homeonpaper.

Builder’s RERA records,
explained for buyers.

The builder’s RERA record, explained

Aapla Ghar Ambegaon Annex Phase I

Maple Buildcon · P52100008761

MahaRERA · registration record · read 12 July 2026

Choose a report ↓

What does the RERA record show?

For Aapla Ghar Ambegaon Annex Phase I (P52100008761), 24 of 134 entries were marked unsold in the MahaRERA home list dated 18 July 2026 (saved-file date).

MahaRERA · per-home inventory · saved-file date 18 July 2026

For Aapla Ghar Ambegaon Annex Phase I, ₹5,131 per sq ft of carpet area is the median rate across 110 sold or booked entries with prices in the MahaRERA home list dated 18 July 2026 (saved-file date). These are historical agreement values, not current asking prices.

MahaRERA · per-home inventory · saved-file date 18 July 2026

These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.

What would help you decide?

Buyer’s Report

Understand this project

Find homes to consider, with advice on light, layout, privacy and surroundings.

₹4,999

Unit Report

Check a particular home

See its advantages, drawbacks and how it compares with other homes in this project.

₹3,999

Project Comparison Report

Choose between projects

Compare two or three projects and get recommended homes in order, with reasons for each choice.

From ₹7,999

Choose projects →

Project status and completion date.

Prices reported to RERA

What prices have been reported?

₹5,131/ sq ft carpet area

Across 110 sold or booked entries with reported prices. The middle 80% of rates fall between ₹4,167 and ₹6,008.

MahaRERA · per-home inventory · saved-file date 18 July 2026

How is this calculated?

For each sold or booked entry, we divide the reported agreement value by its carpet area in square feet. The median is the middle rate when these rates are put in order. We show it only when at least five entries have prices. We exclude valuations of unsold homes and government reference rates. The figures may include different sizes and property types. They are historical agreement values, not current asking prices or the total cost including extra charges.

Sales Report

What did similar homes sell for?

Compare reported agreement values by building, size and floor. See which homes were marked unsold on the date shown.

₹2,999 · delivered on payment

Inside this registered phase

How do the buildings compare in the record?

134 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.

MahaRERA · per-home inventory · saved-file date 18 July 2026

Scroll sideways to see all columns.

Building names, sale status and carpet areas — not current availability
Filed buildingEntriesSoldBookedMarked unsoldOther / unstated statusRecorded carpet-area range
B16450014033.31–47.16 sq m≈ 359–508 sq ft
B27060010028.29 sq m≈ 305 sq ft

Different sizes are not necessarily different bedroom types. How we read and summarise the filing →

Unit Report

Is this the right
home for you?

Understand its light, privacy, layout and surroundings. See how it compares with similar homes and other options in this project.

₹3,999 · 1 working day

Didn’t help you decide? Full refund — no questions asked.

Find your home in the RERA list.

The same home number may appear in more than one building. Check both before choosing.

134 listed entries

MahaRERA · per-home inventory · saved-file date 18 July 2026

RERA home list, not current availability
Home / buildingFloor in the recordCarpet areaReported statusAgreement valueAssess
101B1147.16 sq m≈ 508 sq ftSold₹2,498,813
102B1133.31 sq m≈ 359 sq ftSold₹1,888,028
103B1133.31 sq m≈ 359 sq ftSold₹2,037,438
104B1147.16 sq m≈ 508 sq ftSold₹2,491,250
105B1147.16 sq m≈ 508 sq ftSold₹2,870,455
106B1133.31 sq m≈ 359 sq ftSold₹1,934,064
107B1133.31 sq m≈ 359 sq ftSold₹2,210,640
108B1147.16 sq m≈ 508 sq ftSold₹2,998,718
201B1247.16 sq m≈ 508 sq ftSold₹2,557,500
202B1233.31 sq m≈ 359 sq ftSold₹2,037,438
203B1233.31 sq m≈ 359 sq ftSold₹1,817,314
204B1247.16 sq m≈ 508 sq ftSold₹2,115,462

Read every entry in one table: Read the complete saved home list.

Choose the home you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.

More from the RERA documents

Construction progress and project documents.

Cost reported as incurred

₹192,500,000 of an estimated ₹218,000,000 was reported as incurred (88.3%). This percentage is about costs. It does not show how much construction is complete.

MahaRERA project filing · read 18 July 2026 · registration P52100008761

Work reported, by building

Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.

