The builder’s RERA record, explained

7 Plumeria Drive- Phase 3

B A Consulting · P52100050087

MahaRERA · registration record · read 12 July 2026

Choose a report ↓

What does the RERA record show?

For 7 Plumeria Drive- Phase 3 (P52100050087), 90 of 275 entries were marked unsold in the MahaRERA home list read 10 September 2026.

MahaRERA · per-home inventory · read 10 September 2026

For 7 Plumeria Drive- Phase 3, ₹9,859 per sq ft of carpet area is the median rate across 185 sold or booked entries with prices in the MahaRERA home list read 10 September 2026. These are historical agreement values, not current asking prices.

MahaRERA · per-home inventory · read 10 September 2026

These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.

What would help you decide?

Buyer’s Report

Understand this project

Find homes to consider, with advice on light, layout, privacy and surroundings.

₹4,999

Unit Report

Check a particular home

See its advantages, drawbacks and how it compares with other homes in this project.

₹3,999

Project Comparison Report

Choose between projects

Compare two or three projects and get recommended homes in order, with reasons for each choice.

From ₹7,999

Choose projects →

Project status and completion date.

Prices reported to RERA

What prices have been reported?

₹9,859/ sq ft carpet area

Across 185 sold or booked entries with reported prices. The middle 80% of rates fall between ₹3,909 and ₹11,671.

MahaRERA · per-home inventory · read 10 September 2026

How is this calculated?

For each sold or booked entry, we divide the reported agreement value by its carpet area in square feet. The median is the middle rate when these rates are put in order. We show it only when at least five entries have prices. We exclude valuations of unsold homes and government reference rates. The figures may include different sizes and property types. They are historical agreement values, not current asking prices or the total cost including extra charges.

Sales Report

What did similar homes sell for?

Compare reported agreement values by building, size and floor. See which homes were marked unsold on the date shown.

₹2,999 · delivered on payment

Inside this registered phase

How do the buildings compare in the record?

275 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.

MahaRERA · per-home inventory · read 10 September 2026

Scroll sideways to see all columns.

Building names, sale status and carpet areas — not current availability
Filed buildingEntriesSoldBookedMarked unsoldOther / unstated statusRecorded carpet-area range
H12286036089.93–112.23 sq m≈ 968–1,208 sq ft
I124790450119.48–176.95 sq m≈ 1,286–1,905 sq ft
L292009041.71–44.13 sq m≈ 449–475 sq ft

Different sizes are not necessarily different bedroom types. How we read and summarise the filing →

Unit Report

Is this the right
home for you?

Understand its light, privacy, layout and surroundings. See how it compares with similar homes and other options in this project.

₹3,999 · 1 working day

Didn’t help you decide? Full refund — no questions asked.

Find your home in the RERA list.

The same home number may appear in more than one building. Check both before choosing.

275 listed entries

MahaRERA · per-home inventory · read 10 September 2026

RERA home list, not current availability
Home / buildingFloor in the recordCarpet areaReported statusAgreement valueAssess
1001H10112.2297 sq m≈ 1,208 sq ftSold₹11,047,104
1002H10112.2297 sq m≈ 1,208 sq ftSold₹13,525,051
1003H10112.1897 sq m≈ 1,208 sq ftSold₹11,694,834
1004H10112.1897 sq m≈ 1,208 sq ftSold₹11,044,261
103H1112.1897 sq m≈ 1,208 sq ftMarked unsoldNot stated
104H1112.1897 sq m≈ 1,208 sq ftMarked unsoldNot stated
1101H11112.2297 sq m≈ 1,208 sq ftSold₹11,058,092
1102H11112.2297 sq m≈ 1,208 sq ftSold₹13,172,078
1103H11112.1897 sq m≈ 1,208 sq ftSold₹12,022,374
1104H11112.1897 sq m≈ 1,208 sq ftMarked unsoldNot stated
1201H12112.2297 sq m≈ 1,208 sq ftSold₹14,244,910
1202H12112.2297 sq m≈ 1,208 sq ftSold₹12,831,703

Read every entry in one table: Read the complete saved home list.

Choose the home you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.

More from the RERA documents

Construction progress and project documents.

Cost reported as incurred

₹1,341,944,739 of an estimated ₹1,707,564,200 was reported as incurred (78.6%). This percentage is about costs. It does not show how much construction is complete.

MahaRERA project filing · read 19 July 2026 · registration P52100050087

Work reported, by building

Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.

