homeonpaper.

Builder’s RERA records,
explained for buyers.

The builder’s RERA record, explained

Apple Regency

Sri Sidhievinayak associetes · P52100011604

MahaRERA · registration record · read 12 July 2026

Choose a report ↓

What does the RERA record show?

For Apple Regency (P52100011604), 201 of 269 entries were marked unsold in the MahaRERA home list dated 18 July 2026 (saved-file date).

MahaRERA · per-home inventory · saved-file date 18 July 2026

For Apple Regency, ₹8,355 per sq ft of carpet area is the median rate across 68 sold or booked entries with prices in the MahaRERA home list dated 18 July 2026 (saved-file date). These are historical agreement values, not current asking prices.

MahaRERA · per-home inventory · saved-file date 18 July 2026

These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.

What would help you decide?

Buyer’s Report

Understand this project

Find homes to consider, with advice on light, layout, privacy and surroundings.

₹4,999

Unit Report

Check a particular home

See its advantages, drawbacks and how it compares with other homes in this project.

₹3,999

Project Comparison Report

Choose between projects

Compare two or three projects and get recommended homes in order, with reasons for each choice.

From ₹7,999

Choose projects →

Project status and completion date.

Prices reported to RERA

What prices have been reported?

₹8,355/ sq ft carpet area

Across 68 sold or booked entries with reported prices. The middle 80% of rates fall between ₹5,479 and ₹13,932.

MahaRERA · per-home inventory · saved-file date 18 July 2026

How is this calculated?

For each sold or booked entry, we divide the reported agreement value by its carpet area in square feet. The median is the middle rate when these rates are put in order. We show it only when at least five entries have prices. We exclude valuations of unsold homes and government reference rates. The figures may include different sizes and property types. They are historical agreement values, not current asking prices or the total cost including extra charges.

Sales Report

What did similar homes sell for?

Compare reported agreement values by building, size and floor. See which homes were marked unsold on the date shown.

₹2,999 · delivered on payment

Inside this registered phase

How do the buildings compare in the record?

269 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.

MahaRERA · per-home inventory · saved-file date 18 July 2026

Scroll sideways to see all columns.

Building names, sale status and carpet areas — not current availability
Filed buildingEntriesSoldBookedMarked unsoldOther / unstated statusRecorded carpet-area range
Apple Regency A Wing7813065082.37–130.11 sq m≈ 887–1,400 sq ft
Apple Regency B Wing191550136023.73–147.07 sq m≈ 255–1,583 sq ft

Different sizes are not necessarily different bedroom types. How we read and summarise the filing →

Unit Report

Is this the right
home for you?

Understand its light, privacy, layout and surroundings. See how it compares with similar homes and other options in this project.

₹3,999 · 1 working day

Didn’t help you decide? Full refund — no questions asked.

Find your home in the RERA list.

The same home number may appear in more than one building. Check both before choosing.

269 listed entries

MahaRERA · per-home inventory · saved-file date 18 July 2026

RERA home list, not current availability
Home / buildingFloor in the recordCarpet areaReported statusAgreement valueAssess
1001Apple Regency A Wing10103.52 sq m≈ 1,114 sq ftMarked unsoldNot stated
1002Apple Regency A Wing10102.53 sq m≈ 1,104 sq ftMarked unsoldNot stated
1003Apple Regency A Wing10111.72 sq m≈ 1,203 sq ftMarked unsoldNot stated
1004Apple Regency A Wing1091.14 sq m≈ 981 sq ftMarked unsoldNot stated
1005Apple Regency A Wing1091.13 sq m≈ 981 sq ftMarked unsoldNot stated
1006Apple Regency A Wing1092.0 sq m≈ 990 sq ftMarked unsoldNot stated
101Apple Regency A Wing1130.11 sq m≈ 1,400 sq ftMarked unsoldNot stated
102Apple Regency A Wing1101.09 sq m≈ 1,088 sq ftMarked unsoldNot stated
103Apple Regency A Wing1101.48 sq m≈ 1,092 sq ftMarked unsoldNot stated
104Apple Regency A Wing185.15 sq m≈ 917 sq ftSold₹10,000,000
105Apple Regency A Wing182.37 sq m≈ 887 sq ftMarked unsoldNot stated
106Apple Regency A Wing1126.11 sq m≈ 1,357 sq ftSold₹10,000,000

Read every entry in one table: Read the complete saved home list.

