Buyer’s Report
Understand this project
Find homes to consider, with advice on light, layout, privacy and surroundings.
₹4,999
Builder’s RERA records,
explained for buyers.
The builder’s RERA record, explained
SHREEGRUHA NIRMAN INFRA PROJECTS LLP · P52100054365
For SHREE SWARAJYA PARK (P52100054365), 35 of 110 entries were marked unsold in the MahaRERA home list dated 18 July 2026 (saved-file date).
MahaRERA · per-home inventory · saved-file date 18 July 2026
For SHREE SWARAJYA PARK, ₹3,722 per sq ft of carpet area is the median rate across 21 sold or booked entries with prices in the MahaRERA home list dated 18 July 2026 (saved-file date). These are historical agreement values, not current asking prices.
MahaRERA · per-home inventory · saved-file date 18 July 2026
These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.
Builder’s completion target
The builder reported this target date. It is not a confirmed handover date.
Status shown on RERA
This is the status shown on RERA. It does not confirm an occupancy certificate or today’s construction progress.
Prices reported to RERA
₹3,722/ sq ft carpet area
Across 21 sold or booked entries with reported prices. The middle 80% of rates fall between ₹3,020 and ₹5,301.
MahaRERA · per-home inventory · saved-file date 18 July 2026
For each sold or booked entry, we divide the reported agreement value by its carpet area in square feet. The median is the middle rate when these rates are put in order. We show it only when at least five entries have prices. We exclude valuations of unsold homes and government reference rates. The figures may include different sizes and property types. They are historical agreement values, not current asking prices or the total cost including extra charges.
Sales Report
Compare reported agreement values by building, size and floor. See which homes were marked unsold on the date shown.
Inside this registered phase
110 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.
MahaRERA · per-home inventory · saved-file date 18 July 2026
Scroll sideways to see all columns.
| Filed building | Entries | Sold | Booked | Marked unsold | Other / unstated status | Recorded carpet-area range |
|---|---|---|---|---|---|---|
| Shree Swarajya Park - Building B | 55 | 4 | 5 | 20 | 26 | 25.23–101.04 sq m≈ 272–1,088 sq ft |
| Shree Swarajya Park-Building A | 55 | 2 | 10 | 15 | 28 | 25.23–99.85 sq m≈ 272–1,075 sq ft |
Different sizes are not necessarily different bedroom types. How we read and summarise the filing →
Unit Report
Understand its light, privacy, layout and surroundings. See how it compares with similar homes and other options in this project.
Didn’t help you decide? Full refund — no questions asked.
The same home number may appear in more than one building. Check both before choosing.
MahaRERA · per-home inventory · saved-file date 18 July 2026
| Home / building | Floor in the record | Carpet area | Reported status | Agreement value | Assess |
|---|---|---|---|---|---|
| Flat No 502Shree Swarajya Park - Building B | 5 | 101.04 sq m≈ 1,088 sq ft | Booked | ₹3,000,000 | |
| Flat no 103Shree Swarajya Park - Building B | 1 | 97.29 sq m≈ 1,047 sq ft | Owner investor | Not stated | |
| Flat no 401Shree Swarajya Park - Building B | 4 | 78.68 sq m≈ 847 sq ft | Marked unsold | Not stated | |
| Flat no 402Shree Swarajya Park - Building B | 4 | 75.16 sq m≈ 809 sq ft | Owner investor | Not stated | |
| Flat no 403Shree Swarajya Park - Building B | 4 | 100.87 sq m≈ 1,086 sq ft | Owner investor | Not stated | |
| Flat no 405Shree Swarajya Park - Building B | 4 | 74.86 sq m≈ 806 sq ft | Owner investor | Not stated | |
| Flat no 406Shree Swarajya Park - Building B | 4 | 77.59 sq m≈ 835 sq ft | Marked unsold | Not stated | |
| Flat no 101Shree Swarajya Park - Building B | 1 | 78.53 sq m≈ 845 sq ft | Owner investor | Not stated | |
| Flat no 102Shree Swarajya Park - Building B | 1 | 75.11 sq m≈ 808 sq ft | Marked unsold | Not stated | |
| Flat no 201Shree Swarajya Park - Building B | 2 | 78.68 sq m≈ 847 sq ft | Marked unsold | Not stated | |
| Flat no 202Shree Swarajya Park - Building B | 2 | 75.16 sq m≈ 809 sq ft | Owner investor | Not stated | |
| Flat no 203Shree Swarajya Park - Building B | 2 | 100.87 sq m≈ 1,086 sq ft | Marked unsold | Not stated |
Read every entry in one table: Read the complete saved home list.
