Buyer’s Report
Understand this project
Find homes to consider, with advice on light, layout, privacy and surroundings.
₹4,999
Builder’s RERA records,
explained for buyers.
The builder’s RERA record, explained
Shree Sai Associates · P52100010801
For Phase IV - K1 and L1 Buildings (P52100010801), 0 of 176 entries were marked unsold in the MahaRERA home list dated 18 July 2026 (saved-file date).
MahaRERA · per-home inventory · saved-file date 18 July 2026
For Phase IV - K1 and L1 Buildings, ₹3,481 per sq ft of carpet area is the median rate across 151 sold or booked entries with prices in the MahaRERA home list dated 18 July 2026 (saved-file date). These are historical agreement values, not current asking prices.
MahaRERA · per-home inventory · saved-file date 18 July 2026
These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.
Builder’s completion target
This target date has passed. The record shown here does not confirm whether the project is complete or has received more time.
Status shown on RERA
This is the status shown on RERA. It does not confirm an occupancy certificate or today’s construction progress.
Prices reported to RERA
₹3,481/ sq ft carpet area
Across 151 sold or booked entries with reported prices. The middle 80% of rates fall between ₹2,152 and ₹4,161.
MahaRERA · per-home inventory · saved-file date 18 July 2026
For each sold or booked entry, we divide the reported agreement value by its carpet area in square feet. The median is the middle rate when these rates are put in order. We show it only when at least five entries have prices. We exclude valuations of unsold homes and government reference rates. The figures may include different sizes and property types. They are historical agreement values, not current asking prices or the total cost including extra charges.
Sales Report
Compare reported agreement values by building, size and floor. See which homes were marked unsold on the date shown.
Inside this registered phase
176 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.
MahaRERA · per-home inventory · saved-file date 18 July 2026
Scroll sideways to see all columns.
| Filed building | Entries | Sold | Booked | Marked unsold | Other / unstated status | Recorded carpet-area range |
|---|---|---|---|---|---|---|
| Phase IV - K1 Building | 88 | 81 | 7 | 0 | 0 | 30.46–44.02 sq m≈ 328–474 sq ft |
| Phase IV - L1 Building | 88 | 71 | 17 | 0 | 0 | 39.45–44.02 sq m≈ 425–474 sq ft |
Different sizes are not necessarily different bedroom types. How we read and summarise the filing →
Unit Report
Understand its light, privacy, layout and surroundings. See how it compares with similar homes and other options in this project.
Didn’t help you decide? Full refund — no questions asked.
The same home number may appear in more than one building. Check both before choosing.
MahaRERA · per-home inventory · saved-file date 18 July 2026
| Home / building | Floor in the record | Carpet area | Reported status | Agreement value | Assess |
|---|---|---|---|---|---|
| K1-1001Phase IV - K1 Building | 10 | 41.82 sq m≈ 450 sq ft | Sold | ₹1,060,625 | |
| K1-1002Phase IV - K1 Building | 10 | 43.58 sq m≈ 469 sq ft | Sold | ₹1,482,500 | |
| K1-1003Phase IV - K1 Building | 10 | 43.58 sq m≈ 469 sq ft | Sold | ₹1,006,250 | |
| K1-1004Phase IV - K1 Building | 10 | 41.89 sq m≈ 451 sq ft | Sold | ₹1,575,000 | |
| K1-1005Phase IV - K1 Building | 10 | 40.47 sq m≈ 436 sq ft | Sold | ₹1,466,875 | |
| K1-1006Phase IV - K1 Building | 10 | 44.02 sq m≈ 474 sq ft | Sold | ₹1,466,875 | |
| K1-1007Phase IV - K1 Building | 10 | 44.02 sq m≈ 474 sq ft | Sold | ₹960,625 | |
| K1-1008Phase IV - K1 Building | 10 | 40.38 sq m≈ 435 sq ft | Sold | ₹1,545,000 | |
| K1-101Phase IV - K1 Building | 1 | 39.87 sq m≈ 429 sq ft | Sold | ₹1,588,750 | |
| K1-102Phase IV - K1 Building | 1 | 43.44 sq m≈ 468 sq ft | Sold | ₹1,745,800 | |
| K1-103Phase IV - K1 Building | 1 | 43.44 sq m≈ 468 sq ft | Sold | ₹2,799,695 | |
| K1-104Phase IV - K1 Building | 1 | 39.96 sq m≈ 430 sq ft | Sold | ₹2,750,000 |
Read every entry in one table: Read the complete saved home list.
