The builder’s RERA record, explained

Tamara

Goldfinger Kataria Urban Developments · P52100013230

MahaRERA · registration record · read 12 July 2026

Choose a report ↓

What does the RERA record show?

For Tamara (P52100013230), 155 of 396 entries were marked unsold in the MahaRERA home list read 4 September 2026.

MahaRERA · per-home inventory · read 4 September 2026

For Tamara, ₹9,544 per sq ft of carpet area is the median rate across 241 sold or booked entries with prices in the MahaRERA home list read 4 September 2026. These are historical agreement values, not current asking prices.

MahaRERA · per-home inventory · read 4 September 2026

These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.

What would help you decide?

Buyer’s Report

Understand this project

Find homes to consider, with advice on light, layout, privacy and surroundings.

₹4,999

Unit Report

Check a particular home

See its advantages, drawbacks and how it compares with other homes in this project.

₹3,999

Project Comparison Report

Choose between projects

Compare two or three projects and get recommended homes in order, with reasons for each choice.

From ₹7,999

Choose projects →

Project status and completion date.

Prices reported to RERA

What prices have been reported?

₹9,544/ sq ft carpet area

Across 241 sold or booked entries with reported prices. The middle 80% of rates fall between ₹7,105 and ₹11,617.

MahaRERA · per-home inventory · read 4 September 2026

How is this calculated?

For each sold or booked entry, we divide the reported agreement value by its carpet area in square feet. The median is the middle rate when these rates are put in order. We show it only when at least five entries have prices. We exclude valuations of unsold homes and government reference rates. The figures may include different sizes and property types. They are historical agreement values, not current asking prices or the total cost including extra charges.

Sales Report

What did similar homes sell for?

Compare reported agreement values by building, size and floor. See which homes were marked unsold on the date shown.

₹2,999 · delivered on payment

Inside this registered phase

How do the buildings compare in the record?

396 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.

MahaRERA · per-home inventory · read 4 September 2026

Scroll sideways to see all columns.

Building names, sale status and carpet areas — not current availability
Filed buildingEntriesSoldBookedMarked unsoldOther / unstated statusRecorded carpet-area range
A building434201064.26–66.24 sq m≈ 692–713 sq ft
B Building434003067.72–91.97 sq m≈ 729–990 sq ft
C Building434003059.51–90.52 sq m≈ 641–974 sq ft
Wing D Uprise13573062067.66–204.40 sq m≈ 728–2,200 sq ft
Wing E Uprise13246086022.46–435.31 sq m≈ 242–4,686 sq ft

Different sizes are not necessarily different bedroom types. How we read and summarise the filing →

Unit Report

Is this the right
home for you?

Understand its light, privacy, layout and surroundings. See how it compares with similar homes and other options in this project.

₹3,999 · 1 working day

Didn’t help you decide? Full refund — no questions asked.

Find your home in the RERA list.

The same home number may appear in more than one building. Check both before choosing.

396 listed entries

MahaRERA · per-home inventory · read 4 September 2026

RERA home list, not current availability
Home / buildingFloor in the recordCarpet areaReported statusAgreement valueAssess
1001A building1064.75 sq m≈ 697 sq ftSold₹6,231,400
1002A building1064.75 sq m≈ 697 sq ftSold₹5,518,100
1003A building1066.23 sq m≈ 713 sq ftSold₹5,376,465
1004A building1066.23 sq m≈ 713 sq ftSold₹6,563,000
101A building164.75 sq m≈ 697 sq ftSold₹5,193,800
102A building164.75 sq m≈ 697 sq ftSold₹5,030,600
103A building164.75 sq m≈ 697 sq ftMarked unsoldNot stated
104A building164.75 sq m≈ 697 sq ftSold₹6,500,000
1101A building1164.75 sq m≈ 697 sq ftSold₹6,461,000
1102A building1164.75 sq m≈ 697 sq ftSold₹6,463,000
1103A building1166.23 sq m≈ 713 sq ftSold₹6,555,000
1104A building1166.23 sq m≈ 713 sq ftSold₹6,383,000

Read every entry in one table: Read the complete saved home list.

Choose the home you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.

More from the RERA documents

Construction progress and project documents.

Cost reported as incurred

₹547,000,000 of an estimated ₹1,086,310,000 was reported as incurred (50.4%). This percentage is about costs. It does not show how much construction is complete.

MahaRERA project filing · read 18 July 2026 · registration P52100013230

Work reported, by building

Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.