Choose the home you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.

More from the RERA documents

Construction progress and project documents.

Cost reported as incurred

₹426,779,558 of an estimated ₹850,078,119 was reported as incurred (50.2%). This percentage is about costs. It does not show how much construction is complete.

MahaRERA project filing · read 18 July 2026 · registration P52100011604

Work reported, by building

Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.

See all reported activities
BuildingActivityReported
Apple Regency A WingExcavation100.0%
Apple Regency A WingBasement (if any)100.0%
Apple Regency A WingPodiums (if any) 100.0%
Apple Regency A WingPlinth100.0%
Apple Regency A WingStilt Floor 100.0%
Apple Regency A WingSlabs of Super Structure95.0%
Apple Regency A WingInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90.0%
Apple Regency A WingSanitary Fittings within the flats / premises20.0%
Apple Regency A WingStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100.0%
Apple Regency A WingExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60.0%
Apple Regency A WingInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.40.0%
Apple Regency B WingExcavation100.0%
Apple Regency B WingBasement (if any)100.0%
Apple Regency B WingPodiums (if any) 15.0%
Apple Regency B WingPlinth100.0%
Apple Regency B WingStilt Floor 100.0%
Apple Regency B WingSlabs of Super Structure100.0%
Apple Regency B WingInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85.0%
Apple Regency B WingSanitary Fittings within the flats / premises60.0%
Apple Regency B WingStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90.0%
Apple Regency B WingExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60.0%
Apple Regency B WingInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.45.0%

MahaRERA project filing · read 18 July 2026 · registration P52100011604

Reported deadline extensions

Revised targetReason given by the builder
31 July 2024THE PROJECT SANCTION HIGHER FLOOR E. I BOTH BUILDING SANCTION 13 FLOOR. THE PREVIOUS SANCTION IS 'A' WING 5 FLOOR AND 'B' WING 3RD FLOOR SO KINDLY REQUEST TO YOU PLEASE APPROVE THE EXTENDED DATE
31 December 2025Dear Sir/Madam, We are writing to formally request an extension for the completion of our project Apple Regency, which was registered with MahaRERA in 2017. The project has faced delays due to the following reasons, which were beyond our control: 1. Environment Clearance : a. The project falls under the Environment Clearance category, necessitating approval from the Government of India Ministry of Environment, Forest and Climate Change, as issued by the State Environment Impact Assessment Authority (SEIAA), Maharashtra. b. We initially received the Environment Clearance certificate on 28/05/2019. Despite this, we expedited our work and obtained part completion on 20/03/2020, which has been uploaded to the MahaRERA portal. c. The Final Environment Clearance certificate was only received on 12/11/2024, which has impacted the overall timeline for our project. 2. Plan Sanctioning Authority : a. It is common knowledge that without Environment Clearance, further sanctions and construction work cannot proceed. Due to delays in receiving the initial Environment Clearance, plan sanctions from the Pune Municipal Corporation were also delayed. b. Following the receipt of the Environment Clearance on 28/05/2019, as mentioned in point 1(b), we expedited our efforts, received part completion, and submitted it to the MahaRERA portal on 20/03/2020. c. With the Final Environment Clearance certificate now received as per point 1(c), our final plan sanctions are in place, and we require additional time to complete the remaining construction work. d. We have already given possession to the allottees who have received Part Completion. The possession letters are uploaded in extension documents. We have attached all relevant documents for your review, including the Environment Clearance certificates, plan sanction letters, and the PERT Chart - Construction Schedule. Given the above reasons, we kindly request MahaRERA to grant us an extension for the completion of the project. This will enable us to fulfil our commitment and hand over possession to all allottees.
31 December 20271. Delays in Environmental Clearance (EC) • Initial Approval: The project falls under the EC category. We initially received the Environment Clearance certificate from the State Environment Impact Assessment Authority (SEIAA), Maharashtra, on 28/05/2019. • Proactive Progress: Despite the initial wait, we expedited construction and successfully obtained Part Completion on 20/03/2020, which has been duly updated on the MahaRERA portal. • Final Clearance: The Final Environment Clearance certificate was only granted on 12/11/2024. This prolonged timeline for final clearances directly restricted our ability to finalize the full scope of the project. 2. Impact on Plan Sanctions & Construction • Dependency: In accordance with prevailing regulations, further municipal sanctions and heavy construction work are contingent upon the receipt of Environment Clearance. • PMC Approvals: Following the final EC mentioned above, our final plan sanctions from the Pune Municipal Corporation (PMC) are now in place. • Expanded Scope: While the plan was originally sanctioned for 13 floors, we are now proceeding with the 14th and 15th floors as per the latest sanctioned plans. The construction of these two additional floors requires a reasonable extension of the timeline.   3. Allottee Status and Possession • Interim Deliveries: We have already handed over possession to allottees covered under the Part Completion certificate. • Documentation: Copies of the possession letters have been uploaded to the extension documents section for your verification. 4. Supporting Documentation We have enclosed the following documents for your perusal: • Initial and Final Environment Clearance Certificates. • PERT Chart / Construction Schedule detailing the roadmap to completion. • Proof of possession for existing allottees.

