Buyer’s Report
Understand this project
Find homes to consider, with advice on light, layout, privacy and surroundings.
₹4,999
Builder’s RERA records,
explained for buyers.
The builder’s RERA record, explained
SAI SAMARTTHA PROPERTIES · P52100016985
For SAISHA (P52100016985), 4 of 135 entries were marked unsold in the MahaRERA home list read 17 September 2026.
For SAISHA, ₹7,922 per sq ft of carpet area is the median rate across 122 sold or booked entries with prices in the MahaRERA home list read 17 September 2026. These are historical agreement values, not current asking prices.
These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.
Builder’s completion target
This target date has passed. The record shown here does not confirm whether the project is complete or has received more time.
Status shown on RERA
This is the status shown on RERA. It does not confirm an occupancy certificate or today’s construction progress.
Prices reported to RERA
₹7,922/ sq ft carpet area
Across 122 sold or booked entries with reported prices. The middle 80% of rates fall between ₹6,670 and ₹9,007.
MahaRERA · per-home inventory · read 17 September 2026
For each sold or booked entry, we divide the reported agreement value by its carpet area in square feet. The median is the middle rate when these rates are put in order. We show it only when at least five entries have prices. We exclude valuations of unsold homes and government reference rates. The figures may include different sizes and property types. They are historical agreement values, not current asking prices or the total cost including extra charges.
Sales Report
Compare reported agreement values by building, size and floor. See which homes were marked unsold on the date shown.
Inside this registered phase
135 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.
MahaRERA · per-home inventory · read 17 September 2026
Scroll sideways to see all columns.
| Filed building | Entries | Sold | Booked | Marked unsold | Other / unstated status | Recorded carpet-area range |
|---|---|---|---|---|---|---|
| A Wing - Podium and 3 Floors | 15 | 13 | 0 | 0 | 2 | 52.10–64.11 sq m≈ 561–690 sq ft |
| B WING | 55 | 52 | 0 | 1 | 2 | 35.18–64.73 sq m≈ 379–697 sq ft |
| C WING | 65 | 57 | 0 | 3 | 5 | 34.88–58.09 sq m≈ 375–625 sq ft |
Different sizes are not necessarily different bedroom types. How we read and summarise the filing →
Unit Report
Understand its light, privacy, layout and surroundings. See how it compares with similar homes and other options in this project.
Didn’t help you decide? Full refund — no questions asked.
The same home number may appear in more than one building. Check both before choosing.
MahaRERA · per-home inventory · read 17 September 2026
| Home / building | Floor in the record | Carpet area | Reported status | Agreement value | Assess |
|---|---|---|---|---|---|
| A - 101A Wing - Podium and 3 Floors | 1 | 52.88 sq m≈ 569 sq ft | Sold | ₹5,500,000 | |
| A - 102A Wing - Podium and 3 Floors | 1 | 52.1 sq m≈ 561 sq ft | Sold | ₹4,498,000 | |
| A - 103A Wing - Podium and 3 Floors | 1 | 54.24 sq m≈ 584 sq ft | Sold | ₹5,652,663 | |
| A - 104A Wing - Podium and 3 Floors | 1 | 64.11 sq m≈ 690 sq ft | Sold | ₹6,500,000 | |
| A - 105A Wing - Podium and 3 Floors | 1 | 52.72 sq m≈ 567 sq ft | Sold | ₹4,498,500 | |
| A - 201A Wing - Podium and 3 Floors | 2 | 52.24 sq m≈ 562 sq ft | Sold | ₹5,063,000 | |
| A - 202A Wing - Podium and 3 Floors | 2 | 56.15 sq m≈ 604 sq ft | Sold | ₹5,116,000 | |
| A - 203A Wing - Podium and 3 Floors | 2 | 54.05 sq m≈ 582 sq ft | Sold | ₹5,353,600 | |
| A - 204A Wing - Podium and 3 Floors | 2 | 63.9 sq m≈ 688 sq ft | Sold | ₹5,729,333 | |
| A - 205A Wing - Podium and 3 Floors | 2 | 57.74 sq m≈ 622 sq ft | Not for sale | Not stated | |
| A - 301A Wing - Podium and 3 Floors | 3 | 52.31 sq m≈ 563 sq ft | Sold | ₹4,843,500 | |
| A - 302A Wing - Podium and 3 Floors | 3 | 55.88 sq m≈ 601 sq ft | Sold | ₹4,850,000 |
Read every entry in one table: Read the complete saved home list.
Choose the home you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.
More from the RERA documents
₹227,273,361 of an estimated ₹227,273,361 was reported as incurred (100.0%). This percentage is about costs. It does not show how much construction is complete.
