The builder’s RERA record, explained
Mont Vert Needs · P52100032943
For Mont Vert Axis (P52100032943), 59 of 146 entries were marked unsold in the MahaRERA home list read 9 September 2026.
For Mont Vert Axis, ₹10,440 per sq ft of carpet area is the median rate across 87 sold or booked entries with prices in the MahaRERA home list read 9 September 2026. These are historical agreement values, not current asking prices.
These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.
Builder’s completion target
The builder reported this target date. It is not a confirmed handover date.
Status shown on RERA
This is the status shown on RERA. It does not confirm an occupancy certificate or today’s construction progress.
Prices reported to RERA
₹10,440/ sq ft carpet area
Across 87 sold or booked entries with reported prices. The middle 80% of rates fall between ₹9,364 and ₹14,250.
MahaRERA · per-home inventory · read 9 September 2026
For each sold or booked entry, we divide the reported agreement value by its carpet area in square feet. The median is the middle rate when these rates are put in order. We show it only when at least five entries have prices. We exclude valuations of unsold homes and government reference rates. The figures may include different sizes and property types. They are historical agreement values, not current asking prices or the total cost including extra charges.
Sales Report
Compare reported agreement values by building, size and floor. See which homes were marked unsold on the date shown.
Inside this registered phase
146 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.
MahaRERA · per-home inventory · read 9 September 2026
Scroll sideways to see all columns.
| Filed building | Entries | Sold | Booked | Marked unsold | Other / unstated status | Recorded carpet-area range |
|---|---|---|---|---|---|---|
| Mont Vert Axis | 146 | 81 | 6 | 59 | 0 | 32.39–160.20 sq m≈ 349–1,724 sq ft |
Different sizes are not necessarily different bedroom types. How we read and summarise the filing →
Unit Report
Understand its light, privacy, layout and surroundings. See how it compares with similar homes and other options in this project.
Didn’t help you decide? Full refund — no questions asked.
The same home number may appear in more than one building. Check both before choosing.
MahaRERA · per-home inventory · read 9 September 2026
| Home / building | Floor in the record | Carpet area | Reported status | Agreement value | Assess |
|---|---|---|---|---|---|
| 101Mont Vert Axis | 1 | 69.19 sq m≈ 745 sq ft | Sold | ₹8,827,239 | |
| 102Mont Vert Axis | 1 | 68.34 sq m≈ 736 sq ft | Sold | ₹8,718,796 | |
| 103Mont Vert Axis | 1 | 104.18 sq m≈ 1,121 sq ft | Sold | ₹13,291,252 | |
| 104Mont Vert Axis | 1 | 96.42 sq m≈ 1,038 sq ft | Sold | ₹14,789,505 | |
| 105Mont Vert Axis | 1 | 104.18 sq m≈ 1,121 sq ft | Sold | ₹15,979,808 | |
| 106Mont Vert Axis | 1 | 104.18 sq m≈ 1,121 sq ft | Sold | ₹15,979,950 | |
| 107Mont Vert Axis | 1 | 92.96 sq m≈ 1,001 sq ft | Sold | ₹14,258,835 | |
| 108Mont Vert Axis | 1 | 35.87 sq m≈ 386 sq ft | Sold | ₹23,049,560 | |
| 109Mont Vert Axis | 1 | 32.39 sq m≈ 349 sq ft | Marked unsold | Not stated | |
| 110Mont Vert Axis | 1 | 68.19 sq m≈ 734 sq ft | Marked unsold | Not stated | |
| 201Mont Vert Axis | 2 | 61.0 sq m≈ 657 sq ft | Sold | ₹6,474,100 | |
| 202Mont Vert Axis | 2 | 61.0 sq m≈ 657 sq ft | Marked unsold | Not stated |
Read every entry in one table: Read the complete saved home list.
Choose the home you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.
More from the RERA documents
₹274,955,917 of an estimated ₹581,471,200 was reported as incurred (47.3%). This percentage is about costs. It does not show how much construction is complete.
