homeonpaper.

Builder’s RERA records,
explained for buyers.

The builder’s RERA record, explained

The Midas Residences Phase 1

SELENITE PROPERTIES PRIVATE LIMITED · P52100045688

MahaRERA · registration record · read 12 July 2026

Choose a report ↓

What does the RERA record show?

For The Midas Residences Phase 1 (P52100045688), 36 of 208 entries were marked unsold in the MahaRERA home list read 9 September 2026.

MahaRERA · per-home inventory · read 9 September 2026

For The Midas Residences Phase 1, ₹14,125 per sq ft of carpet area is the median rate across 133 sold or booked entries with prices in the MahaRERA home list read 9 September 2026. These are historical agreement values, not current asking prices.

MahaRERA · per-home inventory · read 9 September 2026

These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.

What would help you decide?

Buyer’s Report

Understand this project

Find homes to consider, with advice on light, layout, privacy and surroundings.

₹4,999

Unit Report

Check a particular home

See its advantages, drawbacks and how it compares with other homes in this project.

₹3,999

Project Comparison Report

Choose between projects

Compare two or three projects and get recommended homes in order, with reasons for each choice.

From ₹7,999

Choose projects →

Project status and completion date.

Prices reported to RERA

What prices have been reported?

₹14,125/ sq ft carpet area

Across 133 sold or booked entries with reported prices. The middle 80% of rates fall between ₹13,263 and ₹16,209.

MahaRERA · per-home inventory · read 9 September 2026

How is this calculated?

For each sold or booked entry, we divide the reported agreement value by its carpet area in square feet. The median is the middle rate when these rates are put in order. We show it only when at least five entries have prices. We exclude valuations of unsold homes and government reference rates. The figures may include different sizes and property types. They are historical agreement values, not current asking prices or the total cost including extra charges.

Sales Report

What did similar homes sell for?

Compare reported agreement values by building, size and floor. See which homes were marked unsold on the date shown.

₹2,999 · delivered on payment

Inside this registered phase

How do the buildings compare in the record?

208 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.

MahaRERA · per-home inventory · read 9 September 2026

Scroll sideways to see all columns.

Building names, sale status and carpet areas — not current availability
Filed buildingEntriesSoldBookedMarked unsoldOther / unstated statusRecorded carpet-area range
BUILDING A17047032046.17–72.46 sq m≈ 497–780 sq ft
BUILDING A23425072103.96 sq m≈ 1,119 sq ft
BUILDING A334200131103.96 sq m≈ 1,119 sq ft
BUILDING A470410131646.17–93.74 sq m≈ 497–1,009 sq ft

Different sizes are not necessarily different bedroom types. How we read and summarise the filing →

Unit Report

Is this the right
home for you?

Understand its light, privacy, layout and surroundings. See how it compares with similar homes and other options in this project.

₹3,999 · 1 working day

Didn’t help you decide? Full refund — no questions asked.

Find your home in the RERA list.

The same home number may appear in more than one building. Check both before choosing.

208 listed entries

MahaRERA · per-home inventory · read 9 September 2026

RERA home list, not current availability
Home / buildingFloor in the recordCarpet areaReported statusAgreement valueAssess
1001BUILDING A11072.46 sq m≈ 780 sq ftSold₹10,542,857
1002BUILDING A11072.46 sq m≈ 780 sq ftSold₹10,521,100
1003BUILDING A11070.42 sq m≈ 758 sq ftSold₹10,448,300
1004BUILDING A11070.42 sq m≈ 758 sq ftSold₹10,604,300
101BUILDING A1172.46 sq m≈ 780 sq ftMarked unsoldNot stated
102BUILDING A1172.46 sq m≈ 780 sq ftMarked unsoldNot stated
1101BUILDING A11172.46 sq m≈ 780 sq ftSold₹9,717,404
1102BUILDING A11172.46 sq m≈ 780 sq ftSold₹11,740,050
1103BUILDING A11170.42 sq m≈ 758 sq ftSold₹10,230,487
1104BUILDING A11170.42 sq m≈ 758 sq ftSold₹10,375,920
1201BUILDING A11272.46 sq m≈ 780 sq ftSold₹10,649,400
1202BUILDING A11272.46 sq m≈ 780 sq ftNot for saleNot stated

Read every entry in one table: Read the complete saved home list.

Choose the home you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.

More from the RERA documents

Construction progress and project documents.

Cost reported as incurred

₹312,867,050 of an estimated ₹665,681,144 was reported as incurred (47.0%). This percentage is about costs. It does not show how much construction is complete.

MahaRERA project filing · read 19 July 2026 · registration P52100045688

Work reported, by building

Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.

