What does the RERA record show?

For VIJAY VIHAR (P52100009408), 0 of 728 entries were marked unsold in the MahaRERA home list dated 18 July 2026 (saved-file date).

MahaRERA · per-home inventory · saved-file date 18 July 2026

For VIJAY VIHAR, ₹5,874 per sq ft of carpet area is the median rate across 728 sold or booked entries with prices in the MahaRERA home list dated 18 July 2026 (saved-file date). These are historical agreement values, not current asking prices.

MahaRERA · per-home inventory · saved-file date 18 July 2026

These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.

What would help you decide?

Buyer’s Report

Understand this project

Find homes to consider, with advice on light, layout, privacy and surroundings.

₹4,999

Unit Report

Check a particular home

See its advantages, drawbacks and how it compares with other homes in this project.

₹3,999

Project Comparison Report

Choose between projects

Compare two or three projects and get recommended homes in order, with reasons for each choice.

From ₹7,999

Choose projects →

Project status and completion date.

Prices reported to RERA

What prices have been reported?

₹5,874/ sq ft carpet area

Across 728 sold or booked entries with reported prices. The middle 80% of rates fall between ₹5,125 and ₹6,247.

MahaRERA · per-home inventory · saved-file date 18 July 2026

How is this calculated?

For each sold or booked entry, we divide the reported agreement value by its carpet area in square feet. The median is the middle rate when these rates are put in order. We show it only when at least five entries have prices. We exclude valuations of unsold homes and government reference rates. The figures may include different sizes and property types. They are historical agreement values, not current asking prices or the total cost including extra charges.

Sales Report

What did similar homes sell for?

Compare reported agreement values by building, size and floor. See which homes were marked unsold on the date shown.

₹2,999 · delivered on payment

Inside this registered phase

How do the buildings compare in the record?

728 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.

MahaRERA · per-home inventory · saved-file date 18 July 2026

Scroll sideways to see all columns.

Building names, sale status and carpet areas — not current availability
Filed buildingEntriesSoldBookedMarked unsoldOther / unstated statusRecorded carpet-area range
TOWER-A5656000100.05 sq m≈ 1,077 sq ft
TOWER-B5656000100.05 sq m≈ 1,077 sq ft
TOWER-C5656000100.05 sq m≈ 1,077 sq ft
TOWER-D5656000100.05 sq m≈ 1,077 sq ft
TOWER-E5656000154.54 sq m≈ 1,663 sq ft
TOWER-F5656000154.54 sq m≈ 1,663 sq ft
TOWER-G848400079.06 sq m≈ 851 sq ft
TOWER-H848400067.91 sq m≈ 731 sq ft
TOWER-J5656000113.99 sq m≈ 1,227 sq ft
TOWER-K5656000113.99 sq m≈ 1,227 sq ft
TOWER-L5656000113.99 sq m≈ 1,227 sq ft
TOWER-M5656000113.99 sq m≈ 1,227 sq ft

Different sizes are not necessarily different bedroom types. How we read and summarise the filing →

Unit Report

Is this the right
home for you?

Understand its light, privacy, layout and surroundings. See how it compares with similar homes and other options in this project.

₹3,999 · 1 working day

Didn’t help you decide? Full refund — no questions asked.

Find your home in the RERA list.

The same home number may appear in more than one building. Check both before choosing.

728 listed entries

MahaRERA · per-home inventory · saved-file date 18 July 2026

RERA home list, not current availability
Home / buildingFloor in the recordCarpet areaReported statusAgreement valueAssess
A 1001TOWER-A10100.05 sq m≈ 1,077 sq ftSold₹6,475,569
A 1002TOWER-A10100.05 sq m≈ 1,077 sq ftSold₹6,475,569
A 1003TOWER-A10100.05 sq m≈ 1,077 sq ftSold₹6,090,000
A 1004TOWER-A10100.05 sq m≈ 1,077 sq ftSold₹6,090,000
A 1101TOWER-A11100.05 sq m≈ 1,077 sq ftSold₹6,136,632
A 1102TOWER-A11100.05 sq m≈ 1,077 sq ftSold₹6,122,335
A 1103TOWER-A11100.05 sq m≈ 1,077 sq ftSold₹6,475,569
A 1104TOWER-A11100.05 sq m≈ 1,077 sq ftSold₹6,090,000
A 1201TOWER-A12100.05 sq m≈ 1,077 sq ftSold₹6,090,000
A 1202TOWER-A12100.05 sq m≈ 1,077 sq ftSold₹6,090,000
A 1203TOWER-A12100.05 sq m≈ 1,077 sq ftSold₹6,090,000
A 1204TOWER-A12100.05 sq m≈ 1,077 sq ftSold₹6,090,000

Read every entry in one table: Read the complete saved home list.

Choose the home you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.

More from the RERA documents

Construction progress and project documents.

Work reported, by building

Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.

