The builder’s RERA record, explained

VISION ONE PHASE TWO

SS GROUP · P52100015755

MahaRERA · registration record · read 12 July 2026

Choose a report ↓

What does the RERA record show?

For VISION ONE PHASE TWO (P52100015755), 21 of 185 entries were marked unsold in the MahaRERA home list dated 18 July 2026 (saved-file date).

MahaRERA · per-home inventory · saved-file date 18 July 2026

For VISION ONE PHASE TWO, ₹9,163 per sq ft of carpet area is the median rate across 164 sold or booked entries with prices in the MahaRERA home list dated 18 July 2026 (saved-file date). These are historical agreement values, not current asking prices.

MahaRERA · per-home inventory · saved-file date 18 July 2026

These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.

What would help you decide?

Buyer’s Report

Understand this project

Find homes to consider, with advice on light, layout, privacy and surroundings.

₹4,999

Unit Report

Check a particular home

See its advantages, drawbacks and how it compares with other homes in this project.

₹3,999

Project Comparison Report

Choose between projects

Compare two or three projects and get recommended homes in order, with reasons for each choice.

From ₹7,999

Choose projects →

Project status and completion date.

Prices reported to RERA

What prices have been reported?

₹9,163/ sq ft carpet area

Across 164 sold or booked entries with reported prices. The middle 80% of rates fall between ₹7,267 and ₹12,200.

MahaRERA · per-home inventory · saved-file date 18 July 2026

How is this calculated?

For each sold or booked entry, we divide the reported agreement value by its carpet area in square feet. The median is the middle rate when these rates are put in order. We show it only when at least five entries have prices. We exclude valuations of unsold homes and government reference rates. The figures may include different sizes and property types. They are historical agreement values, not current asking prices or the total cost including extra charges.

Sales Report

What did similar homes sell for?

Compare reported agreement values by building, size and floor. See which homes were marked unsold on the date shown.

₹2,999 · delivered on payment

Inside this registered phase

How do the buildings compare in the record?

185 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.

MahaRERA · per-home inventory · saved-file date 18 July 2026

Scroll sideways to see all columns.

Building names, sale status and carpet areas — not current availability
Filed buildingEntriesSoldBookedMarked unsoldOther / unstated statusRecorded carpet-area range
VISION ONE1851501421025.24–709.59 sq m≈ 272–7,638 sq ft

Different sizes are not necessarily different bedroom types. How we read and summarise the filing →

Unit Report

Is this the right
home for you?

Understand its light, privacy, layout and surroundings. See how it compares with similar homes and other options in this project.

₹3,999 · 1 working day

Didn’t help you decide? Full refund — no questions asked.

Find your home in the RERA list.

The same home number may appear in more than one building. Check both before choosing.

185 listed entries

MahaRERA · per-home inventory · saved-file date 18 July 2026

RERA home list, not current availability
Home / buildingFloor in the recordCarpet areaReported statusAgreement valueAssess
OFFICE NO 513VISION ONE540.04 sq m≈ 431 sq ftSold₹5,193,550
OFFICE NO 913VISION ONE940.04 sq m≈ 431 sq ftSold₹5,172,000
OFFICE No.1001VISION ONE1027.5 sq m≈ 296 sq ftSold₹3,027,275
OFFICE No.1002VISION ONE1026.1 sq m≈ 281 sq ftMarked unsoldNot stated
OFFICE No.1003VISION ONE1037.53 sq m≈ 404 sq ftMarked unsoldNot stated
OFFICE No.1006VISION ONE1036.32 sq m≈ 391 sq ftMarked unsoldNot stated
OFFICE No.1007VISION ONE1036.32 sq m≈ 391 sq ftMarked unsoldNot stated
OFFICE No.1008VISION ONE1039.3 sq m≈ 423 sq ftMarked unsoldNot stated
OFFICE No.1009VISION ONE1046.73 sq m≈ 503 sq ftMarked unsoldNot stated
OFFICE No.1010VISION ONE1038.46 sq m≈ 414 sq ftMarked unsoldNot stated
OFFICE No.1011VISION ONE1038.46 sq m≈ 414 sq ftMarked unsoldNot stated
OFFICE No.1012VISION ONE1038.46 sq m≈ 414 sq ftMarked unsoldNot stated

Read every entry in one table: Read the complete saved home list.

Choose the home you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.

More from the RERA documents

Construction progress and project documents.

