The builder’s RERA record, explained
GM Buildcon · P52100027329
For Arunya A Wing (P52100027329), 10 of 119 entries were marked unsold in the MahaRERA home list dated 18 July 2026 (saved-file date).
MahaRERA · per-home inventory · saved-file date 18 July 2026
For Arunya A Wing, ₹6,158 per sq ft of carpet area is the median rate across 102 sold or booked entries with prices in the MahaRERA home list dated 18 July 2026 (saved-file date). These are historical agreement values, not current asking prices.
MahaRERA · per-home inventory · saved-file date 18 July 2026
These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.
Builder’s completion target
This target date has passed. The record shown here does not confirm whether the project is complete or has received more time.
Status shown on RERA
This is the status shown on RERA. It does not confirm an occupancy certificate or today’s construction progress.
Prices reported to RERA
₹6,158/ sq ft carpet area
Across 102 sold or booked entries with reported prices. The middle 80% of rates fall between ₹5,429 and ₹6,852.
MahaRERA · per-home inventory · saved-file date 18 July 2026
For each sold or booked entry, we divide the reported agreement value by its carpet area in square feet. The median is the middle rate when these rates are put in order. We show it only when at least five entries have prices. We exclude valuations of unsold homes and government reference rates. The figures may include different sizes and property types. They are historical agreement values, not current asking prices or the total cost including extra charges.
Sales Report
Compare reported agreement values by building, size and floor. See which homes were marked unsold on the date shown.
Inside this registered phase
119 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.
MahaRERA · per-home inventory · saved-file date 18 July 2026
Scroll sideways to see all columns.
| Filed building | Entries | Sold | Booked | Marked unsold | Other / unstated status | Recorded carpet-area range |
|---|---|---|---|---|---|---|
| A Building | 119 | 102 | 0 | 10 | 7 | 29.73–49.47 sq m≈ 320–532 sq ft |
Different sizes are not necessarily different bedroom types. How we read and summarise the filing →
Unit Report
Understand its light, privacy, layout and surroundings. See how it compares with similar homes and other options in this project.
Didn’t help you decide? Full refund — no questions asked.
The same home number may appear in more than one building. Check both before choosing.
MahaRERA · per-home inventory · saved-file date 18 July 2026
| Home / building | Floor in the record | Carpet area | Reported status | Agreement value | Assess |
|---|---|---|---|---|---|
| 1001A Building | 10 | 44.84 sq m≈ 483 sq ft | Sold | ₹2,960,390 | |
| 1002A Building | 10 | 33.56 sq m≈ 361 sq ft | Marked unsold | Not stated | |
| 1003A Building | 10 | 33.56 sq m≈ 361 sq ft | Sold | ₹2,176,000 | |
| 1004A Building | 10 | 33.56 sq m≈ 361 sq ft | Sold | ₹2,129,600 | |
| 1005A Building | 10 | 49.47 sq m≈ 532 sq ft | Sold | ₹3,242,970 | |
| 1006A Building | 10 | 49.47 sq m≈ 532 sq ft | Sold | ₹3,373,800 | |
| 1007A Building | 10 | 33.56 sq m≈ 361 sq ft | Sold | ₹2,222,160 | |
| 1008A Building | 10 | 33.56 sq m≈ 361 sq ft | Sold | ₹2,000,000 | |
| 1009A Building | 10 | 33.56 sq m≈ 361 sq ft | Sold | ₹2,130,500 | |
| 101A Building | 1 | 40.92 sq m≈ 440 sq ft | Marked unsold | Not stated | |
| 1010A Building | 10 | 44.84 sq m≈ 483 sq ft | Sold | ₹2,805,000 | |
| 102A Building | 1 | 30.77 sq m≈ 331 sq ft | Not for sale | Not stated |
Read every entry in one table: Read the complete saved home list.
Choose the home you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.
More from the RERA documents
₹134,359,283 of an estimated ₹136,500,000 was reported as incurred (98.4%). This percentage is about costs. It does not show how much construction is complete.
MahaRERA project filing · read 19 July 2026 · registration P52100027329
Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.
