Buyer’s Report
Understand this project
Find homes to consider, with advice on light, layout, privacy and surroundings.
₹4,999
Builder’s RERA records,
explained for buyers.
The builder’s RERA record, explained
KARMA BUILDERS · P52100026329
For KARMA ICONIC (P52100026329), 57 of 162 entries were marked unsold in the MahaRERA home list read 8 September 2026.
For KARMA ICONIC, ₹7,334 per sq ft of carpet area is the median rate across 79 sold or booked entries with prices in the MahaRERA home list read 8 September 2026. These are historical agreement values, not current asking prices.
These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.
Builder’s completion target
The builder reported this target date. It is not a confirmed handover date.
Status shown on RERA
This is the status shown on RERA. It does not confirm an occupancy certificate or today’s construction progress.
Prices reported to RERA
₹7,334/ sq ft carpet area
Across 79 sold or booked entries with reported prices. The middle 80% of rates fall between ₹6,371 and ₹8,657.
MahaRERA · per-home inventory · read 8 September 2026
For each sold or booked entry, we divide the reported agreement value by its carpet area in square feet. The median is the middle rate when these rates are put in order. We show it only when at least five entries have prices. We exclude valuations of unsold homes and government reference rates. The figures may include different sizes and property types. They are historical agreement values, not current asking prices or the total cost including extra charges.
Sales Report
Compare reported agreement values by building, size and floor. See which homes were marked unsold on the date shown.
Inside this registered phase
162 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.
MahaRERA · per-home inventory · read 8 September 2026
Scroll sideways to see all columns.
| Filed building | Entries | Sold | Booked | Marked unsold | Other / unstated status | Recorded carpet-area range |
|---|---|---|---|---|---|---|
| A | 54 | 38 | 0 | 6 | 10 | 55.93–59.23 sq m≈ 602–638 sq ft |
| B | 54 | 36 | 2 | 6 | 10 | 55.93–56.70 sq m≈ 602–610 sq ft |
| C | 54 | 3 | 0 | 45 | 6 | 55.93–59.23 sq m≈ 602–638 sq ft |
Different sizes are not necessarily different bedroom types. How we read and summarise the filing →
Unit Report
Understand its light, privacy, layout and surroundings. See how it compares with similar homes and other options in this project.
Didn’t help you decide? Full refund — no questions asked.
The same home number may appear in more than one building. Check both before choosing.
MahaRERA · per-home inventory · read 8 September 2026
| Home / building | Floor in the record | Carpet area | Reported status | Agreement value | Assess |
|---|---|---|---|---|---|
| A-1001A | 10 | 59.23 sq m≈ 638 sq ft | Sold | ₹5,286,500 | |
| A-1002A | 10 | 56.7 sq m≈ 610 sq ft | Sold | ₹4,900,000 | |
| A-1003A | 10 | 56.7 sq m≈ 610 sq ft | Sold | ₹4,450,000 | |
| A-1004A | 10 | 59.23 sq m≈ 638 sq ft | Sold | ₹5,060,000 | |
| A-101A | 1 | 58.89 sq m≈ 634 sq ft | Marked unsold | Not stated | |
| A-102A | 1 | 55.93 sq m≈ 602 sq ft | Owner investor | Not stated | |
| A-103A | 1 | 55.93 sq m≈ 602 sq ft | Owner investor | Not stated | |
| A-104A | 1 | 58.89 sq m≈ 634 sq ft | Marked unsold | Not stated | |
| A-1101A | 11 | 59.23 sq m≈ 638 sq ft | Sold | ₹5,253,550 | |
| A-1102A | 11 | 56.7 sq m≈ 610 sq ft | Owner investor | Not stated | |
| A-1103A | 11 | 56.7 sq m≈ 610 sq ft | Sold | ₹4,475,980 | |
| A-1104A | 11 | 59.23 sq m≈ 638 sq ft | Sold | ₹5,835,000 |
Read every entry in one table: Read the complete saved home list.
Choose the home you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.
