homeonpaper.

Builder’s RERA records,
explained for buyers.

The builder’s RERA record, explained

Dwarikadham

Yashodhan Affordable Landmark LLP · P52100019278

MahaRERA · registration record · read 12 July 2026

Choose a report ↓

What does the RERA record show?

For Dwarikadham (P52100019278), 533 of 1135 entries were marked unsold in the MahaRERA unit list dated 18 July 2026 (saved-file date).

MahaRERA · per-unit inventory · saved-file date 18 July 2026

For Dwarikadham, ₹5,895 per sq ft of filed area is the median rate across 600 sold or booked entries with prices in the MahaRERA unit list dated 18 July 2026 (saved-file date). These are historical agreement values, not current asking prices.

MahaRERA · per-unit inventory · saved-file date 18 July 2026

These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.

What would help you decide?

Buyer’s Report

Understand this project

Find units to consider, with advice on light, layout, privacy and surroundings.

₹4,999

Unit Report

Check a particular unit

See its advantages, drawbacks and how it compares with other units in this project.

₹3,999

Project Comparison Report

Choose between projects

Compare two or three projects and get recommended units in order, with reasons for each choice.

From ₹7,999

Choose projects →

Project status and completion date.

Prices reported to RERA

What prices have been reported?

₹5,895/ sq ft filed area

Across 600 sold or booked entries with reported prices. The middle 80% of rates fall between ₹5,019 and ₹6,679.

MahaRERA · per-unit inventory · saved-file date 18 July 2026

How is this calculated?

For each sold or booked entry, we divide the reported agreement value by its filed area in square feet. The median is the middle rate when these rates are put in order. We show it only when at least five entries have prices. We exclude valuations of unsold units and government reference rates. The figures may include different sizes and property types. They are historical agreement values, not current asking prices or the total cost including extra charges.

Sales Report

What did similar units sell for?

Compare filed values by building, unit-number pattern and area. See which units were marked unsold on the date shown.

₹2,999 · delivered on payment

Inside this registered phase

How do the buildings compare in the record?

1135 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.

MahaRERA · per-unit inventory · saved-file date 18 July 2026

Scroll sideways to see all columns.

Building names, sale status and filed areas — not current availability
Filed buildingEntriesSoldBookedMarked unsoldOther / unstated statusRecorded filed-area range
1707000040.13 sq m≈ 432 sq ft
2707000040.13 sq m≈ 432 sq ft
3707000040.13 sq m≈ 432 sq ft
4707000040.13 sq m≈ 432 sq ft
511211200065.96–67.81 sq m≈ 710–730 sq ft
611211200065.96–67.81 sq m≈ 710–730 sq ft
715270145070.60–113.52 sq m≈ 760–1,222 sq ft
8A7600760102.93–143.62 sq m≈ 1,108–1,546 sq ft
8B7610750102.93–143.62 sq m≈ 1,108–1,546 sq ft
9152330119070.51–113.52 sq m≈ 759–1,222 sq ft
Dwarika Dham Commerce Park444400025.91–26.94 sq m≈ 279–290 sq ft
LIG/MIG131130118040.13 sq m≈ 432 sq ft

Area means carpet area for building units and plot area for plots. Size alone does not establish use or layout. How we read and summarise the filing →

Unit Report

Is this the right
unit for you?

Understand its light, privacy, layout and surroundings. See how it compares with similar units and other options in this project.

₹3,999 · 1 working day

Didn’t help you decide? Full refund — no questions asked.

Find your unit in the RERA list.

The same unit number may appear in more than one building. Check both before choosing.

1135 listed entries

MahaRERA · per-unit inventory · saved-file date 18 July 2026

RERA unit list, not current availability
Unit / buildingFloor in the recordFiled areaReported statusAgreement valueAssess
1011 / Wing NA140.13 sq m≈ 432 sq ft · RERA carpet areaSold₹1,903,600
1021 / Wing NA140.13 sq m≈ 432 sq ft · RERA carpet areaSold₹2,600,000
1031 / Wing NA140.13 sq m≈ 432 sq ft · RERA carpet areaSold₹2,808,000
1041 / Wing NA140.13 sq m≈ 432 sq ft · RERA carpet areaSold₹2,401,000
1051 / Wing NA140.13 sq m≈ 432 sq ft · RERA carpet areaSold₹2,384,700
1061 / Wing NA140.13 sq m≈ 432 sq ft · RERA carpet areaSold₹2,384,700
1071 / Wing NA140.13 sq m≈ 432 sq ft · RERA carpet areaSold₹2,271,000
1081 / Wing NA140.13 sq m≈ 432 sq ft · RERA carpet areaSold₹2,649,000
1091 / Wing NA140.13 sq m≈ 432 sq ft · RERA carpet areaSold₹2,649,000
1101 / Wing NA140.13 sq m≈ 432 sq ft · RERA carpet areaSold₹2,597,000
2011 / Wing NA240.13 sq m≈ 432 sq ft · RERA carpet areaSold₹2,500,000
2021 / Wing NA240.13 sq m≈ 432 sq ft · RERA carpet areaSold₹2,600,000

