The builder’s RERA record, explained
Reelicon Red Homes Private Limited · P52100020477
For Reelicon Fairy Bell (P52100020477), 56 of 161 entries were marked unsold in the MahaRERA home list dated 18 July 2026 (saved-file date).
MahaRERA · per-home inventory · saved-file date 18 July 2026
For Reelicon Fairy Bell, ₹7,469 per sq ft of carpet area is the median rate across 66 sold or booked entries with prices in the MahaRERA home list dated 18 July 2026 (saved-file date). These are historical agreement values, not current asking prices.
MahaRERA · per-home inventory · saved-file date 18 July 2026
These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.
Builder’s completion target
The builder reported this target date. It is not a confirmed handover date.
Status shown on RERA
This is the status shown on RERA. It does not confirm an occupancy certificate or today’s construction progress.
Prices reported to RERA
₹7,469/ sq ft carpet area
Across 66 sold or booked entries with reported prices. The middle 80% of rates fall between ₹6,984 and ₹9,769.
MahaRERA · per-home inventory · saved-file date 18 July 2026
For each sold or booked entry, we divide the reported agreement value by its carpet area in square feet. The median is the middle rate when these rates are put in order. We show it only when at least five entries have prices. We exclude valuations of unsold homes and government reference rates. The figures may include different sizes and property types. They are historical agreement values, not current asking prices or the total cost including extra charges.
Sales Report
Compare reported agreement values by building, size and floor. See which homes were marked unsold on the date shown.
Inside this registered phase
161 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.
MahaRERA · per-home inventory · saved-file date 18 July 2026
Scroll sideways to see all columns.
| Filed building | Entries | Sold | Booked | Marked unsold | Other / unstated status | Recorded carpet-area range |
|---|---|---|---|---|---|---|
| Building A | 96 | 61 | 0 | 0 | 35 | 55.35–59.73 sq m≈ 596–643 sq ft |
| Building B | 65 | 5 | 0 | 56 | 4 | 16.35–108.65 sq m≈ 176–1,169 sq ft |
Different sizes are not necessarily different bedroom types. How we read and summarise the filing →
Unit Report
Understand its light, privacy, layout and surroundings. See how it compares with similar homes and other options in this project.
Didn’t help you decide? Full refund — no questions asked.
The same home number may appear in more than one building. Check both before choosing.
MahaRERA · per-home inventory · saved-file date 18 July 2026
| Home / building | Floor in the record | Carpet area | Reported status | Agreement value | Assess |
|---|---|---|---|---|---|
| 1001Building A | 10 | 59.73 sq m≈ 643 sq ft | Sold | ₹6,073,500 | |
| 1002Building A | 10 | 55.35 sq m≈ 596 sq ft | Sold | ₹5,334,000 | |
| 1003Building A | 10 | 55.35 sq m≈ 596 sq ft | Sold | ₹4,400,000 | |
| 1004Building A | 10 | 59.73 sq m≈ 643 sq ft | Not for sale | Not stated | |
| 1005Building A | 10 | 59.73 sq m≈ 643 sq ft | Not for sale | Not stated | |
| 1006Building A | 10 | 55.35 sq m≈ 596 sq ft | Not for sale | Not stated | |
| 1007Building A | 10 | 55.35 sq m≈ 596 sq ft | Not for sale | Not stated | |
| 1008Building A | 10 | 59.73 sq m≈ 643 sq ft | Sold | ₹5,830,200 | |
| 101Building A | 1 | 59.73 sq m≈ 643 sq ft | Sold | ₹4,490,000 | |
| 102Building A | 1 | 55.35 sq m≈ 596 sq ft | Sold | ₹5,500,000 | |
| 103Building A | 1 | 55.35 sq m≈ 596 sq ft | Sold | ₹5,800,000 | |
| 104Building A | 1 | 59.73 sq m≈ 643 sq ft | Sold | ₹4,490,000 |
Read every entry in one table: Read the complete saved home list.
Choose the home you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.
More from the RERA documents
₹342,878,650 of an estimated ₹348,697,500 was reported as incurred (98.3%). This percentage is about costs. It does not show how much construction is complete.
MahaRERA project filing · read 19 July 2026 · registration P52100020477
Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.
