to see all columns.
| Filed building | Entries | Sold | Booked | Marked unsold | Other / unstated status | Recorded carpet-area range |
|---|---|---|---|---|---|---|
| A BUILDING | 75 | 44 | 0 | 31 | 0 | 16.54–43.01 sq m≈ 178–463 sq ft |
| B BUILDING | 75 | 41 | 0 | 34 | 0 | 16.54–39.30 sq m≈ 178–423 sq ft |
| C BUILDING | 46 | 0 | 0 | 46 | 0 | 36.69–36.72 sq m≈ 395–395 sq ft |
Different sizes are not necessarily different bedroom types. How we read and summarise the filing →
Unit Report
Understand its light, privacy, layout and surroundings. See how it compares with similar homes and other options in this project.
Didn’t help you decide? Full refund — no questions asked.
The same home number may appear in more than one building. Check both before choosing.
MahaRERA · per-home inventory · saved-file date 18 July 2026
| Home / building | Floor in the record | Carpet area | Reported status | Agreement value | Assess |
|---|---|---|---|---|---|
| 1A BUILDING | 205 | 22.48 sq m≈ 242 sq ft | Sold | ₹1,171,000 | |
| 1A BUILDING | 205 | 22.11 sq m≈ 238 sq ft | Sold | ₹1,380,212 | |
| 10A BUILDING | 205 | 22.48 sq m≈ 242 sq ft | Marked unsold | Not stated | |
| 11A BUILDING | 205 | 22.48 sq m≈ 242 sq ft | Marked unsold | Not stated | |
| 12A BUILDING | 205 | 22.48 sq m≈ 242 sq ft | Sold | ₹1,403,934 | |
| 13A BUILDING | 205 | 22.48 sq m≈ 242 sq ft | Sold | ₹1,403,934 | |
| 14A BUILDING | 205 | 23.32 sq m≈ 251 sq ft | Sold | ₹1,455,746 | |
| 15A BUILDING | 205 | 16.54 sq m≈ 178 sq ft | Marked unsold | Not stated | |
| 16A BUILDING | 205 | 16.54 sq m≈ 178 sq ft | Sold | ₹1,258,900 | |
| 17A BUILDING | 205 | 23.32 sq m≈ 251 sq ft | Marked unsold | Not stated | |
| 18A BUILDING | 205 | 16.54 sq m≈ 178 sq ft | Marked unsold | Not stated | |
| 19A BUILDING | 205 | 23.32 sq m≈ 251 sq ft | Marked unsold | Not stated |
Read every entry in one table: Read the complete saved home list.
Choose the home you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.
More from the RERA documents
₹121,067,525 of an estimated ₹176,391,500 was reported as incurred (68.6%). This percentage is about costs. It does not show how much construction is complete.
MahaRERA project filing · read 18 July 2026 · registration P52100007353
Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.
| Building | Activity | Reported |
|---|---|---|
| A BUILDING | Excavation | 100.0% |
| A BUILDING | Basement (if any) | 100.0% |
| A BUILDING | Podiums (if any) | 100.0% |
| A BUILDING | Plinth | 100.0% |
| A BUILDING | Stilt Floor | 100.0% |
| A BUILDING | Slabs of Super Structure | 100.0% |
| A BUILDING | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100.0% |
| A BUILDING | Sanitary Fittings within the flats / premises | 100.0% |
| A BUILDING | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100.0% |
| A BUILDING | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100.0% |
| A BUILDING | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100.0% |
| B BUILDING | Excavation | 100.0% |
| B BUILDING | Basement (if any) | 100.0% |
| B BUILDING | Podiums (if any) | 100.0% |
| B BUILDING | Plinth | 100.0% |
| B BUILDING | Stilt Floor | 100.0% |
| B BUILDING | Slabs of Super Structure | 100.0% |
| B BUILDING | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100.0% |
| B BUILDING | Sanitary Fittings within the flats / premises | 100.0% |
| B BUILDING | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100.0% |
| B BUILDING | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100.0% |
| B BUILDING | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100.0% |
| C BUILDING | Excavation | 100.0% |
| C BUILDING | Basement (if any) | 0.0% |
| C BUILDING | Podiums (if any) | 0.0% |
| C BUILDING | Plinth | 0.0% |
| C BUILDING | Stilt Floor | 0.0% |
| C BUILDING | Slabs of Super Structure | 0.0% |
| C BUILDING | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0.0% |
| C BUILDING | Sanitary Fittings within the flats / premises | 0.0% |
| C BUILDING | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0.0% |
| C BUILDING | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0.0% |
| C BUILDING | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0.0% |
MahaRERA project filing · read 18 July 2026 · registration P52100007353
| Revised target | Reason given by the builder |
|---|---|