Read every entry in one table: Read the complete saved unit list.

Choose the unit you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.

More from the RERA documents

Construction progress and project documents.

Cost reported as incurred

₹6,870,037,987 of an estimated ₹15,950,000,000 was reported as incurred (43.1%). This percentage is about costs. It does not show how much construction is complete.

MahaRERA project filing · read 19 July 2026 · registration P52100019278

Work reported, by building

Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.

See all reported activities
BuildingActivityReported
1Excavation100.0%
1Basement (if any)0.0%
1Podiums (if any) 0.0%
1Plinth100.0%
1Stilt Floor 100.0%
1Slabs of Super Structure100.0%
1Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100.0%
1Sanitary Fittings within the flats / premises100.0%
1Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100.0%
1External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100.0%
1Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100.0%
2Excavation100.0%
2Basement (if any)0.0%
2Podiums (if any) 0.0%
2Plinth100.0%
2Stilt Floor 100.0%
2Slabs of Super Structure100.0%
2Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100.0%
2Sanitary Fittings within the flats / premises100.0%
2Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100.0%
2External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100.0%
2Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100.0%
3Excavation100.0%
3Basement (if any)0.0%
3Podiums (if any) 0.0%
3Plinth100.0%
3Stilt Floor 100.0%
3Slabs of Super Structure100.0%
3Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100.0%
3Sanitary Fittings within the flats / premises100.0%
3Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100.0%
3External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100.0%
3Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100.0%
4Excavation100.0%
4Basement (if any)0.0%
4Podiums (if any) 0.0%
4Plinth100.0%
4Stilt Floor 100.0%
4Slabs of Super Structure100.0%
4Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100.0%
4Sanitary Fittings within the flats / premises100.0%
4Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100.0%
4External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100.0%
4Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100.0%
5Excavation100.0%
5Basement (if any)0.0%
5Podiums (if any) 0.0%
5Plinth100.0%
5Stilt Floor 100.0%
5Slabs of Super Structure100.0%
5Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100.0%
5Sanitary Fittings within the flats / premises100.0%
5Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100.0%
5External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100.0%
5Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100.0%
6Excavation100.0%
6Basement (if any)0.0%
6Podiums (if any) 0.0%
6Plinth100.0%
6Stilt Floor 100.0%
6Slabs of Super Structure100.0%
6Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100.0%
6Sanitary Fittings within the flats / premises100.0%
6Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100.0%
6External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100.0%
6Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100.0%
7Excavation100.0%
7Basement (if any)0.0%
7Podiums (if any) 65.0%
7Plinth0.0%
7Stilt Floor 0.0%
7Slabs of Super Structure0.0%
7Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
7Sanitary Fittings within the flats / premises0.0%
7Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks5.0%
7External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
7Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
8AExcavation100.0%
8ABasement (if any)0.0%
8APodiums (if any) 65.0%
8APlinth0.0%
8AStilt Floor 0.0%
8ASlabs of Super Structure0.0%
8AInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
8ASanitary Fittings within the flats / premises0.0%
8AStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks5.0%
8AExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
8AInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
9Excavation100.0%
9Basement (if any)0.0%
9Podiums (if any) 65.0%
9Plinth0.0%
9Stilt Floor 0.0%
9Slabs of Super Structure0.0%
9Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
9Sanitary Fittings within the flats / premises0.0%
9Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks5.0%
9External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
9Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
8BExcavation100.0%
8BBasement (if any)0.0%
8BPodiums (if any) 65.0%
8BPlinth0.0%
8BStilt Floor 0.0%
8BSlabs of Super Structure0.0%
8BInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
8BSanitary Fittings within the flats / premises0.0%
8BStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks5.0%
8BExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
8BInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
LIG/MIGExcavation100.0%
LIG/MIGBasement (if any)0.0%
LIG/MIGPodiums (if any) 0.0%
LIG/MIGPlinth100.0%
LIG/MIGStilt Floor 100.0%
LIG/MIGSlabs of Super Structure100.0%
LIG/MIGInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100.0%
LIG/MIGSanitary Fittings within the flats / premises50.0%
LIG/MIGStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100.0%
LIG/MIGExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100.0%
LIG/MIGInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95.0%
Dwarika Dham Commerce ParkExcavation100.0%
Dwarika Dham Commerce ParkBasement (if any)0.0%
Dwarika Dham Commerce ParkPodiums (if any) 0.0%
Dwarika Dham Commerce ParkPlinth100.0%
Dwarika Dham Commerce ParkStilt Floor 100.0%
Dwarika Dham Commerce ParkSlabs of Super Structure100.0%
Dwarika Dham Commerce ParkInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100.0%
Dwarika Dham Commerce ParkSanitary Fittings within the flats / premises100.0%
Dwarika Dham Commerce ParkStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100.0%
Dwarika Dham Commerce ParkExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100.0%
Dwarika Dham Commerce ParkInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100.0%

