homeonpaper.

Builder’s RERA records,
explained for buyers.

The builder’s RERA record, explained

PRESIDENCY TOWERS

Presidency Hospitality Limited · P52100050059

MahaRERA · registration record · read 12 July 2026

Choose a report ↓

What does the RERA record show?

For PRESIDENCY TOWERS (P52100050059), 95 of 95 entries were marked unsold in the MahaRERA home list dated 18 July 2026 (saved-file date).

MahaRERA · per-home inventory · saved-file date 18 July 2026

These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.

What would help you decide?

Buyer’s Report

Understand this project

Find homes to consider, with advice on light, layout, privacy and surroundings.

₹4,999

Unit Report

Check a particular home

See its advantages, drawbacks and how it compares with other homes in this project.

₹3,999

Project Comparison Report

Choose between projects

Compare two or three projects and get recommended homes in order, with reasons for each choice.

From ₹7,999

Choose projects →

Project status and completion date.

Inside this registered phase

How do the buildings compare in the record?

95 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.

MahaRERA · per-home inventory · saved-file date 18 July 2026

Scroll sideways to see all columns.

Building names, sale status and carpet areas — not current availability
Filed buildingEntriesSoldBookedMarked unsoldOther / unstated statusRecorded carpet-area range
A Building950095014.02–265.39 sq m≈ 151–2,857 sq ft

Different sizes are not necessarily different bedroom types. How we read and summarise the filing →

Unit Report

Is this the right
home for you?

Understand its light, privacy, layout and surroundings. See how it compares with similar homes and other options in this project.

₹3,999 · 1 working day

Didn’t help you decide? Full refund — no questions asked.

Find your home in the RERA list.

The same home number may appear in more than one building. Check both before choosing.

95 listed entries

MahaRERA · per-home inventory · saved-file date 18 July 2026

RERA home list, not current availability
Home / buildingFloor in the recordCarpet areaReported statusAgreement valueAssess
A-201A Building223.59 sq m≈ 254 sq ftMarked unsoldNot stated
A-202A Building215.56 sq m≈ 167 sq ftMarked unsoldNot stated
A-203A Building216.75 sq m≈ 180 sq ftMarked unsoldNot stated
A-204A Building232.73 sq m≈ 352 sq ftMarked unsoldNot stated
A-205A Building233.71 sq m≈ 363 sq ftMarked unsoldNot stated
A-206A Building226.2 sq m≈ 282 sq ftMarked unsoldNot stated
A-207A Building223.31 sq m≈ 251 sq ftMarked unsoldNot stated
A-208A Building216.75 sq m≈ 180 sq ftMarked unsoldNot stated
A-209A Building216.58 sq m≈ 178 sq ftMarked unsoldNot stated
A-210A Building216.58 sq m≈ 178 sq ftMarked unsoldNot stated
A-211A Building217.25 sq m≈ 186 sq ftMarked unsoldNot stated
A-212A Building217.25 sq m≈ 186 sq ftMarked unsoldNot stated

Read every entry in one table: Read the complete saved home list.

Choose the home you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.

More from the RERA documents

Construction progress and project documents.

Cost reported as incurred

₹96,000,000 of an estimated ₹101,136,434 was reported as incurred (94.9%). This percentage is about costs. It does not show how much construction is complete.

MahaRERA project filing · read 19 July 2026 · registration P52100050059

Work reported, by building

Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.

See all reported activities
BuildingActivityReported
A BuildingExcavation100.0%
A BuildingBasement (if any)100.0%
A BuildingPodiums (if any) 0.0%
A BuildingPlinth100.0%
A BuildingStilt Floor 100.0%
A BuildingSlabs of Super Structure100.0%
A BuildingInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100.0%
A BuildingSanitary Fittings within the flats / premises100.0%
A BuildingStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100.0%
A BuildingExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100.0%
A BuildingInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100.0%

