homeonpaper.

Builder’s RERA records,
explained for buyers.

The builder’s RERA record, explained

SAMARTH COUNTY

D A BORADE AND SONS · P52100029698

MahaRERA · registration record · read 12 July 2026

Choose a report ↓

What does the RERA record show?

For SAMARTH COUNTY (P52100029698), 41 of 176 entries were marked unsold in the MahaRERA home list dated 18 July 2026 (saved-file date).

MahaRERA · per-home inventory · saved-file date 18 July 2026

For SAMARTH COUNTY, ₹8,952 per sq ft of carpet area is the median rate across 135 sold or booked entries with prices in the MahaRERA home list dated 18 July 2026 (saved-file date). These are historical agreement values, not current asking prices.

MahaRERA · per-home inventory · saved-file date 18 July 2026

These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.

What would help you decide?

Buyer’s Report

Understand this project

Find homes to consider, with advice on light, layout, privacy and surroundings.

₹4,999

Unit Report

Check a particular home

See its advantages, drawbacks and how it compares with other homes in this project.

₹3,999

Project Comparison Report

Choose between projects

Compare two or three projects and get recommended homes in order, with reasons for each choice.

From ₹7,999

Choose projects →

Project status and completion date.

Prices reported to RERA

What prices have been reported?

₹8,952/ sq ft carpet area

Across 135 sold or booked entries with reported prices. The middle 80% of rates fall between ₹6,002 and ₹10,041.

MahaRERA · per-home inventory · saved-file date 18 July 2026

How is this calculated?

For each sold or booked entry, we divide the reported agreement value by its carpet area in square feet. The median is the middle rate when these rates are put in order. We show it only when at least five entries have prices. We exclude valuations of unsold homes and government reference rates. The figures may include different sizes and property types. They are historical agreement values, not current asking prices or the total cost including extra charges.

Sales Report

What did similar homes sell for?

Compare reported agreement values by building, size and floor. See which homes were marked unsold on the date shown.

₹2,999 · delivered on payment

Inside this registered phase

How do the buildings compare in the record?

176 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.

MahaRERA · per-home inventory · saved-file date 18 July 2026

Scroll sideways to see all columns.

Building names, sale status and carpet areas — not current availability
Filed buildingEntriesSoldBookedMarked unsoldOther / unstated statusRecorded carpet-area range
A WING8367016042.35–112.08 sq m≈ 456–1,206 sq ft
B WING8368015057.27–112.08 sq m≈ 616–1,206 sq ft
C WING100010041.00–98.83 sq m≈ 441–1,064 sq ft

Different sizes are not necessarily different bedroom types. How we read and summarise the filing →

Unit Report

Is this the right
home for you?

Understand its light, privacy, layout and surroundings. See how it compares with similar homes and other options in this project.

₹3,999 · 1 working day

Didn’t help you decide? Full refund — no questions asked.

Find your home in the RERA list.

The same home number may appear in more than one building. Check both before choosing.

176 listed entries

MahaRERA · per-home inventory · saved-file date 18 July 2026

RERA home list, not current availability
Home / buildingFloor in the recordCarpet areaReported statusAgreement valueAssess
A-1001A WING1058.0 sq m≈ 624 sq ftSold₹6,312,476
A-1002A WING1058.0 sq m≈ 624 sq ftSold₹5,697,238
A-1003A WING1057.27 sq m≈ 616 sq ftSold₹5,375,000
A-1004A WING1057.27 sq m≈ 616 sq ftSold₹5,786,571
A-101A WING142.35 sq m≈ 456 sq ftSold₹4,495,000
A-102A WING142.35 sq m≈ 456 sq ftSold₹4,370,297
A-103A WING157.27 sq m≈ 616 sq ftMarked unsoldNot stated
A-104A WING157.27 sq m≈ 616 sq ftSold₹6,063,333
A-1101A WING1158.0 sq m≈ 624 sq ftSold₹5,955,333
A-1102A WING1158.0 sq m≈ 624 sq ftSold₹5,697,300
A-1103A WING1157.27 sq m≈ 616 sq ftSold₹5,795,536
A-1104A WING1157.27 sq m≈ 616 sq ftSold₹5,795,524

Read every entry in one table: Read the complete saved home list.