See all reported activities
BuildingActivityReported
B1Excavation100.0%
B1Basement (if any)100.0%
B1Podiums (if any) 0.0%
B1Plinth100.0%
B1Stilt Floor 0.0%
B1Slabs of Super Structure100.0%
B1Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises97.0%
B1Sanitary Fittings within the flats / premises96.0%
B1Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85.0%
B1External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.98.0%
B1Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.70.0%
B2Excavation100.0%
B2Basement (if any)100.0%
B2Podiums (if any) 0.0%
B2Plinth100.0%
B2Stilt Floor 0.0%
B2Slabs of Super Structure95.0%
B2Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90.0%
B2Sanitary Fittings within the flats / premises85.0%
B2Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75.0%
B2External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75.0%
B2Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.65.0%
proposedExcavation0.0%
proposedBasement (if any)0.0%
proposedPodiums (if any) 0.0%
proposedPlinth0.0%
proposedStilt Floor 0.0%
proposedSlabs of Super Structure0.0%
proposedInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
proposedSanitary Fittings within the flats / premises0.0%
proposedStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
proposedExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
proposedInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
proposedExcavation0.0%
proposedBasement (if any)0.0%
proposedPodiums (if any) 0.0%
proposedPlinth0.0%
proposedStilt Floor 0.0%
proposedSlabs of Super Structure0.0%
proposedInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
proposedSanitary Fittings within the flats / premises0.0%
proposedStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
proposedExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
proposedInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
ProposedExcavation0.0%
ProposedBasement (if any)0.0%
ProposedPodiums (if any) 0.0%
ProposedPlinth0.0%
ProposedStilt Floor 0.0%
ProposedSlabs of Super Structure0.0%
ProposedInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
ProposedSanitary Fittings within the flats / premises0.0%
ProposedStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
ProposedExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
ProposedInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%

MahaRERA project filing · read 18 July 2026 · registration P52100008761

Reported deadline extensions

Revised targetReason given by the builder
29 December 2024due to covid and non availability of material
31 December 2029Due to changes in UDCPR rules and regulations,

MahaRERA project filing · read 18 July 2026 · registration P52100008761

Where the project funding comes from

RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.

FilingOwn fundsBorrowingPayments from buyersTotal
Estimated plan₹0₹0₹527,632,189₹527,632,189
Actual raised₹264,520,547₹0₹186,161,630₹481,935,250

MahaRERA project filing · read 18 July 2026 · registration P52100008761

Quarterly filing record

36 elapsed quarterly periods in the captured compliance schedule. No active quarterly default was recorded in this snapshot.

MahaRERA project filing · read 18 July 2026 · registration P52100008761

Documents named in the filing

  • Commencement certificate · 4 listed
  • Promoter PAN · 1 listed
  • Form 1 — Architect's certificate · 1 listed
  • Form 3 — CA certificate · 1 listed
  • Form 2 — Engineer's certificate · 1 listed
  • Title / search report · 3 listed
  • Form B — Promoter declaration · 3 listed
  • Sanctioned building plan · 3 listed
  • Sanctioned layout plan · 2 listed

A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.

MahaRERA project filing · read 18 July 2026 · registration P52100008761

Builder and past records

What else does the record show?

Projects registered under this company

Maple Buildcon

1Pune registrations

These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.

MahaRERA Pune registration records · read 12 July 2026

Explore other registrations

    Past records of sales and unsold homes

    1. 21 September 2026

      24 marked unsold · 110 sold · 0 booked.

      Saved MahaRERA home list

    2. 13 September 2026

      24 marked unsold · 110 sold · 0 booked.

      Saved MahaRERA home list

    3. 4 September 2026

      24 marked unsold · 110 sold · 0 booked.

      Saved MahaRERA home list

    4. 18 July 2026

      24 marked unsold · 110 sold · 0 booked.

      Saved MahaRERA home list

    These dates show when the records were saved, not when homes were sold. Sales may have changed since then, even if the saved counts are the same.

    Project Comparison Report

    Which project should you buy in?
    And which home?

    Compare up to three projects. We read their plans and RERA documents, recommend homes in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.

    Create my Comparison Report →

    2 projects · ₹7,999
    3 projects · ₹9,999

    Within 1 working day

    Didn’t help you decide? Full refund — no questions asked.

    Compare project details for free →

    Sources and dates.

    MahaRERA · registration record · read 12 July 2026

    MahaRERA · per-home inventory · saved-file date 18 July 2026

    This is a past RERA home list, not current availability. It does not give the date each home was sold.

    The home-list date is based on the saved file’s details.

    Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.

    Open MahaRERA · search P52100008761 ↗
    homeonpaper