Buyer’s Report
Understand this project
Find homes to consider, with advice on light, layout, privacy and surroundings.
₹4,999
Builder’s RERA records,
explained for buyers.
The builder’s RERA record, explained
AMI ESTATES LLP · P52100012616
For VERTILLAS (P52100012616), 9 of 144 entries were marked unsold in the MahaRERA home list dated 18 July 2026 (saved-file date).
MahaRERA · per-home inventory · saved-file date 18 July 2026
For VERTILLAS, ₹9,157 per sq ft of carpet area is the median rate across 133 sold or booked entries with prices in the MahaRERA home list dated 18 July 2026 (saved-file date). These are historical agreement values, not current asking prices.
MahaRERA · per-home inventory · saved-file date 18 July 2026
These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.
Builder’s completion target
This target date has passed. The record shown here does not confirm whether the project is complete or has received more time.
Status shown on RERA
This is the status shown on RERA. It does not confirm an occupancy certificate or today’s construction progress.
Prices reported to RERA
₹9,157/ sq ft carpet area
Across 133 sold or booked entries with reported prices. The middle 80% of rates fall between ₹8,032 and ₹10,577.
MahaRERA · per-home inventory · saved-file date 18 July 2026
For each sold or booked entry, we divide the reported agreement value by its carpet area in square feet. The median is the middle rate when these rates are put in order. We show it only when at least five entries have prices. We exclude valuations of unsold homes and government reference rates. The figures may include different sizes and property types. They are historical agreement values, not current asking prices or the total cost including extra charges.
Sales Report
Compare reported agreement values by building, size and floor. See which homes were marked unsold on the date shown.
Inside this registered phase
144 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.
MahaRERA · per-home inventory · saved-file date 18 July 2026
Scroll sideways to see all columns.
| Filed building | Entries | Sold | Booked | Marked unsold | Other / unstated status | Recorded carpet-area range |
|---|---|---|---|---|---|---|
| TOWER A or TOWER 1 | 72 | 65 | 2 | 5 | 0 | 99.37–144.67 sq m≈ 1,070–1,557 sq ft |
| TOWER B or TOWER 2 | 72 | 67 | 1 | 4 | 0 | 99.37–144.67 sq m≈ 1,070–1,557 sq ft |
Different sizes are not necessarily different bedroom types. How we read and summarise the filing →
Unit Report
Understand its light, privacy, layout and surroundings. See how it compares with similar homes and other options in this project.
Didn’t help you decide? Full refund — no questions asked.
The same home number may appear in more than one building. Check both before choosing.
MahaRERA · per-home inventory · saved-file date 18 July 2026
| Home / building | Floor in the record | Carpet area | Reported status | Agreement value | Assess |
|---|---|---|---|---|---|
| 1001TOWER A or TOWER 1 | 10 | 108.8 sq m≈ 1,171 sq ft | Sold | ₹10,248,263 | |
| 1002TOWER A or TOWER 1 | 10 | 144.67 sq m≈ 1,557 sq ft | Sold | ₹12,700,000 | |
| 1003TOWER A or TOWER 1 | 10 | 144.43 sq m≈ 1,555 sq ft | Sold | ₹13,366,808 | |
| 1004TOWER A or TOWER 1 | 10 | 103.29 sq m≈ 1,112 sq ft | Sold | ₹10,741,147 | |
| 101TOWER A or TOWER 1 | 1 | 106.64 sq m≈ 1,148 sq ft | Sold | ₹9,348,924 | |
| 102TOWER A or TOWER 1 | 1 | 144.66 sq m≈ 1,557 sq ft | Sold | ₹11,579,664 | |
| 103TOWER A or TOWER 1 | 1 | 144.58 sq m≈ 1,556 sq ft | Sold | ₹11,848,887 | |
| 104TOWER A or TOWER 1 | 1 | 99.37 sq m≈ 1,070 sq ft | Sold | ₹9,794,938 | |
| 1101TOWER A or TOWER 1 | 11 | 106.64 sq m≈ 1,148 sq ft | Sold | ₹10,782,523 | |
| 1102TOWER A or TOWER 1 | 11 | 144.67 sq m≈ 1,557 sq ft | Sold | ₹13,366,808 | |
| 1103TOWER A or TOWER 1 | 11 | 144.58 sq m≈ 1,556 sq ft | Sold | ₹14,837,374 | |
| 1104TOWER A or TOWER 1 | 11 | 99.37 sq m≈ 1,070 sq ft | Sold | ₹10,688,913 |
Read every entry in one table: Read the complete saved home list.
Choose the home you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.
More from the RERA documents
₹1,094,760,000 of an estimated ₹1,900,000,000 was reported as incurred (57.6%). This percentage is about costs. It does not show how much construction is complete.
