The builder’s RERA record, explained

AISHWARYAM INSIGNIA

VIKSAK VINODE INFRATECH LLP · P52100033510

MahaRERA · registration record · read 12 July 2026

Choose a report ↓

What does the RERA record show?

For AISHWARYAM INSIGNIA (P52100033510), 79 of 952 entries were marked unsold in the MahaRERA home list dated 18 July 2026 (saved-file date).

MahaRERA · per-home inventory · saved-file date 18 July 2026

For AISHWARYAM INSIGNIA, ₹7,124 per sq ft of carpet area is the median rate across 873 sold or booked entries with prices in the MahaRERA home list dated 18 July 2026 (saved-file date). These are historical agreement values, not current asking prices.

MahaRERA · per-home inventory · saved-file date 18 July 2026

These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.

What would help you decide?

Buyer’s Report

Understand this project

Find homes to consider, with advice on light, layout, privacy and surroundings.

₹4,999

Unit Report

Check a particular home

See its advantages, drawbacks and how it compares with other homes in this project.

₹3,999

Project Comparison Report

Choose between projects

Compare two or three projects and get recommended homes in order, with reasons for each choice.

From ₹7,999

Choose projects →

Project status and completion date.

Prices reported to RERA

What prices have been reported?

₹7,124/ sq ft carpet area

Across 873 sold or booked entries with reported prices. The middle 80% of rates fall between ₹7,010 and ₹8,035.

MahaRERA · per-home inventory · saved-file date 18 July 2026

How is this calculated?

For each sold or booked entry, we divide the reported agreement value by its carpet area in square feet. The median is the middle rate when these rates are put in order. We show it only when at least five entries have prices. We exclude valuations of unsold homes and government reference rates. The figures may include different sizes and property types. They are historical agreement values, not current asking prices or the total cost including extra charges.

Sales Report

What did similar homes sell for?

Compare reported agreement values by building, size and floor. See which homes were marked unsold on the date shown.

₹2,999 · delivered on payment

Inside this registered phase

How do the buildings compare in the record?

952 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.

MahaRERA · per-home inventory · saved-file date 18 July 2026

Scroll sideways to see all columns.

Building names, sale status and carpet areas — not current availability
Filed buildingEntriesSoldBookedMarked unsoldOther / unstated statusRecorded carpet-area range
A33133100041.44–58.56 sq m≈ 446–630 sq ft
B17917801039.38–60.78 sq m≈ 424–654 sq ft
C31731700042.16–58.56 sq m≈ 454–630 sq ft
D474700038.67 sq m≈ 416 sq ft
E780078020.30–313.54 sq m≈ 219–3,375 sq ft

Different sizes are not necessarily different bedroom types. How we read and summarise the filing →

Unit Report

Is this the right
home for you?

Understand its light, privacy, layout and surroundings. See how it compares with similar homes and other options in this project.

₹3,999 · 1 working day

Didn’t help you decide? Full refund — no questions asked.

Find your home in the RERA list.

The same home number may appear in more than one building. Check both before choosing.

952 listed entries

MahaRERA · per-home inventory · saved-file date 18 July 2026

RERA home list, not current availability
Home / buildingFloor in the recordCarpet areaReported statusAgreement valueAssess
1001A1041.44 sq m≈ 446 sq ftSold₹3,370,950
1002A1058.45 sq m≈ 629 sq ftSold₹4,491,320
1003A1058.45 sq m≈ 629 sq ftSold₹4,467,820
1004A1058.56 sq m≈ 630 sq ftSold₹4,491,041
1005A1058.56 sq m≈ 630 sq ftSold₹4,490,104
1006A1058.38 sq m≈ 628 sq ftSold₹4,467,694
1007A1058.38 sq m≈ 628 sq ftSold₹4,455,500
1008A1058.42 sq m≈ 629 sq ftSold₹4,490,928
1009A1058.42 sq m≈ 629 sq ftSold₹4,449,744
101-MHADAA141.44 sq m≈ 446 sq ftSold₹2,280,100
1010A1058.56 sq m≈ 630 sq ftSold₹4,467,616
1011A1058.56 sq m≈ 630 sq ftSold₹4,476,986

Read every entry in one table: Read the complete saved home list.

Choose the home you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.

More from the RERA documents

Construction progress and project documents.

Cost reported as incurred

₹1,802,297,003 of an estimated ₹1,931,282,392 was reported as incurred (93.3%). This percentage is about costs. It does not show how much construction is complete.

MahaRERA project filing · read 19 July 2026 · registration P52100033510

Work reported, by building

Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.

See all reported activities
BuildingActivityReported
AExcavation100.0%
ABasement (if any)100.0%
APodiums (if any) 0.0%
APlinth100.0%
AStilt Floor 0.0%
ASlabs of Super Structure100.0%
AInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises96.0%
ASanitary Fittings within the flats / premises73.14%
AStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100.0%
AExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50.0%
AInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.65.0%
BExcavation100.0%
BBasement (if any)100.0%
BPodiums (if any) 0.0%
BPlinth100.0%
BStilt Floor 0.0%
BSlabs of Super Structure100.0%
BInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises97.5%
BSanitary Fittings within the flats / premises89.88%
BStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100.0%
BExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.86.36%
BInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.70.0%
CExcavation100.0%
CBasement (if any)100.0%
CPodiums (if any) 0.0%
CPlinth100.0%
CStilt Floor 0.0%
CSlabs of Super Structure100.0%
CInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises83.33%
CSanitary Fittings within the flats / premises53.97%
CStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks87.5%
CExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.63.07%
CInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50.0%
DExcavation100.0%
DBasement (if any)0.0%
DPodiums (if any) 0.0%
DPlinth100.0%
DStilt Floor 0.0%
DSlabs of Super Structure100.0%
DInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100.0%
DSanitary Fittings within the flats / premises90.0%
DStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100.0%
DExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100.0%
DInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90.0%
EExcavation100.0%
EBasement (if any)0.0%
EPodiums (if any) 0.0%
EPlinth0.0%
EStilt Floor 0.0%
ESlabs of Super Structure0.0%
EInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
ESanitary Fittings within the flats / premises0.0%
EStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
EExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
EInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%