More from the RERA documents
₹219,649,000 of an estimated ₹298,928,327 was reported as incurred (73.5%). This percentage is about costs. It does not show how much construction is complete.
MahaRERA project filing · read 19 July 2026 · registration P52100026329
Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.
| Building | Activity | Reported |
|---|---|---|
| B | Excavation | 100.0% |
| B | Basement (if any) | 100.0% |
| B | Podiums (if any) | 100.0% |
| B | Plinth | 100.0% |
| B | Stilt Floor | 100.0% |
| B | Slabs of Super Structure | 100.0% |
| B | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 95.0% |
| B | Sanitary Fittings within the flats / premises | 0.0% |
| B | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 80.0% |
| B | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 70.0% |
| B | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 15.0% |
| C | Excavation | 100.0% |
| C | Basement (if any) | 100.0% |
| C | Podiums (if any) | 100.0% |
| C | Plinth | 100.0% |
| C | Stilt Floor | 100.0% |
| C | Slabs of Super Structure | 10.0% |
| C | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0.0% |
| C | Sanitary Fittings within the flats / premises | 0.0% |
| C | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0.0% |
| C | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0.0% |
| C | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0.0% |
| A | Excavation | 100.0% |
| A | Basement (if any) | 100.0% |
| A | Podiums (if any) | 100.0% |
| A | Plinth | 100.0% |
| A | Stilt Floor | 100.0% |
| A | Slabs of Super Structure | 100.0% |
| A | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 95.0% |
| A | Sanitary Fittings within the flats / premises | 0.0% |
| A | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 65.0% |
| A | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 70.0% |
| A | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 10.0% |
MahaRERA project filing · read 19 July 2026 · registration P52100026329
| Revised target | Reason given by the builder |
|---|---|
| 30 June 2026 | We, the promoters of Karma Iconic, respectfully seek a 12-month extension of project registration under the second proviso of Section 6 of the Real Estate (Regulation and Development) Act, 2016, citing reasons beyond the control of the promoter. The project, located at S. No. 9 to 14, Hissa No. 1/61 Part, Mundhwa, Pune, has been delayed due to statutory and administrative obstacles arising from government and municipal authorities. Despite our full compliance with MahaRERA regulations, the project faced delays primarily due to the embargo imposed by Government Resolution (GR) dated 06/08/2021, issued by the Urban Development Department, which halted all TDR/FSI approvals in 11 newly merged villages, including our project location i.e. Keshavnagar - Mundhwa (7/12 attached herewith), where our project is situated. This embargo lasted until 22/12/2022. Further, though these villages were added to PMC limits in 2017, the Draft Development Plan (DDP) was not published until mid-2024. This prolonged absence of a DDP created a regulatory vacuum, preventing issuance of Development Plan Opinion (DPO)—a mandatory prerequisite for obtaining revised layout and building plan approvals. All the above-mentioned Government Resolutions explicitly apply to our project as they cover Keshavnagar – Mundhwa, which is the village of our project as recorded in the 7/12 extract, thereby proving the direct applicability of these statutory restrictions to our site and confirming the veracity of our claims. Only after the State Government took over planning responsibilities in June 2024 was our project able to proceed. Additional delays occurred due to planning changes, including the widening of the approach road from 12m to 36m, resulting in further delays. Despite these setbacks, which are clearly due to government-issued orders, GRs, and municipal delays, Wings A and B are structurally complete, finishing work is underway, and 2 of 15 floors of Wing C have been constructed. With the requested extension, we intend to complete Wing C within 12 months and deliver all units to allottees. The delay is not due to any fault of the promoter but is attributable to “reasons beyond the control of the promoter” under Section 6. Requiring consent from allottees in this scenario would impose an unfair burden on the promoter and may jeopardize the interest of the allottees who await timely completion. We therefore seek a 12month extension up to 30/06/2026, in public interest and as per law |
