homeonpaper.

Builder’s RERA records,
explained for buyers.

The builder’s RERA record, explained

Optima 2.0

M/S. SOBA ASSOCIATES · P52100018793

MahaRERA · registration record · read 12 July 2026

Choose a report ↓

What does the RERA record show?

For Optima 2.0 (P52100018793), 11 of 177 entries were marked unsold in the MahaRERA unit list read 8 September 2026.

MahaRERA · per-unit inventory · read 8 September 2026

For Optima 2.0, ₹11,625 per sq ft of filed area is the median rate across 159 sold or booked entries with prices in the MahaRERA unit list read 8 September 2026. These are historical agreement values, not current asking prices.

MahaRERA · per-unit inventory · read 8 September 2026

These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.

What would help you decide?

Buyer’s Report

Understand this project

Find units to consider, with advice on light, layout, privacy and surroundings.

₹4,999

Unit Report

Check a particular unit

See its advantages, drawbacks and how it compares with other units in this project.

₹3,999

Project Comparison Report

Choose between projects

Compare two or three projects and get recommended units in order, with reasons for each choice.

From ₹7,999

Choose projects →

Project status and completion date.

Prices reported to RERA

What prices have been reported?

₹11,625/ sq ft filed area

Across 159 sold or booked entries with reported prices. The middle 80% of rates fall between ₹7,912 and ₹13,152.

MahaRERA · per-unit inventory · read 8 September 2026

How is this calculated?

For each sold or booked entry, we divide the reported agreement value by its filed area in square feet. The median is the middle rate when these rates are put in order. We show it only when at least five entries have prices. We exclude valuations of unsold units and government reference rates. The figures may include different sizes and property types. They are historical agreement values, not current asking prices or the total cost including extra charges.

Sales Report

What did similar units sell for?

Compare filed values by building, unit-number pattern and area. See which units were marked unsold on the date shown.

₹2,999 · delivered on payment

Inside this registered phase

How do the buildings compare in the record?

177 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.

MahaRERA · per-unit inventory · read 8 September 2026

Scroll sideways to see all columns.

Building names, sale status and filed areas — not current availability
Filed buildingEntriesSoldBookedMarked unsoldOther / unstated statusRecorded filed-area range
BUILDING -G918407055.56–320.00 sq m≈ 598–3,444 sq ft
BUILDING -H868024033.00–145.00 sq m≈ 355–1,561 sq ft

Area means carpet area for building units and plot area for plots. Size alone does not establish use or layout. How we read and summarise the filing →

Unit Report

Is this the right
unit for you?

Understand its light, privacy, layout and surroundings. See how it compares with similar units and other options in this project.

₹3,999 · 1 working day

Didn’t help you decide? Full refund — no questions asked.

Find your unit in the RERA list.

The same unit number may appear in more than one building. Check both before choosing.

177 listed entries

MahaRERA · per-unit inventory · read 8 September 2026

RERA unit list, not current availability
Unit / buildingFloor in the recordFiled areaReported statusAgreement valueAssess
1BUILDING -G / Wing NA205203.0 sq m≈ 2,185 sq ft · RERA carpet areaSold₹14,744,410
2BUILDING -G / Wing NA205262.0 sq m≈ 2,820 sq ft · RERA carpet areaSold₹19,029,730
3BUILDING -G / Wing NA205320.0 sq m≈ 3,444 sq ft · RERA carpet areaSold₹23,242,420
G- 1001BUILDING -G / Wing NA1078.41 sq m≈ 844 sq ft · RERA carpet areaMarked unsoldNot stated
G- 1002BUILDING -G / Wing NA1055.56 sq m≈ 598 sq ft · RERA carpet areaSold₹7,000,000
G- 1003BUILDING -G / Wing NA1055.56 sq m≈ 598 sq ft · RERA carpet areaSold₹4,900,000
G- 1004BUILDING -G / Wing NA1062.67 sq m≈ 675 sq ft · RERA carpet areaSold₹8,230,835
G- 1005BUILDING -G / Wing NA1062.67 sq m≈ 675 sq ft · RERA carpet areaSold₹7,566,935
G- 1006BUILDING -G / Wing NA1061.82 sq m≈ 665 sq ft · RERA carpet areaMarked unsoldNot stated
G- 1007BUILDING -G / Wing NA1061.82 sq m≈ 665 sq ft · RERA carpet areaSold₹8,991,053
G- 1008BUILDING -G / Wing NA1082.55 sq m≈ 889 sq ft · RERA carpet areaSold₹10,080,286
G- 101BUILDING -G / Wing NA178.41 sq m≈ 844 sq ft · RERA carpet areaSold₹10,688,776

Read every entry in one table: Read the complete saved unit list.