Choose the home you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.

More from the RERA documents

Construction progress and project documents.

Cost reported as incurred

₹975,963,342 of an estimated ₹976,783,342 was reported as incurred (99.9%). This percentage is about costs. It does not show how much construction is complete.

MahaRERA project filing · read 19 July 2026 · registration P52100029698

Work reported, by building

Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.

See all reported activities
BuildingActivityReported
A WINGExcavation100.0%
A WINGBasement (if any)100.0%
A WINGPodiums (if any) 100.0%
A WINGPlinth100.0%
A WINGStilt Floor 0.0%
A WINGSlabs of Super Structure25.0%
A WINGInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100.0%
A WINGSanitary Fittings within the flats / premises100.0%
A WINGStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100.0%
A WINGExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100.0%
A WINGInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100.0%
B WINGExcavation100.0%
B WINGBasement (if any)100.0%
B WINGPodiums (if any) 100.0%
B WINGPlinth100.0%
B WINGStilt Floor 0.0%
B WINGSlabs of Super Structure25.0%
B WINGInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100.0%
B WINGSanitary Fittings within the flats / premises100.0%
B WINGStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100.0%
B WINGExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100.0%
B WINGInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100.0%
C WINGExcavation100.0%
C WINGBasement (if any)100.0%
C WINGPodiums (if any) 100.0%
C WINGPlinth100.0%
C WINGStilt Floor 0.0%
C WINGSlabs of Super Structure25.0%
C WINGInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100.0%
C WINGSanitary Fittings within the flats / premises100.0%
C WINGStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100.0%
C WINGExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100.0%
C WINGInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100.0%

MahaRERA project filing · read 19 July 2026 · registration P52100029698

Reported deadline extensions

Revised targetReason given by the builder
30 June 2026Respected Sir/Madam, We, the promoters of Samarth County (Reg. No. P52100029698), humbly request an extension of the project registration, currently valid till 31/12/2025, up to 30/06/2026, to complete the remaining work and obtain the Occupancy Certificate. I. Grounds for Seeking Extension Extended Monsoon Affecting External Plastering The unusually prolonged monsoon in Maharashtra during 2025, with intermittent rains continuing into October–November, delayed external plastering and waterproofing. Internal finishing works could not commence without sealing the building envelope, causing an unavoidable shift in timelines. Delay in Statutory Approvals/NOCs Revised layout approvals and fire compliance permissions were delayed due to inter-departmental processing and administrative backlogs, despite timely submissions and consistent follow-ups. Temporary Labour Shortages Seasonal migration and diversion of skilled labour to nearby infrastructure projects led to intermittent shortages, particularly affecting external and finishing works during critical stages. Material Supply Disruptions Short-term fluctuations in availability and pricing of cement, steel, and façade materials, along with vendor delays for window and aluminium systems, caused temporary slowdowns. Supply has now stabilised. II. Current Status & Completion Plan Structural work up to the 20th floor (of 22) is completed. External plastering is ongoing, and internal finishing will commence immediately after waterproofing and façade completion. The project is progressing as per the revised execution plan and in full compliance with sanctioned plans and MahaRERA guidelines. Supporting Documents Attached: Consent Form (Format-B), Form B, Form E Updated project details (Forms 1, 2, 2A, 3, 5) Photographs of on-site work PERT chart with revised milestones In view of the above reasons, which were beyond the promoter’s reasonable control, we request the Authority to kindly grant an extension of registration till 30/06/2026. We assure continued compliance with all statutory requirements and timely quarterly updates.
31 October 2026Respected Sir/Madam, We, the promoters of SAMARTH COUNTY, registered with the Authority under Registration No. P52100029698, humbly submit this application seeking extension of project registration up to 31/10/2026 for completion of the balance construction work and procurement of the Occupancy Certificate. The present completion date is 30/06/2026. Considering unavoidable circumstances affecting construction activities, we request an extension of four months. The registered Agreement for Sale executed with the allottees also provides that in the event of reasonable circumstances beyond the control of the promoter, a reasonable extension shall be permissible. I. Grounds for Seeking Extension Impact of War and Geopolitical Situation Global disturbances and instability in trade and transportation disrupted supply chains, delaying procurement of essential construction materials and equipment. Shortage and Escalation of Materials Severe shortage and abnormal price escalation in steel, cement, electrical items, plumbing materials, aluminium products, tiles, and finishing materials substantially impacted the construction schedule. Labour and Contractor Availability Shortage of skilled and unskilled labour, delayed contractor mobilization, and inconsistent workforce availability affected continuity and pace of construction. Supply Chain and Transportation Delays Fluctuating fuel prices, shortage of vehicles, delayed deliveries, and congestion in logistics networks caused unavoidable delays in timely delivery of materials and machinery. Other Unforeseen Circumstances Market instability, inflationary pressures, procurement delays, and operational challenges collectively impacted the project timeline. The delay is genuine, unintentional, and beyond the control of the promoter. Substantial work has already been completed, and the remaining activities shall be completed within the extended period sought. II. Planning for Completion The promoter remains fully committed to completing the project within the extended timeline. Financial arrangements, manpower planning, procurement scheduling, and contractor coordination have been undertaken to ensure expeditious completion of finishing work, services installation, statutory compliances, and Occupancy Certificate formalities. Supporting Documents Form B Format B Updated Project Information and Relevant Forms

