The builder’s RERA record, explained
ROHAN BUILDERS & DEVELOPERS PRIVATE LIMITED · P52100019997
For ROHAN ANANTA PHASE III (P52100019997), 5 of 435 entries were marked unsold in the MahaRERA home list dated 18 July 2026 (saved-file date).
MahaRERA · per-home inventory · saved-file date 18 July 2026
For ROHAN ANANTA PHASE III, ₹8,927 per sq ft of carpet area is the median rate across 430 sold or booked entries with prices in the MahaRERA home list dated 18 July 2026 (saved-file date). These are historical agreement values, not current asking prices.
MahaRERA · per-home inventory · saved-file date 18 July 2026
These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.
Builder’s completion target
This target date has passed. The record shown here does not confirm whether the project is complete or has received more time.
Status shown on RERA
This is the status shown on RERA. It does not confirm an occupancy certificate or today’s construction progress.
Prices reported to RERA
₹8,927/ sq ft carpet area
Across 430 sold or booked entries with reported prices. The middle 80% of rates fall between ₹4,236 and ₹10,250.
MahaRERA · per-home inventory · saved-file date 18 July 2026
For each sold or booked entry, we divide the reported agreement value by its carpet area in square feet. The median is the middle rate when these rates are put in order. We show it only when at least five entries have prices. We exclude valuations of unsold homes and government reference rates. The figures may include different sizes and property types. They are historical agreement values, not current asking prices or the total cost including extra charges.
Sales Report
Compare reported agreement values by building, size and floor. See which homes were marked unsold on the date shown.
Inside this registered phase
435 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.
MahaRERA · per-home inventory · saved-file date 18 July 2026
Scroll sideways to see all columns.
| Filed building | Entries | Sold | Booked | Marked unsold | Other / unstated status | Recorded carpet-area range |
|---|---|---|---|---|---|---|
| WING B1 | 84 | 84 | 0 | 0 | 0 | 54.00–59.86 sq m≈ 581–644 sq ft |
| WING B2 | 84 | 84 | 0 | 0 | 0 | 54.09–55.87 sq m≈ 582–601 sq ft |
| WING B3 | 84 | 84 | 0 | 0 | 0 | 35.49–59.54 sq m≈ 382–641 sq ft |
| WING B4 | 86 | 86 | 0 | 0 | 0 | 29.03–32.78 sq m≈ 312–353 sq ft |
| WING C | 97 | 92 | 0 | 5 | 0 | 47.04–50.49 sq m≈ 506–543 sq ft |
Different sizes are not necessarily different bedroom types. How we read and summarise the filing →
Unit Report
Understand its light, privacy, layout and surroundings. See how it compares with similar homes and other options in this project.
Didn’t help you decide? Full refund — no questions asked.
The same home number may appear in more than one building. Check both before choosing.
MahaRERA · per-home inventory · saved-file date 18 July 2026
| Home / building | Floor in the record | Carpet area | Reported status | Agreement value | Assess |
|---|---|---|---|---|---|
| B1-1001WING B1 | 10 | 54.04 sq m≈ 582 sq ft | Sold | ₹6,256,200 | |
| B1-1002WING B1 | 10 | 55.58 sq m≈ 598 sq ft | Sold | ₹5,373,200 | |
| B1-1003WING B1 | 10 | 55.5 sq m≈ 597 sq ft | Sold | ₹5,297,500 | |
| B1-1004WING B1 | 10 | 59.82 sq m≈ 644 sq ft | Sold | ₹5,750,400 | |
| B1-1005WING B1 | 10 | 59.66 sq m≈ 642 sq ft | Sold | ₹5,644,600 | |
| B1-1006WING B1 | 10 | 54.0 sq m≈ 581 sq ft | Sold | ₹5,184,000 | |
| B1-1007WING B1 | 10 | 54.4 sq m≈ 586 sq ft | Sold | ₹5,286,900 | |
| B1-1008WING B1 | 10 | 59.86 sq m≈ 644 sq ft | Sold | ₹5,973,600 | |
| B1-101WING B1 | 1 | 54.04 sq m≈ 582 sq ft | Sold | ₹5,931,000 | |
| B1-102WING B1 | 1 | 55.69 sq m≈ 599 sq ft | Sold | ₹5,985,700 | |
| B1-103WING B1 | 1 | 55.5 sq m≈ 597 sq ft | Sold | ₹5,281,100 | |
| B1-104WING B1 | 1 | 59.66 sq m≈ 642 sq ft | Sold | ₹5,558,700 |
Read every entry in one table: Read the complete saved home list.
Choose the home you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.
More from the RERA documents
₹1,045,799,999 of an estimated ₹1,008,100,000 was reported as incurred (103.7%). This percentage is about costs. It does not show how much construction is complete.
