The builder’s RERA record, explained

Namoville

ROYAL NAMOVILLE VENTURES · P52100022808

MahaRERA · registration record · read 12 July 2026

Choose a report ↓

What does the RERA record show?

For Namoville (P52100022808), 6 of 118 entries were marked unsold in the MahaRERA unit list read 8 September 2026.

MahaRERA · per-unit inventory · read 8 September 2026

For Namoville, ₹8,810 per sq ft of filed area is the median rate across 112 sold or booked entries with prices in the MahaRERA unit list read 8 September 2026. These are historical agreement values, not current asking prices.

MahaRERA · per-unit inventory · read 8 September 2026

These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.

What would help you decide?

Buyer’s Report

Understand this project

Find units to consider, with advice on light, layout, privacy and surroundings.

₹4,999

Unit Report

Check a particular unit

See its advantages, drawbacks and how it compares with other units in this project.

₹3,999

Project Comparison Report

Choose between projects

Compare two or three projects and get recommended units in order, with reasons for each choice.

From ₹7,999

Choose projects →

Project status and completion date.

Prices reported to RERA

What prices have been reported?

₹8,810/ sq ft filed area

Across 112 sold or booked entries with reported prices. The middle 80% of rates fall between ₹7,376 and ₹10,649.

MahaRERA · per-unit inventory · read 8 September 2026

How is this calculated?

For each sold or booked entry, we divide the reported agreement value by its filed area in square feet. The median is the middle rate when these rates are put in order. We show it only when at least five entries have prices. We exclude valuations of unsold units and government reference rates. The figures may include different sizes and property types. They are historical agreement values, not current asking prices or the total cost including extra charges.

Sales Report

What did similar units sell for?

Compare filed values by building, unit-number pattern and area. See which units were marked unsold on the date shown.

₹2,999 · delivered on payment

Inside this registered phase

How do the buildings compare in the record?

118 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.

MahaRERA · per-unit inventory · read 8 September 2026

Scroll sideways to see all columns.

Building names, sale status and filed areas — not current availability
Filed buildingEntriesSoldBookedMarked unsoldOther / unstated statusRecorded filed-area range
Wing B605712038.15–56.55 sq m≈ 411–609 sq ft
Wing C585314037.71–79.28 sq m≈ 406–853 sq ft

Area means carpet area for building units and plot area for plots. Size alone does not establish use or layout. How we read and summarise the filing →

Unit Report

Is this the right
unit for you?

Understand its light, privacy, layout and surroundings. See how it compares with similar units and other options in this project.

₹3,999 · 1 working day

Didn’t help you decide? Full refund — no questions asked.

Find your unit in the RERA list.

The same unit number may appear in more than one building. Check both before choosing.

118 listed entries

MahaRERA · per-unit inventory · read 8 September 2026

RERA unit list, not current availability
Unit / buildingFloor in the recordFiled areaReported statusAgreement valueAssess
1001Wing B / Wing NA1048.89 sq m≈ 526 sq ft · RERA carpet areaSold₹4,973,000
1002Wing B / Wing NA1056.55 sq m≈ 609 sq ft · RERA carpet areaSold₹5,065,000
1003Wing B / Wing NA1056.55 sq m≈ 609 sq ft · RERA carpet areaSold₹5,300,000
1004Wing B / Wing NA1048.89 sq m≈ 526 sq ft · RERA carpet areaSold₹5,812,500
101Wing B / Wing NA148.89 sq m≈ 526 sq ft · RERA carpet areaSold₹4,900,000
102Wing B / Wing NA156.55 sq m≈ 609 sq ft · RERA carpet areaSold₹4,490,000
103Wing B / Wing NA156.55 sq m≈ 609 sq ft · RERA carpet areaSold₹4,490,000
104Wing B / Wing NA148.89 sq m≈ 526 sq ft · RERA carpet areaSold₹5,500,000
1101Wing B / Wing NA1148.89 sq m≈ 526 sq ft · RERA carpet areaSold₹5,864,865
1102Wing B / Wing NA1156.55 sq m≈ 609 sq ft · RERA carpet areaSold₹5,800,000
1103Wing B / Wing NA1156.55 sq m≈ 609 sq ft · RERA carpet areaBooked₹5,500,000
1104Wing B / Wing NA1148.89 sq m≈ 526 sq ft · RERA carpet areaSold₹4,490,000

Read every entry in one table: Read the complete saved unit list.

Choose the unit you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.

More from the RERA documents

Construction progress and project documents.

Cost reported as incurred

₹219,111,414 of an estimated ₹270,000,000 was reported as incurred (81.2%). This percentage is about costs. It does not show how much construction is complete.

MahaRERA project filing · read 19 July 2026 · registration P52100022808

Work reported, by building

Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.

See all reported activities
BuildingActivityReported
Wing CExcavation100.0%
Wing CBasement (if any)100.0%
Wing CPodiums (if any) 0.0%
Wing CPlinth100.0%
Wing CStilt Floor 90.0%
Wing CSlabs of Super Structure100.0%
Wing CInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90.0%
Wing CSanitary Fittings within the flats / premises50.0%
Wing CStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100.0%
Wing CExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.65.0%
Wing CInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.25.0%
Wing BExcavation100.0%
Wing BBasement (if any)100.0%
Wing BPodiums (if any) 0.0%
Wing BPlinth100.0%
Wing BStilt Floor 100.0%
Wing BSlabs of Super Structure100.0%
Wing BInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100.0%
Wing BSanitary Fittings within the flats / premises90.0%
Wing BStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100.0%
Wing BExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90.0%
Wing BInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80.0%

