The builder’s RERA record, explained

Eternia Phase 2

VENTURESPRO PROJECTS LLP · P52100021956

MahaRERA · registration record · read 12 July 2026

Choose a report ↓

What does the RERA record show?

For Eternia Phase 2 (P52100021956), 40 of 202 entries were marked unsold in the MahaRERA home list read 8 September 2026.

MahaRERA · per-home inventory · read 8 September 2026

For Eternia Phase 2, ₹9,501 per sq ft of carpet area is the median rate across 162 sold or booked entries with prices in the MahaRERA home list read 8 September 2026. These are historical agreement values, not current asking prices.

MahaRERA · per-home inventory · read 8 September 2026

These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.

What would help you decide?

Buyer’s Report

Understand this project

Find homes to consider, with advice on light, layout, privacy and surroundings.

₹4,999

Unit Report

Check a particular home

See its advantages, drawbacks and how it compares with other homes in this project.

₹3,999

Project Comparison Report

Choose between projects

Compare two or three projects and get recommended homes in order, with reasons for each choice.

From ₹7,999

Choose projects →

Project status and completion date.

Prices reported to RERA

What prices have been reported?

₹9,501/ sq ft carpet area

Across 162 sold or booked entries with reported prices. The middle 80% of rates fall between ₹8,252 and ₹11,739.

MahaRERA · per-home inventory · read 8 September 2026

How is this calculated?

For each sold or booked entry, we divide the reported agreement value by its carpet area in square feet. The median is the middle rate when these rates are put in order. We show it only when at least five entries have prices. We exclude valuations of unsold homes and government reference rates. The figures may include different sizes and property types. They are historical agreement values, not current asking prices or the total cost including extra charges.

Sales Report

What did similar homes sell for?

Compare reported agreement values by building, size and floor. See which homes were marked unsold on the date shown.

₹2,999 · delivered on payment

Inside this registered phase

How do the buildings compare in the record?

202 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.

MahaRERA · per-home inventory · read 8 September 2026

Scroll sideways to see all columns.

Building names, sale status and carpet areas — not current availability
Filed buildingEntriesSoldBookedMarked unsoldOther / unstated statusRecorded carpet-area range
Tower B from 2nd floor till 27th floor194155435053.39–120.59 sq m≈ 575–1,298 sq ft
Tower B upto 1st floor8305069.79–120.59 sq m≈ 751–1,298 sq ft

Different sizes are not necessarily different bedroom types. How we read and summarise the filing →

Unit Report

Is this the right
home for you?

Understand its light, privacy, layout and surroundings. See how it compares with similar homes and other options in this project.

₹3,999 · 1 working day

Didn’t help you decide? Full refund — no questions asked.

Find your home in the RERA list.

The same home number may appear in more than one building. Check both before choosing.

202 listed entries

MahaRERA · per-home inventory · read 8 September 2026

RERA home list, not current availability
Home / buildingFloor in the recordCarpet areaReported statusAgreement valueAssess
1001Tower B from 2nd floor till 27th floor10120.03 sq m≈ 1,292 sq ftSold₹12,273,730
1002Tower B from 2nd floor till 27th floor10120.59 sq m≈ 1,298 sq ftSold₹10,497,500
1003Tower B from 2nd floor till 27th floor1080.92 sq m≈ 871 sq ftSold₹7,776,000
1004Tower B from 2nd floor till 27th floor1080.92 sq m≈ 871 sq ftSold₹7,754,040
1005Tower B from 2nd floor till 27th floor10108.29 sq m≈ 1,166 sq ftMarked unsoldNot stated
1006Tower B from 2nd floor till 27th floor10112.01 sq m≈ 1,206 sq ftSold₹10,990,400
1007Tower B from 2nd floor till 27th floor1069.79 sq m≈ 751 sq ftSold₹7,187,474
1008Tower B from 2nd floor till 27th floor1070.68 sq m≈ 761 sq ftSold₹6,806,055
1101Tower B from 2nd floor till 27th floor11120.03 sq m≈ 1,292 sq ftSold₹12,899,850
1102Tower B from 2nd floor till 27th floor11120.59 sq m≈ 1,298 sq ftSold₹10,497,500
1103Tower B from 2nd floor till 27th floor1180.92 sq m≈ 871 sq ftSold₹7,689,936
1104Tower B from 2nd floor till 27th floor1180.92 sq m≈ 871 sq ftSold₹8,020,000

Read every entry in one table: Read the complete saved home list.

Choose the home you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.

More from the RERA documents

Construction progress and project documents.