MahaRERA project filing · read 19 July 2026 · registration P52100050059

Reported deadline extensions

Revised targetReason given by the builder
30 June 2026Dear Sir/Ma’am, We, Presidency Hospitality Limited, hereby declare the following with respect to the project “PRESIDENCY TOWERS” bearing registration number P52100050059 registered under MahaRERA In this regard, we respectfully state as under: 1. Application for Extension We hereby confirm that we Are applying for extension of the above-mentioned project under the provisions of the Real Estate (Regulation and Development) Act, 2016, and request that the extension be granted up to 30 June 2026. 2. Status of Sales We hereby clarify and confirm that no units in the said project have been sold to date, and therefore no rights of any allottee are affected by the present application for extension. 3. Occupancy Certificate Obtained We further state that the Occupancy Certificate (OC) for the project has already been obtained, and the project is substantially completed. 4. Clarification Regarding Sanctioned Plans and Units We wish to bring to your notice that there is a mismatch in the sanctioned number of units as presently reflected on the MahaRERA portal vis-à-vis the Final Occupancy Certificate approved plans, which requires correction on the MahaRERA portal. 5. Submission of Corrected Details and Project Closure Upon grant of the Extension Certificate, we undertake to immediately apply for correction of the sanctioned number of units and upload the correct sanctioned plans, Commencement Certificate (CC), Occupancy Certificate (OC), and all other relevant and updated project details on the MahaRERA portal. We further undertake that on or before 30 June 2026, we shall complete all requisite compliances, correct the project profile, and apply for closure of the project on the MahaRERA portal. 6. Commitment to Compliance We hereby affirm our commitment to full compliance with all provisions, rules, regulations, and directions issued by MahaRERA and assure that all corrected and updated project information shall be uploaded accurately and within the stipulated timelines. We request you to kindly take the above on record and consider our application for extension favorably.

MahaRERA project filing · read 19 July 2026 · registration P52100050059

Where the project funding comes from

RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.

FilingOwn fundsBorrowingPayments from buyersTotal
Estimated plan₹185,481,690₹0₹18,927,766₹204,409,456
Actual raised₹185,481,690₹0₹0₹185,481,690

MahaRERA project filing · read 19 July 2026 · registration P52100050059

Quarterly filing record

13 elapsed quarterly periods in the captured compliance schedule. No active quarterly default was recorded in this snapshot.

MahaRERA project filing · read 19 July 2026 · registration P52100050059

Documents named in the filing

  • Promoter PAN · 1 listed
  • Occupancy / completion certificate · 1 listed
  • Form 1 — Architect's certificate · 1 listed
  • Form 3 — CA certificate · 1 listed
  • Form 2 — Engineer's certificate · 1 listed
  • Title / search report · 1 listed
  • Form B — Promoter declaration · 1 listed
  • Sanctioned layout plan · 1 listed
  • Sanctioned building plan · 2 listed

A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.

MahaRERA project filing · read 19 July 2026 · registration P52100050059

Builder and past records

What else does the record show?

Projects registered under this company

Presidency Hospitality Limited

1Pune registrations

These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.

MahaRERA Pune registration records · read 12 July 2026

Explore other registrations

    Past records of sales and unsold homes

    1. 27 September 2026

      95 marked unsold · 0 sold · 0 booked.

      Saved MahaRERA home list

    2. 18 September 2026

      95 marked unsold · 0 sold · 0 booked.

      Saved MahaRERA home list

    3. 10 September 2026

      95 marked unsold · 0 sold · 0 booked.

      Saved MahaRERA home list

    4. 19 July 2026

      95 marked unsold · 0 sold · 0 booked.

      Saved MahaRERA home list

    These dates show when the records were saved, not when homes were sold. Sales may have changed since then, even if the saved counts are the same.

    More projects to explore

    Other projects in this locality.

    These projects list the same locality. They may differ in exact location, home type and price.

    Project Comparison Report

    Which project should you buy in?
    And which home?

    Compare up to three projects. We read their plans and RERA documents, recommend homes in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.

    Create my Comparison Report →

    2 projects · ₹7,999
    3 projects · ₹9,999

    Within 1 working day

    Didn’t help you decide? Full refund — no questions asked.

    Compare project details for free →

    Sources and dates.

    MahaRERA · registration record · read 12 July 2026

    MahaRERA · per-home inventory · saved-file date 18 July 2026

    This is a past RERA home list, not current availability. It does not give the date each home was sold.

    The home-list date is based on the saved file’s details.

    Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.

    Open MahaRERA · search P52100050059 ↗
    homeonpaper