Buyer’s Report
Understand this project
Find homes to consider, with advice on light, layout, privacy and surroundings.
₹4,999
Builder’s RERA records,
explained for buyers.
The builder’s RERA record, explained
Kumar Properties Lifespaces Private Limited · P52100015448
For PLAYTOR CHAKAN MIDC-PHASE 1 (P52100015448), 200 of 262 entries were marked unsold in the MahaRERA home list dated 18 July 2026 (saved-file date).
MahaRERA · per-home inventory · saved-file date 18 July 2026
For PLAYTOR CHAKAN MIDC-PHASE 1, ₹5,393 per sq ft of carpet area is the median rate across 62 sold or booked entries with prices in the MahaRERA home list dated 18 July 2026 (saved-file date). These are historical agreement values, not current asking prices.
MahaRERA · per-home inventory · saved-file date 18 July 2026
These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.
Builder’s completion target
The builder reported this target date. It is not a confirmed handover date.
Status shown on RERA
This is the status shown on RERA. It does not confirm an occupancy certificate or today’s construction progress.
Prices reported to RERA
₹5,393/ sq ft carpet area
Across 62 sold or booked entries with reported prices. The middle 80% of rates fall between ₹4,910 and ₹5,582.
MahaRERA · per-home inventory · saved-file date 18 July 2026
For each sold or booked entry, we divide the reported agreement value by its carpet area in square feet. The median is the middle rate when these rates are put in order. We show it only when at least five entries have prices. We exclude valuations of unsold homes and government reference rates. The figures may include different sizes and property types. They are historical agreement values, not current asking prices or the total cost including extra charges.
Sales Report
Compare reported agreement values by building, size and floor. See which homes were marked unsold on the date shown.
Inside this registered phase
262 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.
MahaRERA · per-home inventory · saved-file date 18 July 2026
Scroll sideways to see all columns.
| Filed building | Entries | Sold | Booked | Marked unsold | Other / unstated status | Recorded carpet-area range |
|---|---|---|---|---|---|---|
| B | 131 | 62 | 0 | 69 | 0 | 23.55–33.79 sq m≈ 253–364 sq ft |
| C | 131 | 0 | 0 | 131 | 0 | 13.86–30.64 sq m≈ 149–330 sq ft |
Different sizes are not necessarily different bedroom types. How we read and summarise the filing →
Unit Report
Understand its light, privacy, layout and surroundings. See how it compares with similar homes and other options in this project.
Didn’t help you decide? Full refund — no questions asked.
The same home number may appear in more than one building. Check both before choosing.
MahaRERA · per-home inventory · saved-file date 18 July 2026
| Home / building | Floor in the record | Carpet area | Reported status | Agreement value | Assess |
|---|---|---|---|---|---|
| 1001B | 10 | 23.55 sq m≈ 253 sq ft | Marked unsold | Not stated | |
| 1002B | 10 | 23.55 sq m≈ 253 sq ft | Marked unsold | Not stated | |
| 1003B | 10 | 33.79 sq m≈ 364 sq ft | Sold | ₹1,980,059 | |
| 1004B | 10 | 33.79 sq m≈ 364 sq ft | Marked unsold | Not stated | |
| 1005B | 10 | 23.55 sq m≈ 253 sq ft | Marked unsold | Not stated | |
| 1006B | 10 | 25.84 sq m≈ 278 sq ft | Marked unsold | Not stated | |
| 1007B | 10 | 23.55 sq m≈ 253 sq ft | Marked unsold | Not stated | |
| 1008B | 10 | 23.55 sq m≈ 253 sq ft | Marked unsold | Not stated | |
| 1009B | 10 | 33.79 sq m≈ 364 sq ft | Marked unsold | Not stated | |
| 101B | 1 | 23.55 sq m≈ 253 sq ft | Sold | ₹1,268,449 | |
| 1010B | 10 | 33.79 sq m≈ 364 sq ft | Marked unsold | Not stated | |
| 1011B | 10 | 23.55 sq m≈ 253 sq ft | Marked unsold | Not stated |
Read every entry in one table: Read the complete saved home list.
Choose the home you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.
