Buyer’s Report
Understand this project
Find homes to consider, with advice on light, layout, privacy and surroundings.
₹4,999
Builder’s RERA records,
explained for buyers.
The builder’s RERA record, explained
Vilas Tukaram Wadghule · P52100007646
For Sai Shawas (P52100007646), 30 of 198 entries were marked unsold in the MahaRERA home list dated 18 July 2026 (saved-file date).
MahaRERA · per-home inventory · saved-file date 18 July 2026
For Sai Shawas, ₹4,902 per sq ft of carpet area is the median rate across 168 sold or booked entries with prices in the MahaRERA home list dated 18 July 2026 (saved-file date). These are historical agreement values, not current asking prices.
MahaRERA · per-home inventory · saved-file date 18 July 2026
These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.
Builder’s completion target
The builder reported this target date. It is not a confirmed handover date.
Status shown on RERA
This is the status shown on RERA. It does not confirm an occupancy certificate or today’s construction progress.
Prices reported to RERA
₹4,902/ sq ft carpet area
Across 168 sold or booked entries with reported prices. The middle 80% of rates fall between ₹3,333 and ₹6,337.
MahaRERA · per-home inventory · saved-file date 18 July 2026
For each sold or booked entry, we divide the reported agreement value by its carpet area in square feet. The median is the middle rate when these rates are put in order. We show it only when at least five entries have prices. We exclude valuations of unsold homes and government reference rates. The figures may include different sizes and property types. They are historical agreement values, not current asking prices or the total cost including extra charges.
Sales Report
Compare reported agreement values by building, size and floor. See which homes were marked unsold on the date shown.
Inside this registered phase
198 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.
MahaRERA · per-home inventory · saved-file date 18 July 2026
Scroll sideways to see all columns.
| Filed building | Entries | Sold | Booked | Marked unsold | Other / unstated status | Recorded carpet-area range |
|---|---|---|---|---|---|---|
| WING A | 63 | 38 | 0 | 25 | 0 | 41.94–58.53 sq m≈ 451–630 sq ft |
| Wing B | 56 | 56 | 0 | 0 | 0 | 41.94–58.53 sq m≈ 451–630 sq ft |
| Wing C | 79 | 74 | 0 | 5 | 0 | 36.29–45.25 sq m≈ 391–487 sq ft |
Different sizes are not necessarily different bedroom types. How we read and summarise the filing →
Unit Report
Understand its light, privacy, layout and surroundings. See how it compares with similar homes and other options in this project.
Didn’t help you decide? Full refund — no questions asked.
The same home number may appear in more than one building. Check both before choosing.
MahaRERA · per-home inventory · saved-file date 18 July 2026
| Home / building | Floor in the record | Carpet area | Reported status | Agreement value | Assess |
|---|---|---|---|---|---|
| 101WING A | 1 | 41.94 sq m≈ 451 sq ft | Marked unsold | Not stated | |
| 102WING A | 1 | 58.53 sq m≈ 630 sq ft | Sold | ₹2,350,000 | |
| 103WING A | 1 | 58.53 sq m≈ 630 sq ft | Marked unsold | Not stated | |
| 104WING A | 1 | 41.94 sq m≈ 451 sq ft | Sold | ₹1,900,000 | |
| 105WING A | 1 | 41.94 sq m≈ 451 sq ft | Marked unsold | Not stated | |
| 106WING A | 1 | 58.53 sq m≈ 630 sq ft | Sold | ₹3,270,000 | |
| 107WING A | 1 | 58.53 sq m≈ 630 sq ft | Sold | ₹3,000,000 | |
| 108WING A | 1 | 41.94 sq m≈ 451 sq ft | Sold | ₹2,800,000 | |
| 201WING A | 2 | 41.94 sq m≈ 451 sq ft | Marked unsold | Not stated | |
| 202WING A | 2 | 58.53 sq m≈ 630 sq ft | Sold | ₹3,550,000 | |
| 203WING A | 2 | 58.53 sq m≈ 630 sq ft | Sold | ₹4,000,000 | |
| 204WING A | 2 | 41.94 sq m≈ 451 sq ft | Marked unsold | Not stated |
Read every entry in one table: Read the complete saved home list.
Choose the home you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.
More from the RERA documents
₹295,000,000 of an estimated ₹358,000,000 was reported as incurred (82.4%). This percentage is about costs. It does not show how much construction is complete.