MahaRERA project filing · read 18 July 2026 · registration P52100012616
Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.
| Building | Activity | Reported |
|---|---|---|
| TOWER A or TOWER 1 | Excavation | 100.0% |
| TOWER A or TOWER 1 | Basement (if any) | 100.0% |
| TOWER A or TOWER 1 | Podiums (if any) | 100.0% |
| TOWER A or TOWER 1 | Plinth | 100.0% |
| TOWER A or TOWER 1 | Stilt Floor | 100.0% |
| TOWER A or TOWER 1 | Slabs of Super Structure | 99.0% |
| TOWER A or TOWER 1 | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 29.0% |
| TOWER A or TOWER 1 | Sanitary Fittings within the flats / premises | 0.0% |
| TOWER A or TOWER 1 | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 71.0% |
| TOWER A or TOWER 1 | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 12.0% |
| TOWER A or TOWER 1 | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 14.0% |
| TOWER B or TOWER 2 | Excavation | 100.0% |
| TOWER B or TOWER 2 | Basement (if any) | 100.0% |
| TOWER B or TOWER 2 | Podiums (if any) | 100.0% |
| TOWER B or TOWER 2 | Plinth | 100.0% |
| TOWER B or TOWER 2 | Stilt Floor | 100.0% |
| TOWER B or TOWER 2 | Slabs of Super Structure | 99.0% |
| TOWER B or TOWER 2 | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 25.0% |
| TOWER B or TOWER 2 | Sanitary Fittings within the flats / premises | 0.0% |
| TOWER B or TOWER 2 | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 71.0% |
| TOWER B or TOWER 2 | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 12.0% |
| TOWER B or TOWER 2 | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 14.0% |
MahaRERA project filing · read 18 July 2026 · registration P52100012616
| Revised target | Reason given by the builder |
|---|---|
| 30 June 2024 | DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION TILL 30-06-2024 |
| 30 June 2025 | AS PER ORDER OF THE RERA AUTHORITY |
| 31 March 2026 | I kindly want to bring to your attention the ongoing issue we are facing regarding pending payments from our customers for the work completed in their flats. Despite numerous follow-ups by our CRM team through emails, WhatsApp messages, and phone calls, we are experiencing no payments as customers are providing various excuses for not fulfilling their financial commitments. Additionally, we have attempted to communicate the necessity of the MAHARERA extension to our customers, but unfortunately, we have not received any consent from them to proceed with the New MAHARERA Extension. Given these circumstances, we kindly request your Intervention to look into this matter and provide us with an extension to manage these delays effectively. We believe that with your support, we can resolve this situation and ensure that all parties arc satisfied. Thank you for your attention to this urgent matter. We look forward to your positive response. |
MahaRERA project filing · read 18 July 2026 · registration P52100012616
RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.
| Filing | Own funds | Borrowing | Payments from buyers | Total |
|---|---|---|---|---|
| Estimated plan | ₹863,000,000 | ₹864,000,000 | ₹50,000,000 | ₹1,777,000,000 |
| Actual raised | ₹0 | ₹208,664,446 | ₹1,485,750,652 | ₹1,694,415,098 |
MahaRERA project filing · read 18 July 2026 · registration P52100012616
31 elapsed quarterly periods in the captured compliance schedule. No active quarterly default was recorded in this snapshot.
MahaRERA project filing · read 18 July 2026 · registration P52100012616
A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.
MahaRERA project filing · read 18 July 2026 · registration P52100012616
Builder and past records
Projects registered under this company
1Pune registrations
These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.
MahaRERA Pune registration records · read 12 July 2026
Past records of sales and unsold homes
22 September 2026
9 marked unsold · 132 sold · 3 booked.
Saved MahaRERA home list
13 September 2026
9 marked unsold · 132 sold · 3 booked.
Saved MahaRERA home list
4 September 2026
9 marked unsold · 132 sold · 3 booked.
Saved MahaRERA home list
18 July 2026
9 marked unsold · 132 sold · 3 booked.
Saved MahaRERA home list
These dates show when the records were saved, not when homes were sold. Sales may have changed since then, even if the saved counts are the same.
More projects to explore
These projects list the same locality. They may differ in exact location, home type and price.
Kharadi · Pune
P52100030680
0 of 192 entries marked unsold
MahaRERA · per-home inventory · saved-file date 18 July 2026
View project details →Kharadi · Pune
P52100056143
286 of 318 entries marked unsold
MahaRERA · per-home inventory · saved-file date 18 July 2026
View project details →Kharadi · Pune
P52100080891
105 of 105 entries marked unsold
MahaRERA · per-home inventory · saved-file date 18 July 2026
View project details →Project Comparison Report
Compare up to three projects. We read their plans and RERA documents, recommend homes in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.
2 projects · ₹7,999
3 projects · ₹9,999
Within 1 working day
Didn’t help you decide? Full refund — no questions asked.
Compare project details for free →MahaRERA · registration record · read 12 July 2026
MahaRERA · per-home inventory · saved-file date 18 July 2026
This is a past RERA home list, not current availability. It does not give the date each home was sold.
The home-list date is based on the saved file’s details.
Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.
Open MahaRERA · search P52100012616 ↗