MahaRERA project filing · read 18 July 2026 · registration P52100011604

Where the project funding comes from

RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.

FilingOwn fundsBorrowingPayments from buyersTotal
Estimated plan₹0₹0₹850,078,119₹850,078,119
Actual raised₹0₹0₹165,775,934₹165,775,934

MahaRERA project filing · read 18 July 2026 · registration P52100011604

Quarterly filing record

35 elapsed quarterly periods in the captured compliance schedule. No active quarterly default was recorded in this snapshot.

MahaRERA project filing · read 18 July 2026 · registration P52100011604

Documents named in the filing

  • Promoter PAN · 1 listed
  • Form 1 — Architect's certificate · 2 listed
  • Form 3 — CA certificate · 3 listed
  • Form 2 — Engineer's certificate · 2 listed
  • Title / search report · 1 listed
  • Form B — Promoter declaration · 2 listed
  • Sanctioned building plan · 13 listed
  • Sanctioned layout plan · 1 listed

A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.

MahaRERA project filing · read 18 July 2026 · registration P52100011604

Builder and past records

What else does the record show?

Projects registered under this company

Sri Sidhievinayak associetes

1Pune registrations

These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.

MahaRERA Pune registration records · read 12 July 2026

Explore other registrations

    Past records of sales and unsold homes

    1. 21 September 2026

      201 marked unsold · 68 sold · 0 booked.

      Saved MahaRERA home list

    2. 13 September 2026

      201 marked unsold · 68 sold · 0 booked.

      Saved MahaRERA home list

    3. 4 September 2026

      201 marked unsold · 68 sold · 0 booked.

      Saved MahaRERA home list

    4. 18 July 2026

      201 marked unsold · 68 sold · 0 booked.

      Saved MahaRERA home list

    These dates show when the records were saved, not when homes were sold. Sales may have changed since then, even if the saved counts are the same.

    Project Comparison Report

    Which project should you buy in?
    And which home?

    Compare up to three projects. We read their plans and RERA documents, recommend homes in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.

    Create my Comparison Report →

    2 projects · ₹7,999
    3 projects · ₹9,999

    Within 1 working day

    Didn’t help you decide? Full refund — no questions asked.

    Compare project details for free →

    Sources and dates.

    MahaRERA · registration record · read 12 July 2026

    MahaRERA · per-home inventory · saved-file date 18 July 2026

    This is a past RERA home list, not current availability. It does not give the date each home was sold.

    The home-list date is based on the saved file’s details.

    Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.

    Open MahaRERA · search P52100011604 ↗