See all reported activities
BuildingActivityReported
TOWER-AExcavation100.0%
TOWER-ABasement (if any)0.0%
TOWER-APodiums (if any) 0.0%
TOWER-APlinth0.0%
TOWER-AStilt Floor 100.0%
TOWER-ASlabs of Super Structure15.0%
TOWER-AInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100.0%
TOWER-ASanitary Fittings within the flats / premises50.0%
TOWER-AStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100.0%
TOWER-AExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100.0%
TOWER-AInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10.0%
TOWER-BExcavation100.0%
TOWER-BBasement (if any)0.0%
TOWER-BPodiums (if any) 0.0%
TOWER-BPlinth0.0%
TOWER-BStilt Floor 100.0%
TOWER-BSlabs of Super Structure15.0%
TOWER-BInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60.0%
TOWER-BSanitary Fittings within the flats / premises20.0%
TOWER-BStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90.0%
TOWER-BExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80.0%
TOWER-BInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
TOWER-CExcavation100.0%
TOWER-CBasement (if any)0.0%
TOWER-CPodiums (if any) 0.0%
TOWER-CPlinth0.0%
TOWER-CStilt Floor 100.0%
TOWER-CSlabs of Super Structure15.0%
TOWER-CInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100.0%
TOWER-CSanitary Fittings within the flats / premises25.0%
TOWER-CStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90.0%
TOWER-CExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80.0%
TOWER-CInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
TOWER-DExcavation100.0%
TOWER-DBasement (if any)0.0%
TOWER-DPodiums (if any) 0.0%
TOWER-DPlinth0.0%
TOWER-DStilt Floor 100.0%
TOWER-DSlabs of Super Structure15.0%
TOWER-DInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70.0%
TOWER-DSanitary Fittings within the flats / premises3.0%
TOWER-DStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90.0%
TOWER-DExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50.0%
TOWER-DInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
TOWER-EExcavation100.0%
TOWER-EBasement (if any)0.0%
TOWER-EPodiums (if any) 0.0%
TOWER-EPlinth0.0%
TOWER-EStilt Floor 100.0%
TOWER-ESlabs of Super Structure15.0%
TOWER-EInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises65.0%
TOWER-ESanitary Fittings within the flats / premises2.0%
TOWER-EStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90.0%
TOWER-EExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.65.0%
TOWER-EInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
TOWER-FExcavation100.0%
TOWER-FBasement (if any)0.0%
TOWER-FPodiums (if any) 0.0%
TOWER-FPlinth0.0%
TOWER-FStilt Floor 100.0%
TOWER-FSlabs of Super Structure15.0%
TOWER-FInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100.0%
TOWER-FSanitary Fittings within the flats / premises50.0%
TOWER-FStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100.0%
TOWER-FExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100.0%
TOWER-FInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
TOWER-GExcavation100.0%
TOWER-GBasement (if any)0.0%
TOWER-GPodiums (if any) 0.0%
TOWER-GPlinth0.0%
TOWER-GStilt Floor 100.0%
TOWER-GSlabs of Super Structure14.0%
TOWER-GInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises65.0%
TOWER-GSanitary Fittings within the flats / premises2.0%
TOWER-GStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80.0%
TOWER-GExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.35.0%
TOWER-GInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
TOWER-HExcavation100.0%
TOWER-HBasement (if any)0.0%
TOWER-HPodiums (if any) 0.0%
TOWER-HPlinth0.0%
TOWER-HStilt Floor 100.0%
TOWER-HSlabs of Super Structure15.0%
TOWER-HInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70.0%
TOWER-HSanitary Fittings within the flats / premises2.0%
TOWER-HStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60.0%
TOWER-HExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.20.0%
TOWER-HInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
TOWER-JExcavation100.0%
TOWER-JBasement (if any)0.0%
TOWER-JPodiums (if any) 0.0%
TOWER-JPlinth0.0%
TOWER-JStilt Floor 100.0%
TOWER-JSlabs of Super Structure15.0%
TOWER-JInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70.0%
TOWER-JSanitary Fittings within the flats / premises4.0%
TOWER-JStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75.0%
TOWER-JExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60.0%
TOWER-JInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
TOWER-KExcavation100.0%
TOWER-KBasement (if any)0.0%
TOWER-KPodiums (if any) 0.0%
TOWER-KPlinth0.0%
TOWER-KStilt Floor 100.0%
TOWER-KSlabs of Super Structure15.0%
TOWER-KInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises75.0%
TOWER-KSanitary Fittings within the flats / premises3.0%
TOWER-KStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80.0%
TOWER-KExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.70.0%
TOWER-KInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
TOWER-LExcavation100.0%
TOWER-LBasement (if any)0.0%
TOWER-LPodiums (if any) 0.0%
TOWER-LPlinth0.0%
TOWER-LStilt Floor 100.0%
TOWER-LSlabs of Super Structure15.0%
TOWER-LInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90.0%
TOWER-LSanitary Fittings within the flats / premises2.0%
TOWER-LStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90.0%
TOWER-LExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95.0%
TOWER-LInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
TOWER-MExcavation100.0%
TOWER-MBasement (if any)0.0%
TOWER-MPodiums (if any) 0.0%
TOWER-MPlinth0.0%
TOWER-MStilt Floor 100.0%
TOWER-MSlabs of Super Structure15.0%
TOWER-MInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70.0%
TOWER-MSanitary Fittings within the flats / premises1.0%
TOWER-MStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70.0%
TOWER-MExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.25.0%
TOWER-MInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
PODIUMExcavation100.0%
PODIUMBasement (if any)0.0%
PODIUMPodiums (if any) 1.0%
PODIUMPlinth0.0%
PODIUMStilt Floor 0.0%
PODIUMSlabs of Super Structure2.0%
PODIUMInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises30.0%
PODIUMSanitary Fittings within the flats / premises0.0%
PODIUMStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50.0%
PODIUMExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
PODIUMInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
CLUBExcavation100.0%
CLUBBasement (if any)0.0%
CLUBPodiums (if any) 0.0%
CLUBPlinth0.0%
CLUBStilt Floor 100.0%
CLUBSlabs of Super Structure1.0%
CLUBInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
CLUBSanitary Fittings within the flats / premises0.0%
CLUBStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
CLUBExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
CLUBInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
SHOPPINGExcavation100.0%
SHOPPINGBasement (if any)0.0%
SHOPPINGPodiums (if any) 0.0%
SHOPPINGPlinth0.0%
SHOPPINGStilt Floor 0.0%
SHOPPINGSlabs of Super Structure0.0%
SHOPPINGInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
SHOPPINGSanitary Fittings within the flats / premises0.0%
SHOPPINGStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
SHOPPINGExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
SHOPPINGInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%