Choose the unit you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.

More from the RERA documents

Construction progress and project documents.

Cost reported as incurred

₹564,475,100 of an estimated ₹570,000,000 was reported as incurred (99.0%). This percentage is about costs. It does not show how much construction is complete.

MahaRERA project filing · read 19 July 2026 · registration P52100018793

Work reported, by building

Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.

See all reported activities
BuildingActivityReported
BUILDING -GExcavation100.0%
BUILDING -GBasement (if any)100.0%
BUILDING -GPodiums (if any) 100.0%
BUILDING -GPlinth100.0%
BUILDING -GStilt Floor 100.0%
BUILDING -GSlabs of Super Structure100.0%
BUILDING -GInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100.0%
BUILDING -GSanitary Fittings within the flats / premises50.0%
BUILDING -GStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100.0%
BUILDING -GExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100.0%
BUILDING -GInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.75.0%
BUILDING -HExcavation100.0%
BUILDING -HBasement (if any)100.0%
BUILDING -HPodiums (if any) 100.0%
BUILDING -HPlinth100.0%
BUILDING -HStilt Floor 100.0%
BUILDING -HSlabs of Super Structure100.0%
BUILDING -HInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100.0%
BUILDING -HSanitary Fittings within the flats / premises50.0%
BUILDING -HStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100.0%
BUILDING -HExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100.0%
BUILDING -HInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.75.0%

MahaRERA project filing · read 19 July 2026 · registration P52100018793

Reported deadline extensions

Revised targetReason given by the builder
31 December 2026The Applicant respectfully submits that since April 2025, the pace of construction has been adversely affected, and certain works could not be commenced due to serious obstruction in road access to the project site. The Pune Municipal Corporation (PMC) has undertaken work in front of the project site, resulting in the creation of a large ditch, which has completely obstructed ingress and egress. Due to the said obstruction, transportation of construction materials has become extremely difficult, making it practically impossible to carry out the balance work. The Applicant has made several representations to PMC, requesting urgent restoration of access. Copies of the following letters are annexed herewith for reference

MahaRERA project filing · read 19 July 2026 · registration P52100018793

Where the project funding comes from

RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.

FilingOwn fundsBorrowingPayments from buyersTotal
Estimated plan₹15,000,000₹300,000,000₹268,800,000₹583,800,000
Actual raised₹0₹15,831,646₹715,962,646₹731,794,292

MahaRERA project filing · read 19 July 2026 · registration P52100018793

Quarterly filing record

31 elapsed quarterly periods in the captured compliance schedule. Active default was recorded for FY 2025-2026.

MahaRERA project filing · read 19 July 2026 · registration P52100018793

Documents named in the filing

  • Promoter PAN · 1 listed
  • Commencement certificate · 4 listed
  • Form 3 — CA certificate · 7 listed
  • Form 2 — Engineer's certificate · 6 listed
  • Title / search report · 2 listed
  • Form B — Promoter declaration · 1 listed
  • Sanctioned layout plan · 4 listed
  • Sanctioned building plan · 18 listed
  • Form 1 — Architect's certificate · 4 listed

A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.

MahaRERA project filing · read 19 July 2026 · registration P52100018793

Builder and past records

What else does the record show?

Projects registered under this company

M/S. SOBA ASSOCIATES

1Pune registrations

These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.

MahaRERA Pune registration records · read 12 July 2026

Explore other registrations

    Past records of sales and unsold units

    1. 26 September 2026

      11 marked unsold · 164 sold · 2 booked.

      Saved MahaRERA unit list

    2. 17 September 2026

      11 marked unsold · 164 sold · 2 booked.

      Saved MahaRERA unit list

    3. 8 September 2026

      11 marked unsold · 164 sold · 2 booked.

      Saved MahaRERA unit list

    4. 19 July 2026

      14 marked unsold · 162 sold · 1 booked.

      Saved MahaRERA unit list

    These dates show when the records were saved, not when units were sold. Sales may have changed since then, even if the saved counts are the same.

    Project Comparison Report

    Which project should you buy in?
    And which unit?

    Compare up to three projects. We read their plans and RERA documents, recommend units in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.

    Create my Comparison Report →

    2 projects · ₹7,999
    3 projects · ₹9,999

    Within 1 working day

    Didn’t help you decide? Full refund — no questions asked.

    Compare project details for free →

    Sources and dates.

    MahaRERA · registration record · read 12 July 2026

    MahaRERA · per-unit inventory · read 8 September 2026

    This is a past RERA unit list, not current availability. It does not give the date each unit was sold.

    Filed area means carpet area for building units and plot area for plots. Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.

    Open MahaRERA · search P52100018793 ↗