The builder’s RERA record, explained

SKY COUNTY

Deshmukh Developments · P52100027014

MahaRERA · registration record · read 12 July 2026

Choose a report ↓

What does the RERA record show?

For SKY COUNTY (P52100027014), 245 of 245 entries were marked unsold in the MahaRERA home list dated 18 July 2026 (saved-file date).

MahaRERA · per-home inventory · saved-file date 18 July 2026

These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.

What would help you decide?

Buyer’s Report

Understand this project

Find homes to consider, with advice on light, layout, privacy and surroundings.

₹4,999

Unit Report

Check a particular home

See its advantages, drawbacks and how it compares with other homes in this project.

₹3,999

Project Comparison Report

Choose between projects

Compare two or three projects and get recommended homes in order, with reasons for each choice.

From ₹7,999

Choose projects →

Project status and completion date.

Inside this registered phase

How do the buildings compare in the record?

245 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.

MahaRERA · per-home inventory · saved-file date 18 July 2026

Scroll sideways to see all columns.

Building names, sale status and carpet areas — not current availability
Filed buildingEntriesSoldBookedMarked unsoldOther / unstated statusRecorded carpet-area range
A10700107012.36–39.88 sq m≈ 133–429 sq ft
B750075030.01 sq m≈ 323 sq ft
C630063030.01 sq m≈ 323 sq ft

Different sizes are not necessarily different bedroom types. How we read and summarise the filing →

Unit Report

Is this the right
home for you?

Understand its light, privacy, layout and surroundings. See how it compares with similar homes and other options in this project.

₹3,999 · 1 working day

Didn’t help you decide? Full refund — no questions asked.

Find your home in the RERA list.

The same home number may appear in more than one building. Check both before choosing.

245 listed entries

MahaRERA · per-home inventory · saved-file date 18 July 2026

RERA home list, not current availability
Home / buildingFloor in the recordCarpet areaReported statusAgreement valueAssess
1001A1039.88 sq m≈ 429 sq ftMarked unsoldNot stated
1002A1039.88 sq m≈ 429 sq ftMarked unsoldNot stated
1003A1039.88 sq m≈ 429 sq ftMarked unsoldNot stated
1004A1039.88 sq m≈ 429 sq ftMarked unsoldNot stated
1005A1030.0 sq m≈ 323 sq ftMarked unsoldNot stated
1006A1030.0 sq m≈ 323 sq ftMarked unsoldNot stated
1007A1030.0 sq m≈ 323 sq ftMarked unsoldNot stated
1008A1030.0 sq m≈ 323 sq ftMarked unsoldNot stated
101A139.88 sq m≈ 429 sq ftMarked unsoldNot stated
102A139.88 sq m≈ 429 sq ftMarked unsoldNot stated
103A139.88 sq m≈ 429 sq ftMarked unsoldNot stated
104A139.88 sq m≈ 429 sq ftMarked unsoldNot stated

Read every entry in one table: Read the complete saved home list.

Choose the home you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.

More from the RERA documents

Construction progress and project documents.

Cost reported as incurred

₹145,756,371 of an estimated ₹342,682,502 was reported as incurred (42.5%). This percentage is about costs. It does not show how much construction is complete.

MahaRERA project filing · read 19 July 2026 · registration P52100027014

Work reported, by building

Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.

See all reported activities
BuildingActivityReported
AExcavation100.0%
ABasement (if any)0.0%
APodiums (if any) 0.0%
APlinth100.0%
AStilt Floor 0.0%
ASlabs of Super Structure95.0%
AInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85.0%
ASanitary Fittings within the flats / premises70.0%
AStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80.0%
AExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90.0%
AInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.40.0%
BExcavation100.0%
BBasement (if any)0.0%
BPodiums (if any) 0.0%
BPlinth0.0%
BStilt Floor 100.0%
BSlabs of Super Structure20.0%
BInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
BSanitary Fittings within the flats / premises0.0%
BStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
BExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
BInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
CExcavation100.0%
CBasement (if any)0.0%
CPodiums (if any) 0.0%
CPlinth0.0%
CStilt Floor 0.0%
CSlabs of Super Structure0.0%
CInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
CSanitary Fittings within the flats / premises0.0%
CStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
CExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
CInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%