MahaRERA project filing · read 19 July 2026 · registration P52100019278

Reported deadline extensions

Revised targetReason given by the builder
30 June 2028Project was registered as whole and not in phase wise manner. Phase 1 and Phase 2 have been allotted to buyers out of which phase 1 and Tower 5 of phase 2 has received OC and other buildings of phase 2 are within stipulated time period as committed to buyers. We require extension for phase 3 where no units have yet been sold. Kindly grant us the extension.

MahaRERA project filing · read 19 July 2026 · registration P52100019278

Where the project funding comes from

RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.

FilingOwn fundsBorrowingPayments from buyersTotal
Estimated plan₹1,641,039,409₹0₹1,452,437,991₹3,093,477,400
Actual raised₹530,094,898₹0₹1,452,437,991₹1,982,532,889

MahaRERA project filing · read 19 July 2026 · registration P52100019278

Quarterly filing record

29 elapsed quarterly periods in the captured compliance schedule. No active quarterly default was recorded in this snapshot.

MahaRERA project filing · read 19 July 2026 · registration P52100019278

Documents named in the filing

  • Commencement certificate · 2 listed
  • Promoter PAN · 1 listed
  • Form 1 — Architect's certificate · 12 listed
  • Form 3 — CA certificate · 9 listed
  • Form 2 — Engineer's certificate · 8 listed
  • Form B — Promoter declaration · 2 listed
  • Title / search report · 1 listed
  • Sanctioned layout plan · 3 listed
  • Sanctioned building plan · 11 listed
  • Occupancy / completion certificate · 1 listed

A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.

MahaRERA project filing · read 19 July 2026 · registration P52100019278

Builder and past records

What else does the record show?

Projects registered under this company

Yashodhan Affordable Landmark LLP

1Pune registrations

These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.

MahaRERA Pune registration records · read 12 July 2026

Explore other registrations

    Past records of sales and unsold units

    1. 26 September 2026

      533 marked unsold · 602 sold · 0 booked.

      Saved MahaRERA unit list

    2. 17 September 2026

      533 marked unsold · 602 sold · 0 booked.

      Saved MahaRERA unit list

    3. 8 September 2026

      533 marked unsold · 602 sold · 0 booked.

      Saved MahaRERA unit list

    4. 19 July 2026

      533 marked unsold · 602 sold · 0 booked.

      Saved MahaRERA unit list

    These dates show when the records were saved, not when units were sold. Sales may have changed since then, even if the saved counts are the same.

    Project Comparison Report

    Which project should you buy in?
    And which unit?

    Compare up to three projects. We read their plans and RERA documents, recommend units in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.

    Create my Comparison Report →

    2 projects · ₹7,999
    3 projects · ₹9,999

    Within 1 working day

    Didn’t help you decide? Full refund — no questions asked.

    Compare project details for free →

    Sources and dates.

    MahaRERA · registration record · read 12 July 2026

    MahaRERA · per-unit inventory · saved-file date 18 July 2026

    This is a past RERA unit list, not current availability. It does not give the date each unit was sold.

    The unit-list date is based on the saved file’s details.

    Filed area means carpet area for building units and plot area for plots. Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.

    Open MahaRERA · search P52100019278 ↗
    homeonpaper