The builder’s RERA record, explained

Akshay Anantam

Sneh Constructions · P52100018878

MahaRERA · registration record · read 12 July 2026

Choose a report ↓

What does the RERA record show?

For Akshay Anantam (P52100018878), 35 of 194 entries were marked unsold in the MahaRERA home list dated 18 July 2026 (saved-file date).

MahaRERA · per-home inventory · saved-file date 18 July 2026

For Akshay Anantam, ₹11,090 per sq ft of carpet area is the median rate across 159 sold or booked entries with prices in the MahaRERA home list dated 18 July 2026 (saved-file date). These are historical agreement values, not current asking prices.

MahaRERA · per-home inventory · saved-file date 18 July 2026

These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.

What would help you decide?

Buyer’s Report

Understand this project

Find homes to consider, with advice on light, layout, privacy and surroundings.

₹4,999

Unit Report

Check a particular home

See its advantages, drawbacks and how it compares with other homes in this project.

₹3,999

Project Comparison Report

Choose between projects

Compare two or three projects and get recommended homes in order, with reasons for each choice.

From ₹7,999

Choose projects →

Project status and completion date.

Prices reported to RERA

What prices have been reported?

₹11,090/ sq ft carpet area

Across 159 sold or booked entries with reported prices. The middle 80% of rates fall between ₹9,033 and ₹13,487.

MahaRERA · per-home inventory · saved-file date 18 July 2026

How is this calculated?

For each sold or booked entry, we divide the reported agreement value by its carpet area in square feet. The median is the middle rate when these rates are put in order. We show it only when at least five entries have prices. We exclude valuations of unsold homes and government reference rates. The figures may include different sizes and property types. They are historical agreement values, not current asking prices or the total cost including extra charges.

Sales Report

What did similar homes sell for?

Compare reported agreement values by building, size and floor. See which homes were marked unsold on the date shown.

₹2,999 · delivered on payment

Inside this registered phase

How do the buildings compare in the record?

194 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.

MahaRERA · per-home inventory · saved-file date 18 July 2026

Scroll sideways to see all columns.

Building names, sale status and carpet areas — not current availability
Filed buildingEntriesSoldBookedMarked unsoldOther / unstated statusRecorded carpet-area range
Building A908901021.63–73.75 sq m≈ 233–794 sq ft
Building B10470034013.92–51.66 sq m≈ 150–556 sq ft

Different sizes are not necessarily different bedroom types. How we read and summarise the filing →

Unit Report

Is this the right
home for you?

Understand its light, privacy, layout and surroundings. See how it compares with similar homes and other options in this project.

₹3,999 · 1 working day

Didn’t help you decide? Full refund — no questions asked.

Find your home in the RERA list.

The same home number may appear in more than one building. Check both before choosing.

194 listed entries

MahaRERA · per-home inventory · saved-file date 18 July 2026

RERA home list, not current availability
Home / buildingFloor in the recordCarpet areaReported statusAgreement valueAssess
1001Building A1045.96 sq m≈ 495 sq ftSold₹4,499,000
1002Building A1043.36 sq m≈ 467 sq ftSold₹5,101,160
1003Building A1025.53 sq m≈ 275 sq ftSold₹3,768,247
1004Building A1021.63 sq m≈ 233 sq ftSold₹2,470,518
1005Building A1021.63 sq m≈ 233 sq ftSold₹3,236,700
1006Building A1025.53 sq m≈ 275 sq ftSold₹3,033,748
1007Building A1042.0 sq m≈ 452 sq ftSold₹5,482,000
1008Building A1044.43 sq m≈ 478 sq ftSold₹4,643,475
101Building A145.87 sq m≈ 494 sq ftSold₹4,460,000
102Building A143.29 sq m≈ 466 sq ftSold₹4,460,000
103Building A125.53 sq m≈ 275 sq ftSold₹3,692,799
104Building A121.63 sq m≈ 233 sq ftSold₹3,310,000

Read every entry in one table: Read the complete saved home list.

Choose the home you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.

More from the RERA documents

Construction progress and project documents.

Cost reported as incurred

₹318,520,000 of an estimated ₹386,250,000 was reported as incurred (82.5%). This percentage is about costs. It does not show how much construction is complete.

MahaRERA project filing · read 19 July 2026 · registration P52100018878

Work reported, by building

Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.