Choose the home you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.
More from the RERA documents
Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.
| Building | Activity | Reported |
|---|---|---|
| Phase IV - K1 Building | Excavation | 100.0% |
| Phase IV - K1 Building | Basement (if any) | 100.0% |
| Phase IV - K1 Building | Podiums (if any) | 0.0% |
| Phase IV - K1 Building | Plinth | 100.0% |
| Phase IV - K1 Building | Stilt Floor | 0.0% |
| Phase IV - K1 Building | Slabs of Super Structure | 100.0% |
| Phase IV - K1 Building | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 90.0% |
| Phase IV - K1 Building | Sanitary Fittings within the flats / premises | 40.0% |
| Phase IV - K1 Building | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 50.0% |
| Phase IV - K1 Building | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 50.0% |
| Phase IV - K1 Building | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 45.0% |
| Phase IV - L1 Building | Excavation | 100.0% |
| Phase IV - L1 Building | Basement (if any) | 100.0% |
| Phase IV - L1 Building | Podiums (if any) | 0.0% |
| Phase IV - L1 Building | Plinth | 100.0% |
| Phase IV - L1 Building | Stilt Floor | 0.0% |
| Phase IV - L1 Building | Slabs of Super Structure | 100.0% |
| Phase IV - L1 Building | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 90.0% |
| Phase IV - L1 Building | Sanitary Fittings within the flats / premises | 40.0% |
| Phase IV - L1 Building | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 50.0% |
| Phase IV - L1 Building | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 50.0% |
| Phase IV - L1 Building | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 45.0% |
MahaRERA project filing · read 18 July 2026 · registration P52100010801
| Revised target | Reason given by the builder |
|---|---|
| 31 December 2025 | The project is almost 90% complete, as indicated in the architect's certificate. However, the promoter requests for additional time to complete the balance 10% work, due to the following reasons: 1) There was a lot of strain on cash flows due to reduced customer bookings and economic slowdown in the market. Therefore, payments to contractors was delayed, 2) Banks and financial institutions were not giving any grace period, and significant cash flows from the customers were utilised to repay project loans taken from Banks and financial institutions, 3) Due to several changes in the GST laws, planning for cash flows became very difficult, and several customers were not willing to pay the GST at higher rates. |
MahaRERA project filing · read 18 July 2026 · registration P52100010801
RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.
| Filing | Own funds | Borrowing | Payments from buyers | Total |
|---|---|---|---|---|
| Estimated plan | ₹87,815,378 | ₹0 | ₹181,900,000 | ₹269,715,378 |
| Actual raised | ₹83,487,482 | ₹0 | ₹181,851,373 | ₹265,338,855 |
MahaRERA project filing · read 18 July 2026 · registration P52100010801
34 elapsed quarterly periods in the captured compliance schedule. Active default was recorded for FY 2025-2026.
MahaRERA project filing · read 18 July 2026 · registration P52100010801
A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.
MahaRERA project filing · read 18 July 2026 · registration P52100010801
Builder and past records
Projects registered under this company
6Pune registrations
These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.
MahaRERA Pune registration records · read 12 July 2026
Past records of sales and unsold homes
22 September 2026
0 marked unsold · 152 sold · 24 booked.
Saved MahaRERA home list
13 September 2026
0 marked unsold · 152 sold · 24 booked.
Saved MahaRERA home list
4 September 2026
0 marked unsold · 152 sold · 24 booked.
Saved MahaRERA home list
18 July 2026
0 marked unsold · 152 sold · 24 booked.
Saved MahaRERA home list
These dates show when the records were saved, not when homes were sold. Sales may have changed since then, even if the saved counts are the same.
Project Comparison Report
Compare up to three projects. We read their plans and RERA documents, recommend homes in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.
2 projects · ₹7,999
3 projects · ₹9,999
Within 1 working day
Didn’t help you decide? Full refund — no questions asked.
Compare project details for free →MahaRERA · registration record · read 12 July 2026
MahaRERA · per-home inventory · saved-file date 18 July 2026
This is a past RERA home list, not current availability. It does not give the date each home was sold.
The home-list date is based on the saved file’s details.
Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.
Open MahaRERA · search P52100010801 ↗