The builder’s RERA record, explained

Arunya A Wing

GM Buildcon · P52100027329

MahaRERA · registration record · read 12 July 2026

Choose a report ↓

What does the RERA record show?

For Arunya A Wing (P52100027329), 10 of 119 entries were marked unsold in the MahaRERA home list dated 18 July 2026 (saved-file date).

MahaRERA · per-home inventory · saved-file date 18 July 2026

For Arunya A Wing, ₹6,158 per sq ft of carpet area is the median rate across 102 sold or booked entries with prices in the MahaRERA home list dated 18 July 2026 (saved-file date). These are historical agreement values, not current asking prices.

MahaRERA · per-home inventory · saved-file date 18 July 2026

These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.

What would help you decide?

Buyer’s Report

Understand this project

Find homes to consider, with advice on light, layout, privacy and surroundings.

₹4,999

Unit Report

Check a particular home

See its advantages, drawbacks and how it compares with other homes in this project.

₹3,999

Project Comparison Report

Choose between projects

Compare two or three projects and get recommended homes in order, with reasons for each choice.

From ₹7,999

Choose projects →

Project status and completion date.

Prices reported to RERA

What prices have been reported?

₹6,158/ sq ft carpet area

Across 102 sold or booked entries with reported prices. The middle 80% of rates fall between ₹5,429 and ₹6,852.

MahaRERA · per-home inventory · saved-file date 18 July 2026

How is this calculated?

For each sold or booked entry, we divide the reported agreement value by its carpet area in square feet. The median is the middle rate when these rates are put in order. We show it only when at least five entries have prices. We exclude valuations of unsold homes and government reference rates. The figures may include different sizes and property types. They are historical agreement values, not current asking prices or the total cost including extra charges.

Sales Report

What did similar homes sell for?

Compare reported agreement values by building, size and floor. See which homes were marked unsold on the date shown.

₹2,999 · delivered on payment

Inside this registered phase

How do the buildings compare in the record?

119 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.

MahaRERA · per-home inventory · saved-file date 18 July 2026

Scroll sideways to see all columns.

Building names, sale status and carpet areas — not current availability
Filed buildingEntriesSoldBookedMarked unsoldOther / unstated statusRecorded carpet-area range
A Building119102010729.73–49.47 sq m≈ 320–532 sq ft

Different sizes are not necessarily different bedroom types. How we read and summarise the filing →

Unit Report

Is this the right
home for you?

Understand its light, privacy, layout and surroundings. See how it compares with similar homes and other options in this project.

₹3,999 · 1 working day

Didn’t help you decide? Full refund — no questions asked.

Find your home in the RERA list.

The same home number may appear in more than one building. Check both before choosing.

119 listed entries

MahaRERA · per-home inventory · saved-file date 18 July 2026

RERA home list, not current availability
Home / buildingFloor in the recordCarpet areaReported statusAgreement valueAssess
1001A Building1044.84 sq m≈ 483 sq ftSold₹2,960,390
1002A Building1033.56 sq m≈ 361 sq ftMarked unsoldNot stated
1003A Building1033.56 sq m≈ 361 sq ftSold₹2,176,000
1004A Building1033.56 sq m≈ 361 sq ftSold₹2,129,600
1005A Building1049.47 sq m≈ 532 sq ftSold₹3,242,970
1006A Building1049.47 sq m≈ 532 sq ftSold₹3,373,800
1007A Building1033.56 sq m≈ 361 sq ftSold₹2,222,160
1008A Building1033.56 sq m≈ 361 sq ftSold₹2,000,000
1009A Building1033.56 sq m≈ 361 sq ftSold₹2,130,500
101A Building140.92 sq m≈ 440 sq ftMarked unsoldNot stated
1010A Building1044.84 sq m≈ 483 sq ftSold₹2,805,000
102A Building130.77 sq m≈ 331 sq ftNot for saleNot stated

Read every entry in one table: Read the complete saved home list.

Choose the home you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.

More from the RERA documents

Construction progress and project documents.

Cost reported as incurred

₹134,359,283 of an estimated ₹136,500,000 was reported as incurred (98.4%). This percentage is about costs. It does not show how much construction is complete.

MahaRERA project filing · read 19 July 2026 · registration P52100027329

Work reported, by building

Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.

See all reported activities
BuildingActivityReported
A BuildingExcavation100.0%
A BuildingBasement (if any)0.0%
A BuildingPodiums (if any) 0.0%
A BuildingPlinth100.0%
A BuildingStilt Floor 100.0%
A BuildingSlabs of Super Structure100.0%
A BuildingInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100.0%
A BuildingSanitary Fittings within the flats / premises85.0%
A BuildingStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100.0%
A BuildingExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100.0%
A BuildingInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.85.0%
Arunya B Building ProposedExcavation0.0%
Arunya B Building ProposedBasement (if any)0.0%
Arunya B Building ProposedPodiums (if any) 0.0%
Arunya B Building ProposedPlinth0.0%
Arunya B Building ProposedStilt Floor 0.0%
Arunya B Building ProposedSlabs of Super Structure0.0%
Arunya B Building ProposedInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
Arunya B Building ProposedSanitary Fittings within the flats / premises0.0%
Arunya B Building ProposedStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
Arunya B Building ProposedExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Arunya B Building ProposedInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%

