The builder’s RERA record, explained

Wonder County

GREEN COLLIS LLP · P52100032072

MahaRERA · registration record · read 12 July 2026

Choose a report ↓

What does the RERA record show?

For Wonder County (P52100032072), 127 of 183 entries were marked unsold in the MahaRERA home list read 19 July 2026.

MahaRERA · per-home inventory · read 19 July 2026

These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.

What would help you decide?

Buyer’s Report

Understand this project

Find homes to consider, with advice on light, layout, privacy and surroundings.

₹4,999

Unit Report

Check a particular home

See its advantages, drawbacks and how it compares with other homes in this project.

₹3,999

Project Comparison Report

Choose between projects

Compare two or three projects and get recommended homes in order, with reasons for each choice.

From ₹7,999

Choose projects →

Project status and completion date.

Inside this registered phase

How do the buildings compare in the record?

183 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.

MahaRERA · per-home inventory · read 19 July 2026

Scroll sideways to see all columns.

Building names, sale status and carpet areas — not current availability
Filed buildingEntriesSoldBookedMarked unsoldOther / unstated statusRecorded carpet-area range
NA plots1835601270100.00–1,319.64 sq m≈ 1,076–14,204 sq ft

Different sizes are not necessarily different bedroom types. How we read and summarise the filing →

Unit Report

Is this the right
home for you?

Understand its light, privacy, layout and surroundings. See how it compares with similar homes and other options in this project.

₹3,999 · 1 working day

Didn’t help you decide? Full refund — no questions asked.

Find your home in the RERA list.

The same home number may appear in more than one building. Check both before choosing.

183 listed entries

MahaRERA · per-home inventory · read 19 July 2026

RERA home list, not current availability
Home / buildingFloor in the recordCarpet areaReported statusAgreement valueAssess
1NA plots201.75 sq m≈ 2,172 sq ftSold₹2,454,323
10NA plots167.27 sq m≈ 1,800 sq ftSold₹360,000
101NA plots152.31 sq m≈ 1,639 sq ftSold₹1,798,025
102NA plots155.98 sq m≈ 1,679 sq ftSold₹2,114,060
103NA plots149.94 sq m≈ 1,614 sq ftSold₹2,039,960
103ANA plots196.71 sq m≈ 2,117 sq ftMarked unsoldNot stated
104NA plots144.0 sq m≈ 1,550 sq ftMarked unsoldNot stated
105NA plots144.1 sq m≈ 1,551 sq ftMarked unsoldNot stated
107NA plots144.0 sq m≈ 1,550 sq ftMarked unsoldNot stated
108NA plots170.24 sq m≈ 1,832 sq ftMarked unsoldNot stated
109NA plots207.49 sq m≈ 2,233 sq ftSold₹2,250,000
11NA plots167.27 sq m≈ 1,800 sq ftSold₹360,000

Read every entry in one table: Read the complete saved home list.

Choose the home you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.

More from the RERA documents

Construction progress and project documents.

Reported deadline extensions

Revised targetReason given by the builder
31 December 2028Administrative & Approval Delays • in obtaining layout approval from local authorities. • Delay in receiving necessary permissions/NOCs from government departments. • Changes in project scope or layout after commencement. • Delay in approval of drawings and technical specifications. Land & Site Related Issues • Land acquisition or ownership disputes. • Encroachment removal taking longer than anticipated. • Unforeseen site conditions requiring additional development work. • Boundary demarcation and survey-related delays. Infrastructure Development Delays • Delay in construction of internal roads. • Delay in water supply infrastructure installation. • Delay in drainage and sewerage network development. • Delay in electricity distribution and transformer installation. • Delay in telecommunications/internet infrastructure setup. Regulatory & Compliance Issues • Environmental clearance delays. • Compliance requirements imposed by regulatory authorities. • Changes in zoning regulations or development control rules. • Litigation or legal proceedings affecting project execution. Contractor & Resource Constraints • Shortage of skilled labour and manpower. • Delay by contractors/sub-contractors in completing assigned work. • Non-availability or delayed supply of construction materials. • Equipment breakdowns and machinery-related disruptions. Financial Constraints • Delay in project funding or release of finances. • Cost escalations requiring revision of project budgets. • Cash flow issues affecting contractor payments and project progress. External Factors • Heavy rainfall, flooding, or adverse weather conditions. • Natural calamities affecting construction activities. • Pandemic-related restrictions and labour shortages. • Strikes, transport disruptions, or supply chain issues. Utility & Coordination Issues • Delay in obtaining utility connections from service providers. • Coordination issues among multiple agencies involved in the project. • Shifting of existing utility lines (water, electricity, gas, telecom) taking longer than expected.

MahaRERA project filing · read 19 July 2026 · registration P52100032072

Where the project funding comes from

RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.

FilingOwn fundsBorrowingPayments from buyersTotal
Estimated plan₹0₹0₹121,526,000₹121,526,000
Actual raised₹0₹0₹109,485,500₹109,485,500

MahaRERA project filing · read 19 July 2026 · registration P52100032072

Quarterly filing record

17 elapsed quarterly periods in the captured compliance schedule. No active quarterly default was recorded in this snapshot.

MahaRERA project filing · read 19 July 2026 · registration P52100032072

Documents named in the filing

  • Promoter PAN · 1 listed
  • Commencement certificate · 3 listed
  • Form 1 — Architect's certificate · 4 listed
  • Form 3 — CA certificate · 1 listed
  • Form 2 — Engineer's certificate · 4 listed
  • Form B — Promoter declaration · 1 listed
  • Title / search report · 2 listed
  • Sanctioned layout plan · 3 listed

A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.

MahaRERA project filing · read 19 July 2026 · registration P52100032072

Builder and past records

What else does the record show?

Projects registered under this company

GREEN COLLIS LLP

1Pune registrations

These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.

MahaRERA Pune registration records · read 12 July 2026

Explore other registrations

    Past records of sales and unsold homes

    1. 26 September 2026

      127 marked unsold · 56 sold · 0 booked.

      Saved MahaRERA home list

    2. 17 September 2026

      127 marked unsold · 56 sold · 0 booked.

      Saved MahaRERA home list

    3. 9 September 2026

      127 marked unsold · 56 sold · 0 booked.

      Saved MahaRERA home list

    4. 19 July 2026

      127 marked unsold · 56 sold · 0 booked.

      Saved MahaRERA home list

    These dates show when the records were saved, not when homes were sold. Sales may have changed since then, even if the saved counts are the same.

    Project Comparison Report

    Which project should you buy in?
    And which home?

    Compare up to three projects. We read their plans and RERA documents, recommend homes in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.

    Create my Comparison Report →

    2 projects · ₹7,999
    3 projects · ₹9,999

    Within 1 working day

    Didn’t help you decide? Full refund — no questions asked.

    Compare project details for free →

    Sources and dates.

    MahaRERA · registration record · read 12 July 2026

    MahaRERA · per-home inventory · read 19 July 2026

    This is a past RERA home list, not current availability. It does not give the date each home was sold.

    Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.

    Open MahaRERA · search P52100032072 ↗