Cost reported as incurred

₹545,149,823 of an estimated ₹1,250,000,000 was reported as incurred (43.6%). This percentage is about costs. It does not show how much construction is complete.

MahaRERA project filing · read 19 July 2026 · registration P52100021956

Work reported, by building

Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.

See all reported activities
BuildingActivityReported
Tower B upto 1st floorExcavation100.0%
Tower B upto 1st floorBasement (if any)100.0%
Tower B upto 1st floorPodiums (if any) 100.0%
Tower B upto 1st floorPlinth100.0%
Tower B upto 1st floorStilt Floor 100.0%
Tower B upto 1st floorSlabs of Super Structure100.0%
Tower B upto 1st floorInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises72.0%
Tower B upto 1st floorSanitary Fittings within the flats / premises2.0%
Tower B upto 1st floorStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50.0%
Tower B upto 1st floorExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.1.0%
Tower B upto 1st floorInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.5.0%
Tower B from 2nd floor till 27th floorExcavation100.0%
Tower B from 2nd floor till 27th floorBasement (if any)100.0%
Tower B from 2nd floor till 27th floorPodiums (if any) 100.0%
Tower B from 2nd floor till 27th floorPlinth100.0%
Tower B from 2nd floor till 27th floorStilt Floor 100.0%
Tower B from 2nd floor till 27th floorSlabs of Super Structure90.0%
Tower B from 2nd floor till 27th floorInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises72.0%
Tower B from 2nd floor till 27th floorSanitary Fittings within the flats / premises2.0%
Tower B from 2nd floor till 27th floorStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50.0%
Tower B from 2nd floor till 27th floorExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.1.0%
Tower B from 2nd floor till 27th floorInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.5.0%

MahaRERA project filing · read 19 July 2026 · registration P52100021956

Reported deadline extensions

Revised targetReason given by the builder
31 December 2026Supply chain disruptions and increased lead times for the delivery of essential construction materials, such as cement, steel, and other building components, have caused delays in the construction schedule. The scarcity of these materials in the local market and price volatility have further compounded the problem, leading to intermittent halts in construction activities.

MahaRERA project filing · read 19 July 2026 · registration P52100021956

Where the project funding comes from

RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.

FilingOwn fundsBorrowingPayments from buyersTotal
Actual raised₹211,076,997₹298,909,531₹759,693,003₹1,269,679,531

MahaRERA project filing · read 19 July 2026 · registration P52100021956

Quarterly filing record

27 elapsed quarterly periods in the captured compliance schedule. No active quarterly default was recorded in this snapshot.

MahaRERA project filing · read 19 July 2026 · registration P52100021956

Documents named in the filing

  • Promoter PAN · 1 listed
  • Form 1 — Architect's certificate · 4 listed
  • Form 3 — CA certificate · 5 listed
  • Form 2 — Engineer's certificate · 4 listed
  • Form B — Promoter declaration · 2 listed
  • Title / search report · 2 listed
  • Sanctioned layout plan · 5 listed
  • Sanctioned building plan · 9 listed

A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.

MahaRERA project filing · read 19 July 2026 · registration P52100021956

Builder and past records

What else does the record show?

Projects registered under this company

VENTURESPRO PROJECTS LLP

4Pune registrations

These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.

MahaRERA Pune registration records · read 12 July 2026

Explore other registrations

Past records of sales and unsold homes

  1. 26 September 2026

    40 marked unsold · 158 sold · 4 booked.

    Saved MahaRERA home list

  2. 17 September 2026

    40 marked unsold · 158 sold · 4 booked.

    Saved MahaRERA home list

  3. 8 September 2026

    40 marked unsold · 158 sold · 4 booked.

    Saved MahaRERA home list

  4. 19 July 2026

    45 marked unsold · 149 sold · 8 booked.

    Saved MahaRERA home list

These dates show when the records were saved, not when homes were sold. Sales may have changed since then, even if the saved counts are the same.

Project Comparison Report

Which project should you buy in?
And which home?

Compare up to three projects. We read their plans and RERA documents, recommend homes in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.

Create my Comparison Report →

2 projects · ₹7,999
3 projects · ₹9,999

Within 1 working day

Didn’t help you decide? Full refund — no questions asked.

Compare project details for free →

Sources and dates.

MahaRERA · registration record · read 12 July 2026

MahaRERA · per-home inventory · read 8 September 2026

This is a past RERA home list, not current availability. It does not give the date each home was sold.

Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.

Open MahaRERA · search P52100021956 ↗