MahaRERA project filing · read 19 July 2026 · registration P52100029698

Where the project funding comes from

RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.

FilingOwn fundsBorrowingPayments from buyersTotal
Estimated plan₹84,700,000₹110,000,000₹255,003,342₹449,703,342
Actual raised₹0₹0₹559,476,794₹559,476,794

MahaRERA project filing · read 19 July 2026 · registration P52100029698

Quarterly filing record

21 elapsed quarterly periods in the captured compliance schedule. No active quarterly default was recorded in this snapshot.

MahaRERA project filing · read 19 July 2026 · registration P52100029698

Documents named in the filing

  • Promoter PAN · 1 listed
  • Form 1 — Architect's certificate · 4 listed
  • Form 3 — CA certificate · 4 listed
  • Form 2 — Engineer's certificate · 4 listed
  • Title / search report · 3 listed
  • Form B — Promoter declaration · 1 listed
  • Sanctioned building plan · 13 listed
  • Sanctioned layout plan · 3 listed

A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.

MahaRERA project filing · read 19 July 2026 · registration P52100029698

Builder and past records

What else does the record show?

Projects registered under this company

D A BORADE AND SONS

1Pune registrations

These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.

MahaRERA Pune registration records · read 12 July 2026

Explore other registrations

    Past records of sales and unsold homes

    1. 26 September 2026

      41 marked unsold · 135 sold · 0 booked.

      Saved MahaRERA home list

    2. 17 September 2026

      41 marked unsold · 135 sold · 0 booked.

      Saved MahaRERA home list

    3. 9 September 2026

      41 marked unsold · 135 sold · 0 booked.

      Saved MahaRERA home list

    4. 19 July 2026

      41 marked unsold · 135 sold · 0 booked.

      Saved MahaRERA home list

    These dates show when the records were saved, not when homes were sold. Sales may have changed since then, even if the saved counts are the same.

    More projects to explore

    Other projects in this locality.

    These projects list the same locality. They may differ in exact location, home type and price.

    Project Comparison Report

    Which project should you buy in?
    And which home?

    Compare up to three projects. We read their plans and RERA documents, recommend homes in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.

    Create my Comparison Report →

    2 projects · ₹7,999
    3 projects · ₹9,999

    Within 1 working day

    Didn’t help you decide? Full refund — no questions asked.

    Compare project details for free →

    Sources and dates.

    MahaRERA · registration record · read 12 July 2026

    MahaRERA · per-home inventory · saved-file date 18 July 2026

    This is a past RERA home list, not current availability. It does not give the date each home was sold.

    The home-list date is based on the saved file’s details.

    Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.

    Open MahaRERA · search P52100029698 ↗