MahaRERA project filing · read 19 July 2026 · registration P52100022808

Reported deadline extensions

Revised targetReason given by the builder
30 April 2025We request you to Grant the Extension of 1 year u/s 6 of Maharera Act. As the occurrence of unexpected global pandemic situation of COVID -19 has direct effect on the work due to shortage of material, labour & other necessary resources of project leads to the delay in completion of the project.
30 April 2026Reasons for Delay in Project/Grounds for Extension of the Project NAMOVILLE – 1. One of the landowner namely Mr. Jeeva Narayanan Vishwakarma expired during the year 2020. Due to tragic death of the Mr. Jeeva Narayanan Vishwakarma his family members got panicked and were unable to make any decision for 1-2 years. As per development agreement No. 3717/2018 landowner has to vacate the bungalow situated on the land S No 32/2/3 & 32/2/4 and need to give peaceful possession to us after executing the DAPA. However due ailment he cannot vacate his land and bungalow till his death. After his demise his legal heirs got panicked did not vacate the bungalow till April 2024 and were asking for additional compensation from the promoters and this confusion was going on till April 2024. However, at end, to achieve the project goals and to complete the project in the given timeline promoters have agreed to provide additional considerations to the legal heirs of landowner Mr. Jeeva Narayanan Vishwakarma & Mrs. Shantha Jiva and got vacated the land from legal heirs of the landowner. There was no legal dispute or litigation on the project land but tragic death of landowner lead to the panic situation between landowners and his legal heirs. Due to above mentioned reasons project NAMOVILLE was got delayed by almost 2-3 years. 2. As per updated UDCPR, 2020 promoters are eligible for additional FSI area and also promoters intend to take paid TDR for additional construction at NAMOVILLE building. Promoters are hopeful that they will get additional FSI area as per updated UDCPR, 2020. 3. Also for selling purposes of the promoters required valid RERA certificate for execution of the sale agreement at registrar office.
31 December 20281. As per updated UDCPR, 2020 promoters are eligible for additional FSI area and also promoters intend to take paid TDR for additional construction at NAMOVILLE building. Additional FSI and paid TDR will result in additional 2 floors at Wing B & Wing C. Sanction process of these area and procedural matters will take 6-8 months and construction of it will take additional 12-15 months. Effectively promoters can complete the Wing B & C upto June 2028. Promoters are hopeful that they will get additional FSI area as per updated UDCPR, 2020. 2. Also promoters intend to add Wing A part and parcel of this present layout and sanctioned plan to this existing RERA project Namoville. Promoters are in the process of obtaining revised sanctioned plans for Wing A. Hence as discussed construction of Wing A also going to take additional 24 to 30 months from date of sanctioning of revised plans. 3. Promoters are near to completion of Wing B & Wing C and hopeful that they will get part completion certificate for these 2 wings by October/November 2026. Since MahaRERA authority does not hold part OC as valid completion certificate on technical terms our project will continue to be classified as ongoing project till the completion of Wing A in the said layout. Hence on this basis also we request Your Honor to extend the proposed completion date of project till 31-12-2028.

MahaRERA project filing · read 19 July 2026 · registration P52100022808

Where the project funding comes from

RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.

FilingOwn fundsBorrowingPayments from buyersTotal
Estimated plan₹77,500,000₹0₹300,000,000₹427,500,000
Actual raised₹26,088,112₹0₹310,335,677₹375,675,379

MahaRERA project filing · read 19 July 2026 · registration P52100022808

Quarterly filing record

26 elapsed quarterly periods in the captured compliance schedule. No active quarterly default was recorded in this snapshot.

MahaRERA project filing · read 19 July 2026 · registration P52100022808

Documents named in the filing

  • Promoter PAN · 1 listed
  • Commencement certificate · 1 listed
  • Form 1 — Architect's certificate · 12 listed
  • Form 3 — CA certificate · 22 listed
  • Form 2 — Engineer's certificate · 20 listed
  • Title / search report · 1 listed
  • Form B — Promoter declaration · 3 listed
  • Sanctioned layout plan · 3 listed
  • Sanctioned building plan · 18 listed

A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.

MahaRERA project filing · read 19 July 2026 · registration P52100022808

Builder and past records

What else does the record show?

Projects registered under this company

ROYAL NAMOVILLE VENTURES

1Pune registrations

These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.

MahaRERA Pune registration records · read 12 July 2026

Explore other registrations

    Past records of sales and unsold units

    1. 26 September 2026

      6 marked unsold · 110 sold · 2 booked.

      Saved MahaRERA unit list

    2. 17 September 2026

      6 marked unsold · 110 sold · 2 booked.

      Saved MahaRERA unit list

    3. 8 September 2026

      6 marked unsold · 110 sold · 2 booked.

      Saved MahaRERA unit list

    4. 19 July 2026

      6 marked unsold · 108 sold · 4 booked.

      Saved MahaRERA unit list

    These dates show when the records were saved, not when units were sold. Sales may have changed since then, even if the saved counts are the same.

    More projects to explore

    Other projects in this locality.

    These projects list the same locality. They may differ in exact location, property type and price.

    Project Comparison Report

    Which project should you buy in?
    And which unit?

    Compare up to three projects. We read their plans and RERA documents, recommend units in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.

    Create my Comparison Report →

    2 projects · ₹7,999
    3 projects · ₹9,999

    Within 1 working day

    Didn’t help you decide? Full refund — no questions asked.

    Compare project details for free →

    Sources and dates.

    MahaRERA · registration record · read 12 July 2026

    MahaRERA · per-unit inventory · read 8 September 2026

    This is a past RERA unit list, not current availability. It does not give the date each unit was sold.

    Filed area means carpet area for building units and plot area for plots. Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.

    Open MahaRERA · search P52100022808 ↗