MahaRERA project filing · read 19 July 2026 · registration P52100019997
Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.
| Building | Activity | Reported |
|---|---|---|
| WING B1 | Excavation | 100.0% |
| WING B1 | Basement (if any) | 100.0% |
| WING B1 | Podiums (if any) | 100.0% |
| WING B1 | Plinth | 100.0% |
| WING B1 | Stilt Floor | 0.0% |
| WING B1 | Slabs of Super Structure | 100.0% |
| WING B1 | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100.0% |
| WING B1 | Sanitary Fittings within the flats / premises | 100.0% |
| WING B1 | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100.0% |
| WING B1 | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100.0% |
| WING B1 | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100.0% |
| WING B2 | Excavation | 100.0% |
| WING B2 | Basement (if any) | 100.0% |
| WING B2 | Podiums (if any) | 100.0% |
| WING B2 | Plinth | 100.0% |
| WING B2 | Stilt Floor | 0.0% |
| WING B2 | Slabs of Super Structure | 100.0% |
| WING B2 | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100.0% |
| WING B2 | Sanitary Fittings within the flats / premises | 100.0% |
| WING B2 | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100.0% |
| WING B2 | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100.0% |
| WING B2 | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100.0% |
| WING B3 | Excavation | 100.0% |
| WING B3 | Basement (if any) | 100.0% |
| WING B3 | Podiums (if any) | 100.0% |
| WING B3 | Plinth | 100.0% |
| WING B3 | Stilt Floor | 0.0% |
| WING B3 | Slabs of Super Structure | 100.0% |
| WING B3 | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100.0% |
| WING B3 | Sanitary Fittings within the flats / premises | 100.0% |
| WING B3 | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100.0% |
| WING B3 | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100.0% |
| WING B3 | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100.0% |
| WING B4 | Excavation | 100.0% |
| WING B4 | Basement (if any) | 100.0% |
| WING B4 | Podiums (if any) | 100.0% |
| WING B4 | Plinth | 100.0% |
| WING B4 | Stilt Floor | 0.0% |
| WING B4 | Slabs of Super Structure | 100.0% |
| WING B4 | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100.0% |
| WING B4 | Sanitary Fittings within the flats / premises | 100.0% |
| WING B4 | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100.0% |
| WING B4 | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100.0% |
| WING B4 | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100.0% |
| WING C | Excavation | 100.0% |
| WING C | Basement (if any) | 100.0% |
| WING C | Podiums (if any) | 100.0% |
| WING C | Plinth | 100.0% |
| WING C | Stilt Floor | 0.0% |
| WING C | Slabs of Super Structure | 100.0% |
| WING C | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100.0% |
| WING C | Sanitary Fittings within the flats / premises | 100.0% |
| WING C | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100.0% |
| WING C | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100.0% |
| WING C | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100.0% |
MahaRERA project filing · read 19 July 2026 · registration P52100019997
RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.
| Filing | Own funds | Borrowing | Payments from buyers | Total |
|---|---|---|---|---|
| Estimated plan | ₹70,000,000 | ₹350,000,000 | ₹850,500,000 | ₹1,270,500,000 |
| Actual raised | ₹406,207,628 | ₹10,004,387 | ₹1,265,387,985 | ₹1,681,600,000 |
MahaRERA project filing · read 19 July 2026 · registration P52100019997
29 elapsed quarterly periods in the captured compliance schedule. Active default was recorded for FY 2025-2026.
MahaRERA project filing · read 19 July 2026 · registration P52100019997
A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.
MahaRERA project filing · read 19 July 2026 · registration P52100019997
Builder and past records
Projects registered under this company
28Pune registrations
These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.
MahaRERA Pune registration records · read 2 July 2026 – 10 September 2026
Past records of sales and unsold homes
26 September 2026
5 marked unsold · 430 sold · 0 booked.
Saved MahaRERA home list
17 September 2026
5 marked unsold · 430 sold · 0 booked.
Saved MahaRERA home list
8 September 2026
5 marked unsold · 430 sold · 0 booked.
Saved MahaRERA home list
19 July 2026
5 marked unsold · 430 sold · 0 booked.
Saved MahaRERA home list
These dates show when the records were saved, not when homes were sold. Sales may have changed since then, even if the saved counts are the same.
More projects to explore
These projects list the same locality. They may differ in exact location, home type and price.
Tathawade · Pune
P52100032772
3 of 144 entries marked unsold
MahaRERA · per-home inventory · saved-file date 18 July 2026
View project details →Tathawade · Pune
P52100029844
10 of 233 entries marked unsold
MahaRERA · per-home inventory · saved-file date 18 July 2026
View project details →Tathawade · Pune
P52100066556
94 of 334 entries marked unsold
MahaRERA · per-home inventory · saved-file date 18 July 2026
View project details →Project Comparison Report
Compare up to three projects. We read their plans and RERA documents, recommend homes in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.
2 projects · ₹7,999
3 projects · ₹9,999
Within 1 working day
Didn’t help you decide? Full refund — no questions asked.
Compare project details for free →MahaRERA · registration record · read 12 July 2026
MahaRERA · per-home inventory · saved-file date 18 July 2026
This is a past RERA home list, not current availability. It does not give the date each home was sold.
The home-list date is based on the saved file’s details.
Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.
Open MahaRERA · search P52100019997 ↗