The builder’s RERA record, explained

RAJNANDINI TOWER

PARSHURAM MAHADEO BHOSALE · P52100020723

MahaRERA · registration record · read 12 July 2026

Choose a report ↓

What does the RERA record show?

For RAJNANDINI TOWER (P52100020723), 78 of 143 entries were marked unsold in the MahaRERA home list read 18 July 2026.

MahaRERA · per-home inventory · read 18 July 2026

For RAJNANDINI TOWER, ₹6,512 per sq ft of carpet area is the median rate across 42 sold or booked entries with prices in the MahaRERA home list read 18 July 2026. These are historical agreement values, not current asking prices.

MahaRERA · per-home inventory · read 18 July 2026

These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.

What would help you decide?

Buyer’s Report

Understand this project

Find homes to consider, with advice on light, layout, privacy and surroundings.

₹4,999

Unit Report

Check a particular home

See its advantages, drawbacks and how it compares with other homes in this project.

₹3,999

Project Comparison Report

Choose between projects

Compare two or three projects and get recommended homes in order, with reasons for each choice.

From ₹7,999

Choose projects →

Project status and completion date.

Prices reported to RERA

What prices have been reported?

₹6,512/ sq ft carpet area

Across 42 sold or booked entries with reported prices. The middle 80% of rates fall between ₹5,827 and ₹8,809.

MahaRERA · per-home inventory · read 18 July 2026

How is this calculated?

For each sold or booked entry, we divide the reported agreement value by its carpet area in square feet. The median is the middle rate when these rates are put in order. We show it only when at least five entries have prices. We exclude valuations of unsold homes and government reference rates. The figures may include different sizes and property types. They are historical agreement values, not current asking prices or the total cost including extra charges.

Sales Report

What did similar homes sell for?

Compare reported agreement values by building, size and floor. See which homes were marked unsold on the date shown.

₹2,999 · delivered on payment

Inside this registered phase

How do the buildings compare in the record?

143 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.

MahaRERA · per-home inventory · read 18 July 2026

Scroll sideways to see all columns.

Building names, sale status and carpet areas — not current availability
Filed buildingEntriesSoldBookedMarked unsoldOther / unstated statusRecorded carpet-area range
RAJNANDINI TOWER143420782313.18–85.60 sq m≈ 142–921 sq ft

Different sizes are not necessarily different bedroom types. How we read and summarise the filing →

Unit Report

Is this the right
home for you?

Understand its light, privacy, layout and surroundings. See how it compares with similar homes and other options in this project.

₹3,999 · 1 working day

Didn’t help you decide? Full refund — no questions asked.

Find your home in the RERA list.

The same home number may appear in more than one building. Check both before choosing.

143 listed entries

MahaRERA · per-home inventory · read 18 July 2026

RERA home list, not current availability
Home / buildingFloor in the recordCarpet areaReported statusAgreement valueAssess
Flat 1001RAJNANDINI TOWER1085.6 sq m≈ 921 sq ftSold₹6,000,000
Flat 1002RAJNANDINI TOWER1085.6 sq m≈ 921 sq ftSold₹6,000,000
Flat 1003RAJNANDINI TOWER1071.56 sq m≈ 770 sq ftSold₹4,450,000
Flat 1004RAJNANDINI TOWER1043.83 sq m≈ 472 sq ftSold₹5,250,000
Flat 1005RAJNANDINI TOWER1060.02 sq m≈ 646 sq ftSold₹4,400,000
Flat 1006RAJNANDINI TOWER1068.19 sq m≈ 734 sq ftSold₹4,450,000
Flat 1007RAJNANDINI TOWER1060.68 sq m≈ 653 sq ftSold₹5,200,000
Flat 1101RAJNANDINI TOWER1185.6 sq m≈ 921 sq ftSold₹5,800,000
Flat 1102RAJNANDINI TOWER1185.6 sq m≈ 921 sq ftNot for saleNot stated
Flat 1103RAJNANDINI TOWER1171.56 sq m≈ 770 sq ftNot for saleNot stated
Flat 1104RAJNANDINI TOWER1143.83 sq m≈ 472 sq ftNot for saleNot stated
Flat 1105RAJNANDINI TOWER1160.02 sq m≈ 646 sq ftNot for saleNot stated

Read every entry in one table: Read the complete saved home list.

Choose the home you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.

More from the RERA documents

Construction progress and project documents.

Cost reported as incurred

₹360,000,000 of an estimated ₹360,000,000 was reported as incurred (100.0%). This percentage is about costs. It does not show how much construction is complete.

MahaRERA project filing · read 18 July 2026 · registration P52100020723

Work reported, by building

Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.