MahaRERA project filing · read 18 July 2026 · registration P52100009408

Reported deadline extensions

Revised targetReason given by the builder
30 December 2020LANDSCAPE WORKS AND INSTALLATION OF LIFTS ARE PROPOSED TO BE DONE
13 December 2022The project work is 100% completed. We have received Full Occupancy Certificate dated 13/12/2022. We require extension till date of Occupancy Certificate.

MahaRERA project filing · read 18 July 2026 · registration P52100009408

Where the project funding comes from

RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.

FilingOwn fundsBorrowingPayments from buyersTotal
Estimated plan₹1,597,923,566₹0₹2,196,851,265₹3,794,774,831
Actual raised₹1,597,923,566₹0₹2,196,851,265₹3,794,774,831

MahaRERA project filing · read 18 July 2026 · registration P52100009408

Quarterly filing record

22 elapsed quarterly periods in the captured compliance schedule. No active quarterly default was recorded in this snapshot.

MahaRERA project filing · read 18 July 2026 · registration P52100009408

Documents named in the filing

  • Commencement certificate · 4 listed
  • Promoter PAN · 2 listed
  • Form 1 — Architect's certificate · 2 listed
  • Form 3 — CA certificate · 2 listed
  • Form 2 — Engineer's certificate · 2 listed
  • Form B — Promoter declaration · 1 listed
  • Title / search report · 2 listed
  • Sanctioned building plan · 1 listed
  • Sanctioned layout plan · 1 listed
  • Occupancy / completion certificate · 1 listed

A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.

MahaRERA project filing · read 18 July 2026 · registration P52100009408

Builder and past records

What else does the record show?

Projects registered under this company

COL. RPS RAWAT

1Pune registrations

These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.

MahaRERA Pune registration records · read 12 July 2026

Explore other registrations

    Past records of sales and unsold homes

    1. 22 September 2026

      0 marked unsold · 728 sold · 0 booked.

      Saved MahaRERA home list

    2. 13 September 2026

      0 marked unsold · 728 sold · 0 booked.

      Saved MahaRERA home list

    3. 4 September 2026

      0 marked unsold · 728 sold · 0 booked.

      Saved MahaRERA home list

    4. 18 July 2026

      0 marked unsold · 728 sold · 0 booked.

      Saved MahaRERA home list

    These dates show when the records were saved, not when homes were sold. Sales may have changed since then, even if the saved counts are the same.

    Project Comparison Report

    Which project should you buy in?
    And which home?

    Compare up to three projects. We read their plans and RERA documents, recommend homes in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.

    Create my Comparison Report →

    2 projects · ₹7,999
    3 projects · ₹9,999

    Within 1 working day

    Didn’t help you decide? Full refund — no questions asked.

    Compare project details for free →

    Sources and dates.

    MahaRERA · registration record · read 12 July 2026

    MahaRERA · per-home inventory · saved-file date 18 July 2026

    This is a past RERA home list, not current availability. It does not give the date each home was sold.

    The home-list date is based on the saved file’s details.

    Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.

    Open MahaRERA · search P52100009408 ↗
    homeonpaper