See all reported activities
BuildingActivityReported
A buildingExcavation100.0%
A buildingBasement (if any)100.0%
A buildingPodiums (if any) 100.0%
A buildingPlinth100.0%
A buildingStilt Floor 100.0%
A buildingSlabs of Super Structure100.0%
A buildingInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100.0%
A buildingSanitary Fittings within the flats / premises100.0%
A buildingStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100.0%
A buildingExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100.0%
A buildingInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100.0%
B BuildingExcavation100.0%
B BuildingBasement (if any)100.0%
B BuildingPodiums (if any) 100.0%
B BuildingPlinth100.0%
B BuildingStilt Floor 100.0%
B BuildingSlabs of Super Structure100.0%
B BuildingInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100.0%
B BuildingSanitary Fittings within the flats / premises100.0%
B BuildingStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100.0%
B BuildingExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100.0%
B BuildingInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100.0%
C BuildingExcavation100.0%
C BuildingBasement (if any)100.0%
C BuildingPodiums (if any) 100.0%
C BuildingPlinth100.0%
C BuildingStilt Floor 100.0%
C BuildingSlabs of Super Structure100.0%
C BuildingInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100.0%
C BuildingSanitary Fittings within the flats / premises100.0%
C BuildingStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100.0%
C BuildingExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100.0%
C BuildingInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100.0%
D - upriseExcavation100.0%
D - upriseBasement (if any)100.0%
D - uprisePodiums (if any) 90.0%
D - uprisePlinth100.0%
D - upriseStilt Floor 0.0%
D - upriseSlabs of Super Structure68.0%
D - upriseInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40.0%
D - upriseSanitary Fittings within the flats / premises0.0%
D - upriseStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70.0%
D - upriseExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
D - upriseInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
E - upriseExcavation90.0%
E - upriseBasement (if any)90.0%
E - uprisePodiums (if any) 50.0%
E - uprisePlinth90.0%
E - upriseStilt Floor 0.0%
E - upriseSlabs of Super Structure65.0%
E - upriseInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises20.0%
E - upriseSanitary Fittings within the flats / premises0.0%
E - upriseStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks65.0%
E - upriseExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
E - upriseInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%

MahaRERA project filing · read 18 July 2026 · registration P52100013230

Reported deadline extensions

Revised targetReason given by the builder
31 December 2020"It was pleasure to complete the project 5 months before the date of completing the project announced in RERA. The date of completing the Project was given as 31.12.17 & we have received Completion Certificate from PCMC on 31.7.17. Completion from PCMC is pending for 6 flats sold, due to change in balcony location & the extension for the same is required for that purpose only. The Environment Clearance of the Project is also pending with the authorities from quite long time. Firm has proposal to construct 2 Residential & 1 Commercial building in the same project, which will be undertaken after getting Environment Clearance & due sanctions of Plan from PCMC."
30 December 2026Due to Covid 19 and Revise sanction as per new UDCPR Rule.

MahaRERA project filing · read 18 July 2026 · registration P52100013230

Where the project funding comes from

RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.

FilingOwn fundsBorrowingPayments from buyersTotal
Estimated plan₹286,199,185₹0₹1,144,796,738₹1,430,995,923
Actual raised₹0₹0₹675,006,181₹675,006,181

MahaRERA project filing · read 18 July 2026 · registration P52100013230

Quarterly filing record

34 elapsed quarterly periods in the captured compliance schedule. No active quarterly default was recorded in this snapshot.

MahaRERA project filing · read 18 July 2026 · registration P52100013230

Documents named in the filing

  • Promoter PAN · 1 listed
  • Form 1 — Architect's certificate · 4 listed
  • Form 3 — CA certificate · 1 listed
  • Form 2 — Engineer's certificate · 21 listed
  • Form B — Promoter declaration · 1 listed
  • Title / search report · 4 listed
  • Sanctioned layout plan · 11 listed
  • Sanctioned building plan · 24 listed

A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.

MahaRERA project filing · read 18 July 2026 · registration P52100013230

Builder and past records

What else does the record show?

Projects registered under this company

Goldfinger Kataria Urban Developments

1Pune registrations

These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.

MahaRERA Pune registration records · read 12 July 2026

Explore other registrations

    Past records of sales and unsold homes

    1. 22 September 2026

      155 marked unsold · 241 sold · 0 booked.

      Saved MahaRERA home list

    2. 13 September 2026

      155 marked unsold · 241 sold · 0 booked.

      Saved MahaRERA home list

    3. 4 September 2026

      155 marked unsold · 241 sold · 0 booked.

      Saved MahaRERA home list

    4. 18 July 2026

      111 marked unsold · 230 sold · 0 booked.

      Saved MahaRERA home list

    These dates show when the records were saved, not when homes were sold. Sales may have changed since then, even if the saved counts are the same.

    Project Comparison Report

    Which project should you buy in?
    And which home?

    Compare up to three projects. We read their plans and RERA documents, recommend homes in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.

    Create my Comparison Report →

    2 projects · ₹7,999
    3 projects · ₹9,999

    Within 1 working day

    Didn’t help you decide? Full refund — no questions asked.

    Compare project details for free →

    Sources and dates.

    MahaRERA · registration record · read 12 July 2026

    MahaRERA · per-home inventory · read 4 September 2026

    This is a past RERA home list, not current availability. It does not give the date each home was sold.

    Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.

    Open MahaRERA · search P52100013230 ↗