MahaRERA project filing · read 18 July 2026 · registration P52100007646
Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.
| Building | Activity | Reported |
|---|---|---|
| WING A | Excavation | 100.0% |
| WING A | Basement (if any) | 100.0% |
| WING A | Podiums (if any) | 0.0% |
| WING A | Plinth | 100.0% |
| WING A | Stilt Floor | 100.0% |
| WING A | Slabs of Super Structure | 100.0% |
| WING A | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100.0% |
| WING A | Sanitary Fittings within the flats / premises | 100.0% |
| WING A | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100.0% |
| WING A | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100.0% |
| WING A | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100.0% |
| Wing B | Excavation | 100.0% |
| Wing B | Basement (if any) | 100.0% |
| Wing B | Podiums (if any) | 0.0% |
| Wing B | Plinth | 100.0% |
| Wing B | Stilt Floor | 0.0% |
| Wing B | Slabs of Super Structure | 100.0% |
| Wing B | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100.0% |
| Wing B | Sanitary Fittings within the flats / premises | 100.0% |
| Wing B | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100.0% |
| Wing B | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100.0% |
| Wing B | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100.0% |
| Wing C | Excavation | 100.0% |
| Wing C | Basement (if any) | 100.0% |
| Wing C | Podiums (if any) | 0.0% |
| Wing C | Plinth | 100.0% |
| Wing C | Stilt Floor | 0.0% |
| Wing C | Slabs of Super Structure | 100.0% |
| Wing C | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100.0% |
| Wing C | Sanitary Fittings within the flats / premises | 100.0% |
| Wing C | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100.0% |
| Wing C | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100.0% |
| Wing C | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100.0% |
MahaRERA project filing · read 18 July 2026 · registration P52100007646
| Revised target | Reason given by the builder |
|---|---|
| 23 December 2023 | Our project namely "Sai Sahawas"situated Gat no-53,in Wadebolhai,Tal-Haweli,Dist-Pune,going to delay because we got revised sanction from PMRDA,which is our sanctioning authority in 27th Oct.2021.And our RERA commitment will be on 24th Dec.2022 in this situation and short time of 12 month it is not possible to construct 2 towers Wing "A"&WING "C".So want to extra time for complete this project. |
| 23 December 2025 | Contingencies arising during the Corona period made it inevitable to make some changes in the project, so the revised design of A and c wings of the project was delayed by the concerned sanctioning authority, then due to the lack of response from the contractor labors and the customers, the sale was delayed. |
| 23 December 2026 | We respectfully submit that the construction work of the project has been substantially completed as per the sanctioned plans. The application for issuance of the Occupancy Certificate (OC) has already been submitted to the competent planning authority, and the same is under process. The delay in obtaining the Occupancy Certificate is primarily due to procedural requirements, inspections, and administrative processing at the level of the concerned authority, which is beyond the control of the promoter. No major structural work remains pending. Only minor finishing touches and compliance-related formalities, if any, are being addressed to meet the requirements of the authority. To ensure continuous regulatory compliance and to avoid any technical lapse in the validity of MahaRERA registration during the period required for issuance of the Occupancy Certificate, we are seeking an extension of the project registration. A detailed status report and PERT Chart indicating completion milestones and expected timelines are enclosed herewith. In view of the above, we kindly request the Authority to grant an extension of the project registration up to 23-12-2026, to enable us to obtain the Occupancy Certificate and complete all regulatory formalities. We assure the Authority of our full cooperation and compliance with the provisions of the Real Estate (Regulation and Development) Act, 2016 and the Rules and Regulations made thereunder. |
MahaRERA project filing · read 18 July 2026 · registration P52100007646
RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.
| Filing | Own funds | Borrowing | Payments from buyers | Total |
|---|---|---|---|---|
| Estimated plan | ₹243,629,925 | ₹0 | ₹0 | ₹243,629,925 |
| Actual raised | ₹407,510,000 | ₹0 | ₹0 | ₹407,510,000 |
MahaRERA project filing · read 18 July 2026 · registration P52100007646
36 elapsed quarterly periods in the captured compliance schedule. Active default was recorded for FY 2025-2026.
MahaRERA project filing · read 18 July 2026 · registration P52100007646
A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.
MahaRERA project filing · read 18 July 2026 · registration P52100007646
Builder and past records
Projects registered under this company
1Pune registrations
These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.
MahaRERA Pune registration records · read 12 July 2026
Past records of sales and unsold homes
21 September 2026
30 marked unsold · 168 sold · 0 booked.
Saved MahaRERA home list
13 September 2026
30 marked unsold · 168 sold · 0 booked.
Saved MahaRERA home list
4 September 2026
30 marked unsold · 168 sold · 0 booked.
Saved MahaRERA home list
18 July 2026
30 marked unsold · 168 sold · 0 booked.
Saved MahaRERA home list
These dates show when the records were saved, not when homes were sold. Sales may have changed since then, even if the saved counts are the same.
Project Comparison Report
Compare up to three projects. We read their plans and RERA documents, recommend homes in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.
2 projects · ₹7,999
3 projects · ₹9,999
Within 1 working day
Didn’t help you decide? Full refund — no questions asked.
Compare project details for free →MahaRERA · registration record · read 12 July 2026
MahaRERA · per-home inventory · saved-file date 18 July 2026
This is a past RERA home list, not current availability. It does not give the date each home was sold.
The home-list date is based on the saved file’s details.
Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.
Open MahaRERA · search P52100007646 ↗