Cost reported as incurred

₹322,309,518 of an estimated ₹406,823,945 was reported as incurred (79.2%). This percentage is about costs. It does not show how much construction is complete.

MahaRERA project filing · read 18 July 2026 · registration P52100015755

Work reported, by building

Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.

See all reported activities
BuildingActivityReported
VISION ONEExcavation100.0%
VISION ONEBasement (if any)100.0%
VISION ONEPodiums (if any) 0.0%
VISION ONEPlinth100.0%
VISION ONEStilt Floor 100.0%
VISION ONESlabs of Super Structure92.0%
VISION ONEInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises67.0%
VISION ONESanitary Fittings within the flats / premises67.0%
VISION ONEStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks78.0%
VISION ONEExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75.0%
VISION ONEInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.75.0%

MahaRERA project filing · read 18 July 2026 · registration P52100015755

Reported deadline extensions

Revised targetReason given by the builder
28 May 2022Construction almost completed in all aspects, need one extension to obtain completion.
31 December 2024In the current pandemic COVID-19, there has been lockdown at certain intervals declared either by the central government (March 2020 to July 2020) or state government (April 15 2021 to May 31 2021). Due to this, there has been a big challenge for the availability of labour and materials for the construction site. Thus the work of the project has been severally impacted.
31 December 2026The project is facing delay due to severe labour shortage, resulting in unavailiblity of skilled worker. Additionally, the contractor performance has been adverserly affected , leading in inefficiencies and compromised work quality. Given these challenges, requesting an extention become imperative to insure the project successful completion while maintaining the desired standard and mitigating the impact of unforeseen workforce constraints. It is important to note that the promoter has transparently communicated this matter to all allottees, majority of the allottees have agreed to provide their consent for the extension.It is important to note that the promoter has transparently communicated this matter to all allottees, majority of the allottees have agreed to provide their consent for the extension.

MahaRERA project filing · read 18 July 2026 · registration P52100015755

Where the project funding comes from

RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.

FilingOwn fundsBorrowingPayments from buyersTotal
Estimated plan₹80,000,000₹30,000,000₹490,371,292₹650,371,292
Actual raised₹60,000,000₹30,000,000₹325,659,320₹415,659,320

MahaRERA project filing · read 18 July 2026 · registration P52100015755

Quarterly filing record

33 elapsed quarterly periods in the captured compliance schedule. No active quarterly default was recorded in this snapshot.

MahaRERA project filing · read 18 July 2026 · registration P52100015755

Documents named in the filing

  • Promoter PAN · 1 listed
  • Form 1 — Architect's certificate · 2 listed
  • Form 3 — CA certificate · 4 listed
  • Form 2 — Engineer's certificate · 2 listed
  • Form B — Promoter declaration · 2 listed
  • Title / search report · 2 listed
  • Sanctioned building plan · 57 listed
  • Sanctioned layout plan · 9 listed
  • Commencement certificate · 1 listed

A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.

MahaRERA project filing · read 18 July 2026 · registration P52100015755

Builder and past records

What else does the record show?

Projects registered under this company

SS GROUP

1Pune registrations

These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.

MahaRERA Pune registration records · read 12 July 2026

Explore other registrations

    Past records of sales and unsold homes

    1. 25 September 2026

      21 marked unsold · 150 sold · 14 booked.

      Saved MahaRERA home list

    2. 17 September 2026

      21 marked unsold · 150 sold · 14 booked.

      Saved MahaRERA home list

    3. 8 September 2026

      21 marked unsold · 150 sold · 14 booked.

      Saved MahaRERA home list

    4. 18 July 2026

      21 marked unsold · 150 sold · 14 booked.

      Saved MahaRERA home list

    These dates show when the records were saved, not when homes were sold. Sales may have changed since then, even if the saved counts are the same.

    More projects to explore

    Other projects in this locality.

    These projects list the same locality. They may differ in exact location, home type and price.

    Project Comparison Report

    Which project should you buy in?
    And which home?

    Compare up to three projects. We read their plans and RERA documents, recommend homes in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.

    Create my Comparison Report →

    2 projects · ₹7,999
    3 projects · ₹9,999

    Within 1 working day

    Didn’t help you decide? Full refund — no questions asked.

    Compare project details for free →

    Sources and dates.

    MahaRERA · registration record · read 12 July 2026

    MahaRERA · per-home inventory · saved-file date 18 July 2026

    This is a past RERA home list, not current availability. It does not give the date each home was sold.

    The home-list date is based on the saved file’s details.

    Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.