| 30 June 2027 | Respected Sir/Madam, We, the promoters of Karma Iconic, registered with the Authority under Registration No. P52100026329, humbly submit this application seeking extension of project registration up to 30/06/2027 for completion of the balance construction work and procurement of the Occupancy Certificate. The present completion date is 30/06/2026. Considering unavoidable circumstances affecting construction activities, we request an extension of 1 Year. The registered Agreement for Sale executed with the allottees also provides that in the event of reasonable circumstances beyond the control of the promoter, a reasonable extension shall be permissible. I. Grounds for Seeking Extension Impact of War and Geopolitical Situation Global disturbances and instability in trade and transportation disrupted supply chains, delaying procurement of essential construction materials and equipment. Shortage and Escalation of Materials Severe shortage and abnormal price escalation in steel, cement, electrical items, plumbing materials, aluminium products, tiles, and finishing materials substantially impacted the construction schedule. Labour and Contractor Availability Shortage of skilled and unskilled labour, delayed contractor mobilization, and inconsistent workforce availability affected continuity and pace of construction. Supply Chain and Transportation Delays Fluctuating fuel prices, shortage of vehicles, delayed deliveries, and congestion in logistics networks caused unavoidable delays in timely delivery of materials and machinery. Other Unforeseen Circumstances Market instability, inflationary pressures, procurement delays, and operational challenges collectively impacted the project timeline. The delay is genuine, unintentional, and beyond the control of the promoter. Substantial work has already been completed, and the remaining activities shall be completed within the extended period sought. II. Planning for Completion The promoter remains fully committed to completing the project within the extended timeline. Financial arrangements, manpower planning, procurement scheduling, and contractor coordination have been undertaken to ensure expeditious completion of finishing work, services installation, statutory compliances, and Occupancy Certificate formalities. Supporting Documents Form B Format B Updated Project Information and Relevant Forms |
MahaRERA project filing · read 19 July 2026 · registration P52100026329
RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.
| Filing | Own funds | Borrowing | Payments from buyers | Total |
|---|---|---|---|---|
| Estimated plan | ₹20,000,000 | ₹120,000,000 | ₹372,886,933 | ₹552,886,933 |
| Actual raised | ₹81,388,736 | ₹0 | ₹287,816,172 | ₹397,204,908 |
MahaRERA project filing · read 19 July 2026 · registration P52100026329
23 elapsed quarterly periods in the captured compliance schedule. No active quarterly default was recorded in this snapshot.
MahaRERA project filing · read 19 July 2026 · registration P52100026329
A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.
MahaRERA project filing · read 19 July 2026 · registration P52100026329
Builder and past records
Projects registered under this company
1Pune registrations
These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.
MahaRERA Pune registration records · read 12 July 2026
Past records of sales and unsold homes
26 September 2026
57 marked unsold · 77 sold · 2 booked.
Saved MahaRERA home list
17 September 2026
57 marked unsold · 77 sold · 2 booked.
Saved MahaRERA home list
8 September 2026
57 marked unsold · 77 sold · 2 booked.
Saved MahaRERA home list
19 July 2026
58 marked unsold · 77 sold · 1 booked.
Saved MahaRERA home list
These dates show when the records were saved, not when homes were sold. Sales may have changed since then, even if the saved counts are the same.
More projects to explore
These projects list the same locality. They may differ in exact location, home type and price.
Mundhawa · Pune
PR1261012501453
122 of 189 entries marked unsold
MahaRERA · per-home inventory · read 12 September 2026
View project details →Mundhawa · Pune
P52100078851
122 of 256 entries marked unsold
MahaRERA · per-home inventory · read 11 September 2026
View project details →Mundhawa · Pune
P52100077317
60 of 146 entries marked unsold
MahaRERA · per-home inventory · read 11 September 2026
View project details →Project Comparison Report
Compare up to three projects. We read their plans and RERA documents, recommend homes in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.
2 projects · ₹7,999
3 projects · ₹9,999
Within 1 working day
Didn’t help you decide? Full refund — no questions asked.
Compare project details for free →MahaRERA · registration record · read 12 July 2026
MahaRERA · per-home inventory · read 8 September 2026
This is a past RERA home list, not current availability. It does not give the date each home was sold.
Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.
Open MahaRERA · search P52100026329 ↗