MahaRERA project filing · read 19 July 2026 · registration P52100027014

Reported deadline extensions

Revised targetReason given by the builder
28 December 2027*Added new wing I, Pratik Deshmukh, Promoter of the Project Sky County, hereby inform and convey to you that, previously the Completion Date for the Project was 01/05/2025. This project is being implemented under PMAY Scheme and the previous Approval Authority and implementing agency for the project was Pune Metropolitan Region Development Authority (PMRDA). Due to lack of information and guidance from the PMRDA the project was not reflecting on the Central Housing Portal/Website. Precious time was lost in all the follow-ups with the PMRDA, ultimately to no avail. We then approached MHADA and it took over the Project and became the implementing and approval authority by issuing Order regarding the same. Hence, PMRDA was no longer the approval authority. All this work took tremendous amount of time to succeed and meanwhile I could not initiate the Work of the project in a timely manner, also, I was unable to make any progress in the project once registered under MahaRERA. Keeping the delay in mind and the importance of project completion in a timely manner we have proposed the completion date to 28th December 2027. Hence, I request you to accept my application for Extension of project. I have disclosed all the required information on the MahaRERA Portal along with the Order of MHADA.

MahaRERA project filing · read 19 July 2026 · registration P52100027014

Where the project funding comes from

RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.

FilingOwn fundsBorrowingPayments from buyersTotal
Estimated plan₹196,850,207₹36,500,000₹0₹233,350,207
Actual raised₹95,669,878₹36,500,000₹0₹132,169,878

MahaRERA project filing · read 19 July 2026 · registration P52100027014

Quarterly filing record

21 elapsed quarterly periods in the captured compliance schedule. No active quarterly default was recorded in this snapshot.

MahaRERA project filing · read 19 July 2026 · registration P52100027014

Documents named in the filing

  • Form 1 — Architect's certificate · 1 listed
  • Form 3 — CA certificate · 1 listed
  • Form 2 — Engineer's certificate · 1 listed
  • Title / search report · 1 listed
  • Form B — Promoter declaration · 1 listed
  • Sanctioned layout plan · 1 listed
  • Sanctioned building plan · 3 listed

A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.

MahaRERA project filing · read 19 July 2026 · registration P52100027014

Builder and past records

What else does the record show?

Projects registered under this company

Deshmukh Developments

3Pune registrations

These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.

MahaRERA Pune registration records · read 12 July 2026

Explore other registrations

Past records of sales and unsold homes

  1. 26 September 2026

    245 marked unsold · 0 sold · 0 booked.

    Saved MahaRERA home list

  2. 17 September 2026

    245 marked unsold · 0 sold · 0 booked.

    Saved MahaRERA home list

  3. 9 September 2026

    245 marked unsold · 0 sold · 0 booked.

    Saved MahaRERA home list

  4. 19 July 2026

    245 marked unsold · 0 sold · 0 booked.

    Saved MahaRERA home list

These dates show when the records were saved, not when homes were sold. Sales may have changed since then, even if the saved counts are the same.

Project Comparison Report

Which project should you buy in?
And which home?

Compare up to three projects. We read their plans and RERA documents, recommend homes in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.

Create my Comparison Report →

2 projects · ₹7,999
3 projects · ₹9,999

Within 1 working day

Didn’t help you decide? Full refund — no questions asked.

Compare project details for free →

Sources and dates.

MahaRERA · registration record · read 12 July 2026

MahaRERA · per-home inventory · saved-file date 18 July 2026

This is a past RERA home list, not current availability. It does not give the date each home was sold.

The home-list date is based on the saved file’s details.

Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.

Open MahaRERA · search P52100027014 ↗