| Building | Activity | Reported |
|---|---|---|
| A Building | Excavation | 100.0% |
| A Building | Basement (if any) | 0.0% |
| A Building | Podiums (if any) | 0.0% |
| A Building | Plinth | 100.0% |
| A Building | Stilt Floor | 100.0% |
| A Building | Slabs of Super Structure | 100.0% |
| A Building | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100.0% |
| A Building | Sanitary Fittings within the flats / premises | 85.0% |
| A Building | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100.0% |
| A Building | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100.0% |
| A Building | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 85.0% |
| Arunya B Building Proposed | Excavation | 0.0% |
| Arunya B Building Proposed | Basement (if any) | 0.0% |
| Arunya B Building Proposed | Podiums (if any) | 0.0% |
| Arunya B Building Proposed | Plinth | 0.0% |
| Arunya B Building Proposed | Stilt Floor | 0.0% |
| Arunya B Building Proposed | Slabs of Super Structure | 0.0% |
| Arunya B Building Proposed | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0.0% |
| Arunya B Building Proposed | Sanitary Fittings within the flats / premises | 0.0% |
| Arunya B Building Proposed | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0.0% |
| Arunya B Building Proposed | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0.0% |
| Arunya B Building Proposed | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0.0% |
MahaRERA project filing · read 19 July 2026 · registration P52100027329
| Revised target | Reason given by the builder |
|---|---|
| 30 June 2025 | The construction of project has been very seriously negatively affected by the Covid and related lockdowns. Also the project falls under very affordable housing scheme. The main targeted customers were from lower middle class segment. Due to Covid and related disruption in economy especially the lower middle class, the demand for such houses has dropped to almost zero. The promoters could not sell or even allot a single unit in the said project. This extension is requested u/s.6 of RERA. There is no requirement of any permission or approval from competent authority which is valid for a period that is longer than the proposed term of extension of the registration sought from the regulatory authority . |
| 31 December 2025 | 1. The first phase of the entire project named Arunya B got delayed due to several reasons like: a. Frequent changes in the partners resulting in change of ownership, authority and responsibility, b. incarceration of one of the partners in an attempted murder case who was handling statutory compliances, c. delays in obtaining fir NOC d. loss of important original documents resulting in delayed demarcations, e. Covid disruptions This project was completed after extension from RERA authorities and possession has been handed over to the buyers. All compliances have been done. 2. This project Arunya A is the second phase of larger Project Arunya. Since the first project got delayed, this second phase too got delayed. We had earlier applied for any extension till 30.06.2025 since we expected this phase to get completed by that date. Accordingly, our application for extension was approved and we were given an extension till 30.06.25. 3. The construction of this phase is being carried out in full swing. However we forsee that the project might get delayed due to the following multiple reasons: a. Mass strike by all the suppliers of crush sand and stone metal against actions taken by government authorities on them and extension of mining lease. Copies of relevant proofs is attached. b. One of our ex-partners filed a police complaint at the Commissioner of Police office. This resulted in diversion of the partners time and efforts in resolving the issues. The police department too acted in very high-handed manner and restrained our vehicles, labour and partners from entering the premises. Proof for the same is also attached. c. The said ex-partner then was trying to derail and delay the project by using coersive techniques. We were forced to file a civil case on our ex-partner for the same. Copy of the same is also enclosed. Both the above cases consumed lot of time, efforts and money of the partners. d. Since the project got delayed, the customers and future bookings to was adversely impacted. This weak realizations from customers too put lot of strain on our finances. e. To make the matters worse, monsoon rains which are generally expected in second week of June hit our project in May 25 itself. The unseasonal rains and early monsoon completely disrupted our progress. The rains also caused huge financial loss to our raw material like cement, steel, sand, fittings. The work like scaffoldings, premix, paints too were damaged to a large extent. |
| 31 May 2026 | There were liquidity issues and delays in funding. Labour and material shortages, along with disruptions in supply chains and workforce availability, are impacting construction timelines. |
MahaRERA project filing · read 19 July 2026 · registration P52100027329
RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.
| Filing | Own funds | Borrowing | Payments from buyers | Total |
|---|---|---|---|---|
| Estimated plan | ₹54,039,283 | ₹0 | ₹168,510,717 | ₹222,550,000 |
| Actual raised | ₹54,039,283 | ₹0 | ₹147,577,339 | ₹201,616,622 |
MahaRERA project filing · read 19 July 2026 · registration P52100027329
23 elapsed quarterly periods in the captured compliance schedule. Active default was recorded for FY 2026-2027.
MahaRERA project filing · read 19 July 2026 · registration P52100027329
A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.
MahaRERA project filing · read 19 July 2026 · registration P52100027329
Builder and past records
Projects registered under this company
2Pune registrations
These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.
MahaRERA Pune registration records · read 12 July 2026
Past records of sales and unsold homes
26 September 2026
10 marked unsold · 102 sold · 0 booked.
Saved MahaRERA home list
17 September 2026
10 marked unsold · 102 sold · 0 booked.
Saved MahaRERA home list
9 September 2026
10 marked unsold · 102 sold · 0 booked.
Saved MahaRERA home list
19 July 2026
10 marked unsold · 102 sold · 0 booked.
Saved MahaRERA home list
These dates show when the records were saved, not when homes were sold. Sales may have changed since then, even if the saved counts are the same.
More projects to explore
These projects list the same locality. They may differ in exact location, home type and price.
Dehugaon · Pune
P52100034909
8 of 94 entries marked unsold
MahaRERA · per-home inventory · saved-file date 18 July 2026
View project details →Dehugaon · Pune
P52100031774
62 of 182 entries marked unsold
MahaRERA · per-home inventory · read 9 September 2026
View project details →Project Comparison Report
Compare up to three projects. We read their plans and RERA documents, recommend homes in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.
2 projects · ₹7,999
3 projects · ₹9,999
Within 1 working day
Didn’t help you decide? Full refund — no questions asked.
Compare project details for free →MahaRERA · registration record · read 12 July 2026
MahaRERA · per-home inventory · saved-file date 18 July 2026
This is a past RERA home list, not current availability. It does not give the date each home was sold.
The home-list date is based on the saved file’s details.
Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.