More from the RERA documents
Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.
| Building | Activity | Reported |
|---|---|---|
| B | Excavation | 100.0% |
| B | Basement (if any) | 100.0% |
| B | Podiums (if any) | 0.0% |
| B | Plinth | 100.0% |
| B | Stilt Floor | 0.0% |
| B | Slabs of Super Structure | 100.0% |
| B | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 70.0% |
| B | Sanitary Fittings within the flats / premises | 40.0% |
| B | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 60.0% |
| B | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 30.0% |
| B | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0.0% |
| C | Excavation | 0.0% |
| C | Basement (if any) | 0.0% |
| C | Podiums (if any) | 0.0% |
| C | Plinth | 0.0% |
| C | Stilt Floor | 0.0% |
| C | Slabs of Super Structure | 0.0% |
| C | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0.0% |
| C | Sanitary Fittings within the flats / premises | 0.0% |
| C | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0.0% |
| C | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0.0% |
| C | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0.0% |
MahaRERA project filing · read 18 July 2026 · registration P52100015448
| Revised target | Reason given by the builder |
|---|---|
| 30 December 2023 | shortage of building material, because of that |
| 30 June 2026 | The delay in the completion of the real estate project has been primarily caused by a combination of procurement issues, site conditions, coordination challenges, and Insufficient funds. By implementing the outlined action plan, we aim to mitigate these delays and move forward efficiently. However, we assure you that our utmost priority is to safeguard the interests of the allottees and ensure the successful completion of the project. We kindly request an extension under section 7(3) until 30-06-2026, allowing us sufficient time to complete all necessary procedures and meet our commitments to stakeholders while ensuring compliance with applicable regulations. |
| 30 June 2027 | The delay and subsequent stall in the project's completion primarily arose due to unforeseen operational and cash flow limitations faced by the erstwhile promoter i.e, Playtor Rajgurunagar Developers Private Limited. To stabilize the project and secure the interests of all stakeholders, we, Kumar Properties Lifespaces Private Limited, stepped in to take over the development via a registered Sale Deed executed on 31/12/2025. Following this transition, the necessary compliance procedures were promptly initiated to update the regulatory records, resulting in the formal change of promoter being successfully updated on the MahaRERA portal on 26/05/2026. Immediately upon the official handover, we mobilized full resources and restarted construction activities at maximum capacity. However, because the project's registration validity is due to lapse by June 2026, a formal extension is essential to maintain legal and operational continuity on-site, ensuring a seamless, uninterrupted workflow to execute the remaining development work. As a result, we kindly request the extension of the Project till 30/06/2027 to complete the balance work and fulfill all regulatory requirements. |
MahaRERA project filing · read 18 July 2026 · registration P52100015448
RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.
| Filing | Own funds | Borrowing | Payments from buyers | Total |
|---|---|---|---|---|
| Estimated plan | ₹0 | ₹0 | ₹162,713,357 | ₹162,713,357 |
| Actual raised | ₹0 | ₹0 | ₹80,274,960 | ₹80,274,960 |
MahaRERA project filing · read 18 July 2026 · registration P52100015448
33 elapsed quarterly periods in the captured compliance schedule. No active quarterly default was recorded in this snapshot.
MahaRERA project filing · read 18 July 2026 · registration P52100015448
A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.
MahaRERA project filing · read 18 July 2026 · registration P52100015448
Builder and past records
Projects registered under this company
3Pune registrations
These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.
MahaRERA Pune registration records · read 12 July 2026
Past records of sales and unsold homes
25 September 2026
200 marked unsold · 62 sold · 0 booked.
Saved MahaRERA home list
17 September 2026
200 marked unsold · 62 sold · 0 booked.
Saved MahaRERA home list
8 September 2026
200 marked unsold · 62 sold · 0 booked.
Saved MahaRERA home list
18 July 2026
200 marked unsold · 62 sold · 0 booked.
Saved MahaRERA home list
These dates show when the records were saved, not when homes were sold. Sales may have changed since then, even if the saved counts are the same.
Project Comparison Report
Compare up to three projects. We read their plans and RERA documents, recommend homes in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.
2 projects · ₹7,999
3 projects · ₹9,999
Within 1 working day
Didn’t help you decide? Full refund — no questions asked.
Compare project details for free →MahaRERA · registration record · read 12 July 2026
MahaRERA · per-home inventory · saved-file date 18 July 2026
This is a past RERA home list, not current availability. It does not give the date each home was sold.
The home-list date is based on the saved file’s details.
Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.
Open MahaRERA · search P52100015448 ↗