See all reported activities
BuildingActivityReported
BUILDING A1Excavation90.0%
BUILDING A1Basement (if any)0.0%
BUILDING A1Podiums (if any) 0.0%
BUILDING A1Plinth0.0%
BUILDING A1Stilt Floor 0.0%
BUILDING A1Slabs of Super Structure0.0%
BUILDING A1Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
BUILDING A1Sanitary Fittings within the flats / premises0.0%
BUILDING A1Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
BUILDING A1External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
BUILDING A1Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
BUILDING A2Excavation90.0%
BUILDING A2Basement (if any)0.0%
BUILDING A2Podiums (if any) 0.0%
BUILDING A2Plinth0.0%
BUILDING A2Stilt Floor 0.0%
BUILDING A2Slabs of Super Structure0.0%
BUILDING A2Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
BUILDING A2Sanitary Fittings within the flats / premises0.0%
BUILDING A2Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
BUILDING A2External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
BUILDING A2Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
BUILDING A3Excavation90.0%
BUILDING A3Basement (if any)0.0%
BUILDING A3Podiums (if any) 0.0%
BUILDING A3Plinth0.0%
BUILDING A3Stilt Floor 0.0%
BUILDING A3Slabs of Super Structure0.0%
BUILDING A3Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
BUILDING A3Sanitary Fittings within the flats / premises0.0%
BUILDING A3Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
BUILDING A3External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
BUILDING A3Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
BUILDING A4Excavation90.0%
BUILDING A4Basement (if any)0.0%
BUILDING A4Podiums (if any) 0.0%
BUILDING A4Plinth0.0%
BUILDING A4Stilt Floor 0.0%
BUILDING A4Slabs of Super Structure0.0%
BUILDING A4Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
BUILDING A4Sanitary Fittings within the flats / premises0.0%
BUILDING A4Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
BUILDING A4External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
BUILDING A4Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%

MahaRERA project filing · read 19 July 2026 · registration P52100045688

Reported deadline extensions

Revised targetReason given by the builder
30 June 2028Project Launch Delayed therefore require extension for the project
30 June 2029Our construction plans for the project were delayed due to some unforeseen circumstances, and as of now, no construction activities have been undertaken. However, we have now decided to resume the construction. As a result, it will take additional time to complete the project

MahaRERA project filing · read 19 July 2026 · registration P52100045688

Where the project funding comes from

RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.

FilingOwn fundsBorrowingPayments from buyersTotal
Estimated plan₹150,000,000₹250,000,000₹673,260,702₹1,073,260,702
Actual raised₹131,270,472₹0₹419,171,823₹550,442,295

MahaRERA project filing · read 19 July 2026 · registration P52100045688

Quarterly filing record

16 elapsed quarterly periods in the captured compliance schedule. No active quarterly default was recorded in this snapshot.

MahaRERA project filing · read 19 July 2026 · registration P52100045688

Documents named in the filing

  • Promoter PAN · 1 listed
  • Form 1 — Architect's certificate · 4 listed
  • Form 3 — CA certificate · 4 listed
  • Form 2 — Engineer's certificate · 4 listed
  • Form B — Promoter declaration · 2 listed
  • Title / search report · 3 listed
  • Sanctioned layout plan · 3 listed
  • Sanctioned building plan · 9 listed
  • Occupancy / completion certificate · 1 listed

A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.

MahaRERA project filing · read 19 July 2026 · registration P52100045688

Builder and past records

What else does the record show?

Projects registered under this company

SELENITE PROPERTIES PRIVATE LIMITED

6Pune registrations

These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.

MahaRERA Pune registration records · read 2 July 2026 – 10 September 2026

Explore other registrations

Past records of sales and unsold homes

  1. 27 September 2026

    36 marked unsold · 133 sold · 0 booked.

    Saved MahaRERA home list

  2. 18 September 2026

    36 marked unsold · 133 sold · 0 booked.

    Saved MahaRERA home list

  3. 9 September 2026

    36 marked unsold · 133 sold · 0 booked.

    Saved MahaRERA home list

  4. 19 July 2026

    50 marked unsold · 113 sold · 6 booked.

    Saved MahaRERA home list

These dates show when the records were saved, not when homes were sold. Sales may have changed since then, even if the saved counts are the same.

More projects to explore

Other projects in this locality.

These projects list the same locality. They may differ in exact location, home type and price.

Project Comparison Report

Which project should you buy in?
And which home?

Compare up to three projects. We read their plans and RERA documents, recommend homes in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.

Create my Comparison Report →

2 projects · ₹7,999
3 projects · ₹9,999

Within 1 working day

Didn’t help you decide? Full refund — no questions asked.

Compare project details for free →

Sources and dates.

MahaRERA · registration record · read 12 July 2026

MahaRERA · per-home inventory · read 9 September 2026

This is a past RERA home list, not current availability. It does not give the date each home was sold.

Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.

Open MahaRERA · search P52100045688 ↗
homeonpaper