See all reported activities
BuildingActivityReported
HExcavation100.0%
HBasement (if any)100.0%
HPodiums (if any) 0.0%
HPlinth100.0%
HStilt Floor 100.0%
HSlabs of Super Structure100.0%
HInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises84.92%
HSanitary Fittings within the flats / premises50.0%
HStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100.0%
HExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100.0%
HInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.71.98%
IExcavation100.0%
IBasement (if any)100.0%
IPodiums (if any) 0.0%
IPlinth100.0%
IStilt Floor 100.0%
ISlabs of Super Structure100.0%
IInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises83.31%
ISanitary Fittings within the flats / premises50.0%
IStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks94.55%
IExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100.0%
IInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.69.04%
LExcavation100.0%
LBasement (if any)0.0%
LPodiums (if any) 0.0%
LPlinth100.0%
LStilt Floor 100.0%
LSlabs of Super Structure100.0%
LInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises79.14%
LSanitary Fittings within the flats / premises50.0%
LStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks86.5%
LExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.84.0%
LInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.35.25%

MahaRERA project filing · read 19 July 2026 · registration P52100050087

Reported deadline extensions

Revised targetReason given by the builder
30 September 2026Respected Sir/Madam, We, the Promoter of the below-mentioned project, hereby state and confirm that the project has been delayed by approximately 3–4 months due to circumstances beyond our control. The primary reasons for the delay are as follows: Adverse Weather Conditions Material and Supply Chain Issues Regulatory Delays Financial and Sales-Related Impact In view of the above unavoidable circumstances, we are hereby applying for an extension of the project completion date as per MahaRERA Order No. 40. We kindly request an extension up to 30-09-2026, by which time we are confident that we will be able to obtain the required Completion Certificate/Occupancy Certificate for the project. We request your kind consideration of the above and approval of the extension. Thanking you.

MahaRERA project filing · read 19 July 2026 · registration P52100050087

Where the project funding comes from

RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.

FilingOwn fundsBorrowingPayments from buyersTotal
Estimated plan₹145,000,000₹450,000,000₹1,315,766,394₹1,910,766,394
Actual raised₹143,031,966₹179,265,418₹1,213,033,470₹1,535,330,854

MahaRERA project filing · read 19 July 2026 · registration P52100050087

Quarterly filing record

13 elapsed quarterly periods in the captured compliance schedule. No active quarterly default was recorded in this snapshot.

MahaRERA project filing · read 19 July 2026 · registration P52100050087

Documents named in the filing

  • Promoter PAN · 1 listed
  • Commencement certificate · 1 listed
  • Occupancy / completion certificate · 5 listed
  • Form 1 — Architect's certificate · 4 listed
  • Form 3 — CA certificate · 4 listed
  • Form 2 — Engineer's certificate · 4 listed
  • Form B — Promoter declaration · 1 listed
  • Title / search report · 1 listed
  • Sanctioned building plan · 35 listed
  • Sanctioned layout plan · 1 listed

A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.

MahaRERA project filing · read 19 July 2026 · registration P52100050087

Builder and past records

What else does the record show?

Projects registered under this company

B A Consulting

3Pune registrations

These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.

MahaRERA Pune registration records · read 12 July 2026

Explore other registrations

Past records of sales and unsold homes

  1. 27 September 2026

    90 marked unsold · 185 sold · 0 booked.

    Saved MahaRERA home list

  2. 18 September 2026

    90 marked unsold · 185 sold · 0 booked.

    Saved MahaRERA home list

  3. 10 September 2026

    90 marked unsold · 185 sold · 0 booked.

    Saved MahaRERA home list

  4. 19 July 2026

    98 marked unsold · 177 sold · 0 booked.

    Saved MahaRERA home list

These dates show when the records were saved, not when homes were sold. Sales may have changed since then, even if the saved counts are the same.

More projects to explore

Other projects in this locality.

These projects list the same locality. They may differ in exact location, home type and price.

Project Comparison Report

Which project should you buy in?
And which home?

Compare up to three projects. We read their plans and RERA documents, recommend homes in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.

Create my Comparison Report →

2 projects · ₹7,999
3 projects · ₹9,999

Within 1 working day

Didn’t help you decide? Full refund — no questions asked.

Compare project details for free →

Sources and dates.

MahaRERA · registration record · read 12 July 2026

MahaRERA · per-home inventory · read 10 September 2026

This is a past RERA home list, not current availability. It does not give the date each home was sold.

Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.

Open MahaRERA · search P52100050087 ↗