MahaRERA project filing · read 19 July 2026 · registration P52100027329

Reported deadline extensions

Revised targetReason given by the builder
30 June 2025The construction of project has been very seriously negatively affected by the Covid and related lockdowns. Also the project falls under very affordable housing scheme. The main targeted customers were from lower middle class segment. Due to Covid and related disruption in economy especially the lower middle class, the demand for such houses has dropped to almost zero. The promoters could not sell or even allot a single unit in the said project. This extension is requested u/s.6 of RERA. There is no requirement of any permission or approval from competent authority which is valid for a period that is longer than the proposed term of extension of the registration sought from the regulatory authority .
31 December 20251. The first phase of the entire project named Arunya B got delayed due to several reasons like: a. Frequent changes in the partners resulting in change of ownership, authority and responsibility, b. incarceration of one of the partners in an attempted murder case who was handling statutory compliances, c. delays in obtaining fir NOC d. loss of important original documents resulting in delayed demarcations, e. Covid disruptions This project was completed after extension from RERA authorities and possession has been handed over to the buyers. All compliances have been done. 2. This project Arunya A is the second phase of larger Project Arunya. Since the first project got delayed, this second phase too got delayed. We had earlier applied for any extension till 30.06.2025 since we expected this phase to get completed by that date. Accordingly, our application for extension was approved and we were given an extension till 30.06.25. 3. The construction of this phase is being carried out in full swing. However we forsee that the project might get delayed due to the following multiple reasons: a. Mass strike by all the suppliers of crush sand and stone metal against actions taken by government authorities on them and extension of mining lease. Copies of relevant proofs is attached. b. One of our ex-partners filed a police complaint at the Commissioner of Police office. This resulted in diversion of the partners time and efforts in resolving the issues. The police department too acted in very high-handed manner and restrained our vehicles, labour and partners from entering the premises. Proof for the same is also attached. c. The said ex-partner then was trying to derail and delay the project by using coersive techniques. We were forced to file a civil case on our ex-partner for the same. Copy of the same is also enclosed. Both the above cases consumed lot of time, efforts and money of the partners. d. Since the project got delayed, the customers and future bookings to was adversely impacted. This weak realizations from customers too put lot of strain on our finances. e. To make the matters worse, monsoon rains which are generally expected in second week of June hit our project in May 25 itself. The unseasonal rains and early monsoon completely disrupted our progress. The rains also caused huge financial loss to our raw material like cement, steel, sand, fittings. The work like scaffoldings, premix, paints too were damaged to a large extent.
31 May 2026There were liquidity issues and delays in funding. Labour and material shortages, along with disruptions in supply chains and workforce availability, are impacting construction timelines.

MahaRERA project filing · read 19 July 2026 · registration P52100027329

Where the project funding comes from

RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.

FilingOwn fundsBorrowingPayments from buyersTotal
Estimated plan₹54,039,283₹0₹168,510,717₹222,550,000
Actual raised₹54,039,283₹0₹147,577,339₹201,616,622

MahaRERA project filing · read 19 July 2026 · registration P52100027329

Quarterly filing record

23 elapsed quarterly periods in the captured compliance schedule. Active default was recorded for FY 2026-2027.

MahaRERA project filing · read 19 July 2026 · registration P52100027329

Documents named in the filing

  • Promoter PAN · 1 listed
  • Form 1 — Architect's certificate · 3 listed
  • Form 3 — CA certificate · 4 listed
  • Form 2 — Engineer's certificate · 3 listed
  • Title / search report · 1 listed
  • Form B — Promoter declaration · 5 listed
  • Sanctioned layout plan · 3 listed
  • Sanctioned building plan · 5 listed
  • Encumbrance certificate · 1 listed

A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.

MahaRERA project filing · read 19 July 2026 · registration P52100027329

Builder and past records

What else does the record show?

Projects registered under this company

GM Buildcon

2Pune registrations

These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.

MahaRERA Pune registration records · read 12 July 2026

Explore other registrations

Past records of sales and unsold homes

  1. 26 September 2026

    10 marked unsold · 102 sold · 0 booked.

    Saved MahaRERA home list

  2. 17 September 2026

    10 marked unsold · 102 sold · 0 booked.

    Saved MahaRERA home list

  3. 9 September 2026

    10 marked unsold · 102 sold · 0 booked.

    Saved MahaRERA home list

  4. 19 July 2026

    10 marked unsold · 102 sold · 0 booked.

    Saved MahaRERA home list

These dates show when the records were saved, not when homes were sold. Sales may have changed since then, even if the saved counts are the same.

More projects to explore

Other projects in this locality.

These projects list the same locality. They may differ in exact location, home type and price.

Project Comparison Report

Which project should you buy in?
And which home?

Compare up to three projects. We read their plans and RERA documents, recommend homes in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.

Create my Comparison Report →

2 projects · ₹7,999
3 projects · ₹9,999

Within 1 working day

Didn’t help you decide? Full refund — no questions asked.

Compare project details for free →

Sources and dates.

MahaRERA · registration record · read 12 July 2026

MahaRERA · per-home inventory · saved-file date 18 July 2026

This is a past RERA home list, not current availability. It does not give the date each home was sold.

The home-list date is based on the saved file’s details.

Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.

Open MahaRERA · search P52100027329 ↗