See all reported activities
BuildingActivityReported
RAJNANDINI TOWERExcavation100.0%
RAJNANDINI TOWERBasement (if any)100.0%
RAJNANDINI TOWERPodiums (if any) 100.0%
RAJNANDINI TOWERPlinth100.0%
RAJNANDINI TOWERStilt Floor 100.0%
RAJNANDINI TOWERSlabs of Super Structure100.0%
RAJNANDINI TOWERInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100.0%
RAJNANDINI TOWERSanitary Fittings within the flats / premises1000.0%
RAJNANDINI TOWERStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100.0%
RAJNANDINI TOWERExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100.0%
RAJNANDINI TOWERInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100.0%

MahaRERA project filing · read 18 July 2026 · registration P52100020723

Reported deadline extensions

Revised targetReason given by the builder
10 May 2026Due to a minor delay beyond the originally stipulated completion date, the Occupancy Certificate was received on 29/07/2025. Since the date of the Occupancy Certificate is later than the declared project completion date, the system is not permitting submission of the Completion Application. Accordingly, an extension up to 10/05/2026 (or such extended time as permissible under the applicable provisions) is respectfully sought to enable the Promoter to file the Completion Application and to comply with any further statutory or procedural requirements, if necessary. Further, we submit the following for your kind consideration: Affidavit for Plan Update & Correction: An affidavit for update and correction of plans is being uploaded. The necessary updates will be carried out on the portal immediately within the prescribed time upon grant of the extension. QPR Compliance: The latest Quarterly Progress Reports (QPR) have already been submitted. Mismatch in Portal Data vs. Approved Records: Certain discrepancies have been identified between the information currently reflected on the MahaRERA portal and the approved plans and actual unit details. As per approved records, the total number of units is 142 (42 Sold, 22 Landowner Allotted, 78 Promoter Reserved). However, the portal presently reflects 143 units. These mismatches occurred while migration & as correction was not permitted on the portal at the relevant time. The same shall be rectified through the Project Correction module immediately upon approval of the extension. Mismatch in Professional Details: There is also a discrepancy between the name/details of certain professionals reflected on the portal and those mentioned in the updated statutory forms. The same shall also be corrected once the correction window is enabled after grant of extension. SRO Membership Certificate: The SRO Membership Certificate issued by CREDAI Pune is being submitted herewith for your reference and record.

MahaRERA project filing · read 18 July 2026 · registration P52100020723

Where the project funding comes from

RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.

FilingOwn fundsBorrowingPayments from buyersTotal
Estimated plan₹0₹0₹176,921,500₹176,921,500
Actual raised₹0₹0₹214,421,500₹214,421,500

MahaRERA project filing · read 18 July 2026 · registration P52100020723

Quarterly filing record

29 elapsed quarterly periods in the captured compliance schedule. No active quarterly default was recorded in this snapshot.

MahaRERA project filing · read 18 July 2026 · registration P52100020723

Documents named in the filing

  • Promoter PAN · 1 listed
  • Commencement certificate · 2 listed
  • Form 1 — Architect's certificate · 1 listed
  • Form 3 — CA certificate · 1 listed
  • Form 2 — Engineer's certificate · 1 listed
  • Form B — Promoter declaration · 1 listed
  • Title / search report · 1 listed
  • Sanctioned layout plan · 8 listed
  • Sanctioned building plan · 18 listed
  • Encumbrance certificate · 1 listed

A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.

MahaRERA project filing · read 18 July 2026 · registration P52100020723

Builder and past records

What else does the record show?

Projects registered under this company

PARSHURAM MAHADEO BHOSALE

1Pune registrations

These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.

MahaRERA Pune registration records · read 12 July 2026

Explore other registrations

    Past records of sales and unsold homes

    1. 21 September 2026

      78 marked unsold · 42 sold · 0 booked.

      Saved MahaRERA home list

    2. 12 September 2026

      78 marked unsold · 42 sold · 0 booked.

      Saved MahaRERA home list

    3. 4 September 2026

      78 marked unsold · 42 sold · 0 booked.

      Saved MahaRERA home list

    4. 18 July 2026

      78 marked unsold · 42 sold · 0 booked.

      Saved MahaRERA home list

    These dates show when the records were saved, not when homes were sold. Sales may have changed since then, even if the saved counts are the same.

    qpr noncompliance

    May

    MahaRERA · due-non-compliance-qpr · read 2026-09-28T23:07:26.247150+00:00

    Project Comparison Report

    Which project should you buy in?
    And which home?

    Compare up to three projects. We read their plans and RERA documents, recommend homes in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.

    Create my Comparison Report →

    2 projects · ₹7,999
    3 projects · ₹9,999

    Within 1 working day

    Didn’t help you decide? Full refund — no questions asked.

    Compare project details for free →

    Sources and dates.

    MahaRERA · registration record · read 12 July 2026

    MahaRERA · per-home inventory · read 18 July 2026

    This is a past RERA home list, not current availability. It does not give the date each home was sold.

    Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.

    Open MahaRERA · search P52100020723 ↗