MahaRERA project filing · read 19 July 2026 · registration P52100032943
Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.
| Building | Activity | Reported |
|---|---|---|
| Mont Vert Axis | Excavation | 100.0% |
| Mont Vert Axis | Basement (if any) | 95.0% |
| Mont Vert Axis | Podiums (if any) | 0.0% |
| Mont Vert Axis | Plinth | 0.0% |
| Mont Vert Axis | Stilt Floor | 0.0% |
| Mont Vert Axis | Slabs of Super Structure | 0.0% |
| Mont Vert Axis | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0.0% |
| Mont Vert Axis | Sanitary Fittings within the flats / premises | 0.0% |
| Mont Vert Axis | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0.0% |
| Mont Vert Axis | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0.0% |
| Mont Vert Axis | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0.0% |
MahaRERA project filing · read 19 July 2026 · registration P52100032943
| Revised target | Reason given by the builder |
|---|---|
| 31 December 2028 | 1. Excavation took at least 8 months more due to unexpectedly hard rock strata and a weaker adjoining building on adjacent project, limiting us to use low intensity excavation equipment as an abundant precaution. 2. Revision of plan took 2 months more than expected. 3. We had to let go of a non-performing RCC contractor and hire a new contractor adding to 3 months of transition delays. 4. This project is a part of multiple projects in a basket funding with a financial institution(lenders). There is a default of loan payment of these loans. The financial institution has initiated proceedings under SARFAESI Act. We are in process of negotiations with our lenders. As a result, the work has stalled. 5. Work is planned to resume soon with privately raised money. Our priority is to complete the work in the fastest possible time. 6. We explained the situation to all allottees either in person or by telephonic conversations and requested them to give us consent under section 7(3). We have now received more than 51% consent. 7. We have never applied for extension of this project earlier. Without extension it will not be possible to complete the work. Hence it is our sincere and humble request to please consider our extension request under section 7(3). |
MahaRERA project filing · read 19 July 2026 · registration P52100032943
RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.
| Filing | Own funds | Borrowing | Payments from buyers | Total |
|---|---|---|---|---|
| Estimated plan | ₹0 | ₹0 | ₹745,808,833 | ₹866,999,191 |
| Actual raised | ₹73,228,703 | ₹0 | ₹184,044,601 | ₹425,520,584 |
MahaRERA project filing · read 19 July 2026 · registration P52100032943
17 elapsed quarterly periods in the captured compliance schedule. No active quarterly default was recorded in this snapshot.
MahaRERA project filing · read 19 July 2026 · registration P52100032943
A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.
MahaRERA project filing · read 19 July 2026 · registration P52100032943
Builder and past records
Projects registered under this company
1Pune registrations
These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.
MahaRERA Pune registration records · read 12 July 2026
Past records of sales and unsold homes
26 September 2026
59 marked unsold · 81 sold · 6 booked.
Saved MahaRERA home list
18 September 2026
59 marked unsold · 81 sold · 6 booked.
Saved MahaRERA home list
9 September 2026
59 marked unsold · 81 sold · 6 booked.
Saved MahaRERA home list
19 July 2026
61 marked unsold · 81 sold · 4 booked.
Saved MahaRERA home list
These dates show when the records were saved, not when homes were sold. Sales may have changed since then, even if the saved counts are the same.
More projects to explore
These projects list the same locality. They may differ in exact location, home type and price.
Bavdhan · Pune
P52100076756
65 of 214 entries marked unsold
MahaRERA · per-home inventory · saved-file date 18 July 2026
View project details →Bavdhan · Pune
P52100045900
3 of 263 entries marked unsold
MahaRERA · per-home inventory · read 19 July 2026
View project details →Bavdhan · Pune
P52100076968
193 of 214 entries marked unsold
MahaRERA · per-home inventory · read 19 July 2026
View project details →Project Comparison Report
Compare up to three projects. We read their plans and RERA documents, recommend homes in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.
2 projects · ₹7,999
3 projects · ₹9,999
Within 1 working day
Didn’t help you decide? Full refund — no questions asked.
Compare project details for free →MahaRERA · registration record · read 12 July 2026
MahaRERA · per-home inventory · read 9 September 2026
This is a past RERA home list, not current availability. It does not give the date each home was sold.
Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.
Open MahaRERA · search P52100032943 ↗