Choose the home you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.
More from the RERA documents
₹67,500,000 of an estimated ₹126,000,000 was reported as incurred (53.6%). This percentage is about costs. It does not show how much construction is complete.
MahaRERA project filing · read 19 July 2026 · registration P52100054365
Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.
| Building | Activity | Reported |
|---|---|---|
| Shree Swarajya Park-Building A | Excavation | 100.0% |
| Shree Swarajya Park-Building A | Basement (if any) | 100.0% |
| Shree Swarajya Park-Building A | Podiums (if any) | 100.0% |
| Shree Swarajya Park-Building A | Plinth | 100.0% |
| Shree Swarajya Park-Building A | Stilt Floor | 100.0% |
| Shree Swarajya Park-Building A | Slabs of Super Structure | 100.0% |
| Shree Swarajya Park-Building A | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 75.0% |
| Shree Swarajya Park-Building A | Sanitary Fittings within the flats / premises | 50.0% |
| Shree Swarajya Park-Building A | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 80.0% |
| Shree Swarajya Park-Building A | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 50.0% |
| Shree Swarajya Park-Building A | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 50.0% |
| Shree Swarajya Park - Building B | Excavation | 100.0% |
| Shree Swarajya Park - Building B | Basement (if any) | 100.0% |
| Shree Swarajya Park - Building B | Podiums (if any) | 100.0% |
| Shree Swarajya Park - Building B | Plinth | 100.0% |
| Shree Swarajya Park - Building B | Stilt Floor | 100.0% |
| Shree Swarajya Park - Building B | Slabs of Super Structure | 100.0% |
| Shree Swarajya Park - Building B | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 75.0% |
| Shree Swarajya Park - Building B | Sanitary Fittings within the flats / premises | 50.0% |
| Shree Swarajya Park - Building B | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 80.0% |
| Shree Swarajya Park - Building B | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 50.0% |
| Shree Swarajya Park - Building B | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 50.0% |
MahaRERA project filing · read 19 July 2026 · registration P52100054365
RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.
| Filing | Own funds | Borrowing | Payments from buyers | Total |
|---|---|---|---|---|
| Estimated plan | ₹7,700,851 | ₹0 | ₹126,000,000 | ₹133,700,851 |
| Actual raised | ₹30,584,813 | ₹0 | ₹44,478,893 | ₹75,063,706 |
MahaRERA project filing · read 19 July 2026 · registration P52100054365
8 elapsed quarterly periods in the captured compliance schedule. No active quarterly default was recorded in this snapshot.
MahaRERA project filing · read 19 July 2026 · registration P52100054365
A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.
MahaRERA project filing · read 19 July 2026 · registration P52100054365
Builder and past records
Projects registered under this company
1Pune registrations
These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.
MahaRERA Pune registration records · read 12 July 2026
Past records of sales and unsold homes
28 September 2026
35 marked unsold · 6 sold · 15 booked.
Saved MahaRERA home list
19 September 2026
35 marked unsold · 6 sold · 15 booked.
Saved MahaRERA home list
11 September 2026
35 marked unsold · 6 sold · 15 booked.
Saved MahaRERA home list
19 July 2026
35 marked unsold · 6 sold · 15 booked.
Saved MahaRERA home list
These dates show when the records were saved, not when homes were sold. Sales may have changed since then, even if the saved counts are the same.
Project Comparison Report
Compare up to three projects. We read their plans and RERA documents, recommend homes in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.
2 projects · ₹7,999
3 projects · ₹9,999
Within 1 working day
Didn’t help you decide? Full refund — no questions asked.
Compare project details for free →MahaRERA · registration record · read 12 July 2026
MahaRERA · per-home inventory · saved-file date 18 July 2026
This is a past RERA home list, not current availability. It does not give the date each home was sold.
The home-list date is based on the saved file’s details.
Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.
Open MahaRERA · search P52100054365 ↗