MahaRERA project filing · read 19 July 2026 · registration P52100016985
Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.
| Building | Activity | Reported |
|---|---|---|
| B WING | Excavation | 100.0% |
| B WING | Basement (if any) | 100.0% |
| B WING | Podiums (if any) | 100.0% |
| B WING | Plinth | 100.0% |
| B WING | Stilt Floor | 0.0% |
| B WING | Slabs of Super Structure | 100.0% |
| B WING | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100.0% |
| B WING | Sanitary Fittings within the flats / premises | 100.0% |
| B WING | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100.0% |
| B WING | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100.0% |
| B WING | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100.0% |
| C WING | Excavation | 100.0% |
| C WING | Basement (if any) | 100.0% |
| C WING | Podiums (if any) | 100.0% |
| C WING | Plinth | 100.0% |
| C WING | Stilt Floor | 0.0% |
| C WING | Slabs of Super Structure | 100.0% |
| C WING | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100.0% |
| C WING | Sanitary Fittings within the flats / premises | 100.0% |
| C WING | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100.0% |
| C WING | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100.0% |
| C WING | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100.0% |
| A Wing - Podium and 3 Floors | Excavation | 100.0% |
| A Wing - Podium and 3 Floors | Basement (if any) | 100.0% |
| A Wing - Podium and 3 Floors | Podiums (if any) | 100.0% |
| A Wing - Podium and 3 Floors | Plinth | 100.0% |
| A Wing - Podium and 3 Floors | Stilt Floor | 0.0% |
| A Wing - Podium and 3 Floors | Slabs of Super Structure | 100.0% |
| A Wing - Podium and 3 Floors | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100.0% |
| A Wing - Podium and 3 Floors | Sanitary Fittings within the flats / premises | 100.0% |
| A Wing - Podium and 3 Floors | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100.0% |
| A Wing - Podium and 3 Floors | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 99.0% |
| A Wing - Podium and 3 Floors | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100.0% |
MahaRERA project filing · read 19 July 2026 · registration P52100016985
| Revised target | Reason given by the builder |
|---|---|
| 23 September 2024 | The delays are occurred as the there was shortage of Labour due to Various festivals like Holi, Eid etc. and as well as election was there so most of the labours were not available for work. In addition, one of our door vendors, whom we have given orders of doors, has closed their factory, and they failed to provide us the doors and related material on time. We have to shift to new vendor and get done the work. Our Fire Fighting vendor is also changed. Hence requesting for an extension for 3 months to complete the work. |
| 31 December 2025 | 1. Financial Issues • Labour unavailability due to delay in payments to suppliers of labours. The project was moving slow due to delayed payments to suppliers. Due to delay in payments, the contractors have allocated some other project work to the labours allotted to our site. • Material delivery issues due to delay in payments to suppliers. Since, there was delay in the payments to suppliers they were not ready to deliver the materials without advance payments. • Usage and repayment of Construction Finance: o Originally we have availed a construction finance for the project from Shri Sant Nagebaba Multistate Co-Operative Urban Credit Society Limited of Rs.3.55 Cr. The said finance was not sufficient for completion of the project hence we approached another financer who can provide more funding for the project. o Then, we got a fnance of Rs. 24.50 Cr from Capri Global Capital Limited and additional top up of Rs.13.00 Cr. They also closed the earlier loan from Shri Sant Nagebaba Multistate Co-Operative Urban Credit Society Limited. o Now, all the loans on the project are closed from the project receipts and No Dues from the financer are obtained. 2. Reason for Granting Extension • Part completion certificate is already obtained (98.50% i.e. 196 units out of 199 units) project completion from PCMC and e-mailed to MahaRERA Authority by Pimpri Chinchwad Muncipal Corporation. • Construction and finishing work is already completed for 3 units which were revised at a later date. Only completion certificate from the PCMC is pending and no balance cost or work is pending for these units. • Supporting Engineer Certificate, Architect Certificate and the physical progress photographs of these 3 units is enclosed for your reference. • As per Sec 7(3), promoter is required to obtain approval of 51% of the allottees. Considering the second extension beyond 1 year we have provided approval of 2/3rd allottees. • MahaRERA Authority has power to grant the extension in the interest of homebuyers and public confidence. • Possession is also handed over to the 196 allottees for whom completion certificate is already received. |
MahaRERA project filing · read 19 July 2026 · registration P52100016985
RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.
| Filing | Own funds | Borrowing | Payments from buyers | Total |
|---|---|---|---|---|
| Estimated plan | ₹117,944,128 | ₹30,000,000 | ₹316,528,188 | ₹464,472,316 |
| Actual raised | ₹140,440,504 | ₹0 | ₹320,738,859 | ₹461,179,363 |
MahaRERA project filing · read 19 July 2026 · registration P52100016985
31 elapsed quarterly periods in the captured compliance schedule. Active default was recorded for FY 2025-2026.
MahaRERA project filing · read 19 July 2026 · registration P52100016985
A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.
MahaRERA project filing · read 19 July 2026 · registration P52100016985
Builder and past records
Projects registered under this company
5Pune registrations
These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.
MahaRERA Pune registration records · read 12 July 2026
Past records of sales and unsold homes
25 September 2026
4 marked unsold · 122 sold · 0 booked.
Saved MahaRERA home list
17 September 2026
4 marked unsold · 122 sold · 0 booked.
Saved MahaRERA home list
8 September 2026
5 marked unsold · 117 sold · 5 booked.
Saved MahaRERA home list
19 July 2026
5 marked unsold · 117 sold · 5 booked.
Saved MahaRERA home list
These dates show when the records were saved, not when homes were sold. Sales may have changed since then, even if the saved counts are the same.
Project Comparison Report
Compare up to three projects. We read their plans and RERA documents, recommend homes in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.
2 projects · ₹7,999
3 projects · ₹9,999
Within 1 working day
Didn’t help you decide? Full refund — no questions asked.
Compare project details for free →MahaRERA · registration record · read 12 July 2026
MahaRERA · per-home inventory · read 17 September 2026
This is a past RERA home list, not current availability. It does not give the date each home was sold.
Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.
Open MahaRERA · search P52100016985 ↗