MahaRERA project filing · read 19 July 2026 · registration P52100033510

Reported deadline extensions

Revised targetReason given by the builder
30 June 2027To,
The Secretary,
Maharashtra Real Estate Regulatory Authority (MahaRERA),
Mumbai. Subject: Application for Extension of Registration under Section 7(3) of the Real Estate (Regulation and Development) Act, 2016 for the Project AISHWARYAM INSIGNIA (RERA No. P52100033510) Respected Sir/Madam, We, the promoters of the project AISHWARYAM INSIGNIA, registered with the Authority under Registration No. P52100033510, humbly submit this application seeking an extension of the project registration. The current registration for Wings A and B is valid till 31st December 2025, and we request an extension up to 30/06/2027 to ensure timely completion of the remaining works and procurement of the Occupancy Certificate. The request for extension is necessitated due to circumstances beyond the reasonable control of the promoter, which cumulatively impacted the construction timeline: Labour shortage due to Bihar Legislative Assembly Elections, during which a substantial portion of the migrant workforce returned to their native state, resulting in an unexpected manpower deficit. Chhath Puja-related labour migration, leading to extended absenteeism of 2–4 weeks and disruption of key construction activities. Extended and unseasonal monsoon rainfall, which adversely affected curing cycles, external plastering, waterproofing, scaffolding, and material handling, and required stoppage of work for safety reasons. Festive season slowdown (Ganesh Chaturthi to Diwali), traditionally marked by reduced labour availability and slower supplier operations. Overall inconsistency in labour availability due to overlapping effects of elections, festivals, migration, and climatic conditions, despite continuous efforts by the promoter to engage alternative labour and contractors. Notwithstanding the above, substantial on-site progress has been achieved, and the project is proceeding as per a revised execution plan. With stabilised labour availability and favourable weather conditions, the balance works—including internal finishing, external façade, services installation, and final inspections—are proposed to be completed within the extended period. The project continues to be executed strictly in accordance with sanctioned plans, applicable regulations, and MahaRERA guidelines, with full commitment to compliance, financial discipline, and transparency. Supporting documents including Consent Form (Format B), Forms B and E, Forms 1, 2, 2A, 3, and 5, and PERT chart are submitted.

MahaRERA project filing · read 19 July 2026 · registration P52100033510

Where the project funding comes from

RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.

FilingOwn fundsBorrowingPayments from buyersTotal
Estimated plan₹366,378,000₹350,000,000₹1,420,468,515₹2,136,846,515
Actual raised₹308,831,342₹350,000,000₹2,207,687,145₹2,866,518,487

MahaRERA project filing · read 19 July 2026 · registration P52100033510

Quarterly filing record

18 elapsed quarterly periods in the captured compliance schedule. No active quarterly default was recorded in this snapshot.

MahaRERA project filing · read 19 July 2026 · registration P52100033510

Documents named in the filing

  • Promoter PAN · 9 listed
  • Form 1 — Architect's certificate · 4 listed
  • Form 3 — CA certificate · 6 listed
  • Form 2 — Engineer's certificate · 4 listed
  • Title / search report · 1 listed
  • Form B — Promoter declaration · 1 listed
  • Sanctioned layout plan · 7 listed
  • Sanctioned building plan · 58 listed

A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.

MahaRERA project filing · read 19 July 2026 · registration P52100033510

Builder and past records

What else does the record show?

Projects registered under this company

VIKSAK VINODE INFRATECH LLP

1Pune registrations

These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.

MahaRERA Pune registration records · read 12 July 2026

Explore other registrations

    Past records of sales and unsold homes

    1. 26 September 2026

      79 marked unsold · 873 sold · 0 booked.

      Saved MahaRERA home list

    2. 18 September 2026

      79 marked unsold · 873 sold · 0 booked.

      Saved MahaRERA home list

    3. 9 September 2026

      79 marked unsold · 873 sold · 0 booked.

      Saved MahaRERA home list

    4. 19 July 2026

      79 marked unsold · 873 sold · 0 booked.

      Saved MahaRERA home list

    These dates show when the records were saved, not when homes were sold. Sales may have changed since then, even if the saved counts are the same.

    More projects to explore

    Other projects in this locality.

    These projects list the same locality. They may differ in exact location, home type and price.

    Project Comparison Report

    Which project should you buy in?
    And which home?

    Compare up to three projects. We read their plans and RERA documents, recommend homes in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.

    Create my Comparison Report →

    2 projects · ₹7,999
    3 projects · ₹9,999

    Within 1 working day

    Didn’t help you decide? Full refund — no questions asked.

    Compare project details for free →

    Sources and dates.

    MahaRERA · registration record · read 12 July 2026

    MahaRERA · per-home inventory · saved-file date 18 July 2026

    This is a past RERA home list, not current availability. It does not give the date each home was sold.

    The home-list date is based on the saved file’s details.

    Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.