See all reported activities
BuildingActivityReported
Building AExcavation100.0%
Building ABasement (if any)100.0%
Building APodiums (if any) 100.0%
Building APlinth100.0%
Building AStilt Floor 100.0%
Building ASlabs of Super Structure100.0%
Building AInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises75.0%
Building ASanitary Fittings within the flats / premises99.0%
Building AStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks99.0%
Building AExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.99.0%
Building AInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.99.0%
Building BExcavation100.0%
Building BBasement (if any)100.0%
Building BPodiums (if any) 0.0%
Building BPlinth100.0%
Building BStilt Floor 0.0%
Building BSlabs of Super Structure95.0%
Building BInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises69.0%
Building BSanitary Fittings within the flats / premises65.0%
Building BStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks65.0%
Building BExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50.0%
Building BInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20.0%

MahaRERA project filing · read 19 July 2026 · registration P52100018878

Reported deadline extensions

Revised targetReason given by the builder
27 August 2024In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19.
27 August 2025In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 54.68% allottees for purpose of extension of RERA registration period of the said project.
31 March 2026We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. Given the circumstances, we kindly request an extension until 31-03-2026, to complete the project and fulfil all regulatory requirements.
31 March 2028Construction of Wing A has been completed in all respects and possession has been handed over to the allottees. Further, approximately 80% construction work of Wing B has also been completed and possession has been handed over for the completed units; however, approvals/sanctions for certain units are still pending before the competent authority. Due to the said procedural pendency, which is beyond the control of the Promoter, the Completion/Occupancy Certificate could not be obtained. Therefore humbly requests the Hon’ble Authority to grant an extension of registration up to 31/03/2028 for completion of the remaining project formalities, including obtaining the Occupancy Certificate.

MahaRERA project filing · read 19 July 2026 · registration P52100018878

Where the project funding comes from

RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.

FilingOwn fundsBorrowingPayments from buyersTotal
Estimated plan₹50,000,000₹40,000,000₹240,799,650₹480,799,650
Actual raised₹0₹60,000,000₹337,811,903₹487,811,903

MahaRERA project filing · read 19 July 2026 · registration P52100018878

Quarterly filing record

30 elapsed quarterly periods in the captured compliance schedule. No active quarterly default was recorded in this snapshot.

MahaRERA project filing · read 19 July 2026 · registration P52100018878

Documents named in the filing

  • Promoter PAN · 1 listed
  • Form 1 — Architect's certificate · 1 listed
  • Form 3 — CA certificate · 5 listed
  • Form 2 — Engineer's certificate · 5 listed
  • Title / search report · 4 listed
  • Form B — Promoter declaration · 3 listed
  • Sanctioned building plan · 30 listed
  • Sanctioned layout plan · 3 listed

A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.

MahaRERA project filing · read 19 July 2026 · registration P52100018878

Builder and past records

What else does the record show?

Projects registered under this company

Sneh Constructions

1Pune registrations

These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.

MahaRERA Pune registration records · read 12 July 2026

Explore other registrations

    Past records of sales and unsold homes

    1. 26 September 2026

      35 marked unsold · 159 sold · 0 booked.

      Saved MahaRERA home list

    2. 17 September 2026

      35 marked unsold · 159 sold · 0 booked.

      Saved MahaRERA home list

    3. 8 September 2026

      35 marked unsold · 159 sold · 0 booked.

      Saved MahaRERA home list

    4. 19 July 2026

      35 marked unsold · 159 sold · 0 booked.

      Saved MahaRERA home list

    These dates show when the records were saved, not when homes were sold. Sales may have changed since then, even if the saved counts are the same.

    Project Comparison Report

    Which project should you buy in?
    And which home?

    Compare up to three projects. We read their plans and RERA documents, recommend homes in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.

    Create my Comparison Report →

    2 projects · ₹7,999
    3 projects · ₹9,999

    Within 1 working day

    Didn’t help you decide? Full refund — no questions asked.

    Compare project details for free →

    Sources and dates.

    MahaRERA · registration record · read 12 July 2026

    MahaRERA · per-home inventory · saved-file date 18 July 2026

    This is a past RERA home list, not current availability. It does not give the date each home was sold.

    The home-list date is based on the saved file’s details.

    Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.

    Open MahaRERA · search P52100018878 ↗