| 1 May 2023 | Respected Sir /Madam, The project development work of the project ‘SUNRISE CITY’ is underway and we are leaving no stone unturned to finish the project work at the earliest but due to various reasons and adverse circumstances we are unable to complete the project by 01/05/2022. We have done the revised estimate of time required for completion and we are confident to complete the project by 01/05/2023. Following are some of the important reasons for delay of SUNRISE CITY project. a. The Covid 19 Virus has caused a major disruption in the entire economy and the real estate sector is worst affected among all. The site development work had gone sand still for more than 6-8 months. b. We were facing various challenges including non receipt progress payments from customers, shortage of labour and essential raw material, and fear in the minds of staff members due to rising cases of Covid 19 in Pune etc. c. Due to factors discussed in above there has been a delay in completion of the project. d. We are confident that in all possibility we will be able to complete the project by 01/05/2023. You are requested to kindly grant an extension for registration till 01/05/2023 and oblige. Thank You |
| 1 May 2024 | We seek extension for the project for one year due to delay in construction activities. We have obtained consent of majority of sold apartment owners. Request you to grant the extension at earliest. We would be committed to finish the project within the extended due date of completion. With this application, we have attached consent of allottees, Form B duly notarized with updated Date of completion and other documents for your reference. Request you to go through the same and approve the extension |
| 30 September 2025 | We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges, delays in obtaining the Occupancy Certificate (OC), and temporary financial constraints. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. We are closely monitoring progress and taking all necessary steps to ensure timely completion. Given the circumstances, we kindly request an extension until 30th September 2025 to complete the project and fulfil all regulatory requirements |
| 31 March 2026 | We are currently unable to secure the Full Occupancy Certificate (OC) for the project owing to the pending issuance of the Lift No Objection Certificate (NOC) from the relevant department. This outstanding clearance has resulted in a delay in project completion. Therefore, the promoter respectfully requests an extension of the project timeline to accommodate the resolution of this matter. |
MahaRERA project filing · read 18 July 2026 · registration P52100007353
34 elapsed quarterly periods in the captured compliance schedule. No active quarterly default was recorded in this snapshot.
MahaRERA project filing · read 18 July 2026 · registration P52100007353
A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.
MahaRERA project filing · read 18 July 2026 · registration P52100007353
Builder and past records
Projects registered under this company
1Pune registrations
These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.
MahaRERA Pune registration records · read 12 July 2026
Past records of sales and unsold homes
22 September 2026
111 marked unsold · 85 sold · 0 booked.
Saved MahaRERA home list
13 September 2026
111 marked unsold · 85 sold · 0 booked.
Saved MahaRERA home list
4 September 2026
111 marked unsold · 85 sold · 0 booked.
Saved MahaRERA home list
18 July 2026
111 marked unsold · 85 sold · 0 booked.
Saved MahaRERA home list
These dates show when the records were saved, not when homes were sold. Sales may have changed since then, even if the saved counts are the same.
Project Comparison Report
Compare up to three projects. We read their plans and RERA documents, recommend homes in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.
2 projects · ₹7,999
3 projects · ₹9,999
Within 1 working day
Didn’t help you decide? Full refund — no questions asked.
Compare project details for free →MahaRERA · registration record · read 12 July 2026
MahaRERA · per-home inventory · saved-file date 18 July 2026
This is a past RERA home list, not current availability. It does not give the date each home was sold.
The home-list date is based on the saved file’s details.
Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.