| Building | Activity | Reported |
|---|---|---|
| Building A | Excavation | 100.0% |
| Building A | Basement (if any) | 100.0% |
| Building A | Podiums (if any) | 0.0% |
| Building A | Plinth | 100.0% |
| Building A | Stilt Floor | 100.0% |
| Building A | Slabs of Super Structure | 100.0% |
| Building A | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100.0% |
| Building A | Sanitary Fittings within the flats / premises | 100.0% |
| Building A | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100.0% |
| Building A | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100.0% |
| Building A | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100.0% |
| Building B | Excavation | 100.0% |
| Building B | Basement (if any) | 100.0% |
| Building B | Podiums (if any) | 0.0% |
| Building B | Plinth | 100.0% |
| Building B | Stilt Floor | 0.0% |
| Building B | Slabs of Super Structure | 100.0% |
| Building B | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100.0% |
| Building B | Sanitary Fittings within the flats / premises | 100.0% |
| Building B | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100.0% |
| Building B | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100.0% |
| Building B | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100.0% |
MahaRERA project filing · read 19 July 2026 · registration P52100020477
| Revised target | Reason given by the builder |
|---|---|
| 29 December 2024 | The project got its first sanction from PMRDA on 5.04.2019 wherein B plus G floor + 8 floors for residential building and B + G floor for commercial building was sanctioned. Amenity space and road widening area to be handed over to PMRDA was demarcated on the sanctioned plan. The amenity space and area for road widening was handed over to PMRDA. Project got revised sanction from PMRDA on 04.11.2020 wherein residential building got sanction till 12 floor (B + G floor plus 12 floors) and commercial till B + G floor only. The commercial building got its plinth check certificate on 08.07.2021 which was issued by PMRDA wherein it is mentioned that RCC work of ground floor of commercial building is completed. On 2.8.21 PMRDA Draft Plan was published wherein proposed 30 M wide draft DP road was shown on the commercial building. Aggrieved by this arbitrary action of the PMRDA, Promoter has moved application to PMRDA and appealed to realign the proposed DP road as it is unjust to shift the road on committed development. Project got revised sanction from the PMRDA on 03.12.2021 wherein residential building got sanction till 12 floor (B + G + 12) and for commercial building till 3 floor (B + Gr + 3). The proposed 30 M wide draft DP road is marked on the sanctioned plan which has created obstruction for prospective buyer to purchase the commercial unit in project. A notice was issued by the PMRDA on 05.05.2022 to give statement before planning committee to record grievances. We have raised this issue before PMRDA, they acknowledged their mistake by sending a letter dated 15.06.2022 to Planning Dept that they consider the realignment of the draft DP road as it affects the committed development. The grievance is raised before the expert committee constituted for this purpose. Promoter has received Completion Certificate on 03.03.2023 for Residential Building ONLY and the Promoter has handed over possession to all residential unit holders by registering a deed of apartment. Considering contingency of proposed Draft DP Road Promoter seeks project extension u/s 6 of the Act for one year. Promoter draws attention of authority that the work progress of commercial building got stuck by the arbitrary action of PMRDA. The completion of the Commercial building and in sense completion of the project is contingent upon the time the concerned authority will take to realign the proposed DP road so as to not affect Commercial Building of the said project, a committed development. |
| 28 December 2026 | Project got its sanction from PMRDA on 5.04.19 (B+G+8) floors for residential and B+G for commercial was sanctioned. Amenity space and road widening area to be handed over to PMRDA was demarcated on the sanctioned plan and subsequently it was handed over to PMRDA. Project got revised sanction from PMRDA on 4.11.20 wherein residential got sanction till 12th floor (B+G+12 floors) and commercial till B+G. The commercial building got its plinth check certificate on 8.7.21 which was issued by PMRDA wherein it is mentioned that RCC work of ground floor of commercial is completed. On 2.8.21 PMRDA Draft Plan was published wherein proposed 30 M wide draft DP road was shown on the commercial building. Aggrieved by this arbitrary action, Promoter has moved application on 27.8.21 and appealed to realign the proposed DP road as it is unjust to shift the road on committed development. Project got revised sanction from the PMRDA on 3.12.21 wherein residential got sanction till 12th floor and for commercial till 3rd floor. The proposed 30M wide draft DP road was marked on the plan which has created obstruction for prospective buyer to purchase the commercial unit in project. Notice was issued by PMRDA on 05.05.2022 to give statement before planning committee to record grievances. We have raised issue before PMRDA, they acknowledged their mistake by sending letter dt15.06.22 to Planning Dept that they consider realignment. Grievance was raised before expert committee. Promoter received Completion Certificate on 3.3.23 for Residential Building A. Promoter has handed over possession to all residential unit holders by registering a deed of apartment. On 27.12.23, MAHARERA has extended project deadline in accordance with section 6/7 of the Act till 29.12.24. On 20.3.24, we received completion certificate for club house (Gr + first floor) and for commercial building B (Shops 1 to 8). The shop owners were given possession after registering their respective apartment deed. The proposal was submitted for revised sanctioning till 10th floor and after due scrutiny PMRDA issued revised sanctioning for commercial building on 5.7.24. Considering the above-mentioned developments Promoter seeks project extension u/s 7 (3) of the Act for two years without consent of allottees as each and every allottee from residential as well as commercial building has been given possession and respective apartment deed is registered as those units have received completion certificate. |
MahaRERA project filing · read 19 July 2026 · registration P52100020477
RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.
| Filing | Own funds | Borrowing | Payments from buyers | Total |
|---|---|---|---|---|
| Estimated plan | ₹100,000 | ₹20,000,000 | ₹369,127,199 | ₹419,227,199 |
| Actual raised | ₹100,000 | ₹53,355,862 | ₹372,213,397 | ₹533,493,795 |
MahaRERA project filing · read 19 July 2026 · registration P52100020477
29 elapsed quarterly periods in the captured compliance schedule. No active quarterly default was recorded in this snapshot.
MahaRERA project filing · read 19 July 2026 · registration P52100020477
A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.
MahaRERA project filing · read 19 July 2026 · registration P52100020477
Builder and past records
Projects registered under this company
1Pune registrations
These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.
MahaRERA Pune registration records · read 12 July 2026
Past records of sales and unsold homes
26 September 2026
56 marked unsold · 66 sold · 0 booked.
Saved MahaRERA home list
17 September 2026
56 marked unsold · 66 sold · 0 booked.
Saved MahaRERA home list
8 September 2026
56 marked unsold · 66 sold · 0 booked.
Saved MahaRERA home list
19 July 2026
56 marked unsold · 66 sold · 0 booked.
Saved MahaRERA home list
These dates show when the records were saved, not when homes were sold. Sales may have changed since then, even if the saved counts are the same.
Project Comparison Report
Compare up to three projects. We read their plans and RERA documents, recommend homes in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.
2 projects · ₹7,999
3 projects · ₹9,999
Within 1 working day
Didn’t help you decide? Full refund — no questions asked.
Compare project details for free →MahaRERA · registration record · read 12 July 2026
MahaRERA · per-home inventory · saved-file date 18 July 2026
This is a past RERA home list, not current availability. It does not give the date each home was sold.
The home-list date is based on the saved file’s details.
Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.
Open MahaRERA · search P52100020477 ↗