homeonpaper.

Builder’s RERA records,
explained for buyers.

The builder’s RERA record, explained

SHREENATH MARKET CITY

OZONE INFRASTRUCTURE · P52100054982

MahaRERA · registration record · read 12 July 2026

Choose a report ↓

What does the RERA record show?

For SHREENATH MARKET CITY (P52100054982), 240 of 275 entries were marked unsold in the MahaRERA home list read 11 September 2026.

MahaRERA · per-home inventory · read 11 September 2026

For SHREENATH MARKET CITY, ₹4,598 per sq ft of carpet area is the median rate across 35 sold or booked entries with prices in the MahaRERA home list read 11 September 2026. These are historical agreement values, not current asking prices.

MahaRERA · per-home inventory · read 11 September 2026

These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.

What would help you decide?

Buyer’s Report

Understand this project

Find homes to consider, with advice on light, layout, privacy and surroundings.

₹4,999

Unit Report

Check a particular home

See its advantages, drawbacks and how it compares with other homes in this project.

₹3,999

Project Comparison Report

Choose between projects

Compare two or three projects and get recommended homes in order, with reasons for each choice.

From ₹7,999

Choose projects →

Project status and completion date.

Prices reported to RERA

What prices have been reported?

₹4,598/ sq ft carpet area

Across 35 sold or booked entries with reported prices. The middle 80% of rates fall between ₹4,316 and ₹11,733.

MahaRERA · per-home inventory · read 11 September 2026

How is this calculated?

For each sold or booked entry, we divide the reported agreement value by its carpet area in square feet. The median is the middle rate when these rates are put in order. We show it only when at least five entries have prices. We exclude valuations of unsold homes and government reference rates. The figures may include different sizes and property types. They are historical agreement values, not current asking prices or the total cost including extra charges.

Sales Report

What did similar homes sell for?

Compare reported agreement values by building, size and floor. See which homes were marked unsold on the date shown.

₹2,999 · delivered on payment

Inside this registered phase

How do the buildings compare in the record?

275 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.

MahaRERA · per-home inventory · read 11 September 2026

Scroll sideways to see all columns.

Building names, sale status and carpet areas — not current availability
Filed buildingEntriesSoldBookedMarked unsoldOther / unstated statusRecorded carpet-area range
A WING5518037016.53–42.35 sq m≈ 178–456 sq ft
B WING310031016.53–40.93 sq m≈ 178–441 sq ft
C WING389029016.07–48.85 sq m≈ 173–526 sq ft
D WING321031018.81–40.93 sq m≈ 202–441 sq ft
E WING506044018.81–41.16 sq m≈ 202–443 sq ft
F WING230023011.80–54.14 sq m≈ 127–583 sq ft
G WING231022011.80–53.92 sq m≈ 127–580 sq ft
H WING230023011.80–53.92 sq m≈ 127–580 sq ft

Different sizes are not necessarily different bedroom types. How we read and summarise the filing →

Unit Report

Is this the right
home for you?

Understand its light, privacy, layout and surroundings. See how it compares with similar homes and other options in this project.

₹3,999 · 1 working day

Didn’t help you decide? Full refund — no questions asked.

Find your home in the RERA list.

The same home number may appear in more than one building. Check both before choosing.

275 listed entries

MahaRERA · per-home inventory · read 11 September 2026

RERA home list, not current availability
Home / buildingFloor in the recordCarpet areaReported statusAgreement valueAssess
10A WING20518.81 sq m≈ 202 sq ftSold₹2,750,000
101A WING136.59 sq m≈ 394 sq ftSold₹1,775,000
102A WING136.59 sq m≈ 394 sq ftSold₹1,860,000
103A WING136.58 sq m≈ 394 sq ftMarked unsoldNot stated
103A WING116.53 sq m≈ 178 sq ftMarked unsoldNot stated
104A WING116.53 sq m≈ 178 sq ftMarked unsoldNot stated
105A WING116.53 sq m≈ 178 sq ftMarked unsoldNot stated
106A WING116.53 sq m≈ 178 sq ftMarked unsoldNot stated
107A WING116.53 sq m≈ 178 sq ftMarked unsoldNot stated
108A WING137.05 sq m≈ 399 sq ftSold₹1,940,000
108A WING116.53 sq m≈ 178 sq ftMarked unsoldNot stated
109A WING116.53 sq m≈ 178 sq ftMarked unsoldNot stated

Read every entry in one table: Read the complete saved home list.

Choose the home you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.

More from the RERA documents

Construction progress and project documents.

Cost reported as incurred

₹52,057,265 of an estimated ₹207,152,401 was reported as incurred (25.1%). This percentage is about costs. It does not show how much construction is complete.

MahaRERA project filing · read 19 July 2026 · registration P52100054982

Work reported, by building

Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.

See all reported activities
BuildingActivityReported
A WINGExcavation100.0%
A WINGBasement (if any)0.0%
A WINGPodiums (if any) 0.0%
A WINGPlinth100.0%
A WINGStilt Floor 0.0%
A WINGSlabs of Super Structure100.0%
A WINGInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100.0%
A WINGSanitary Fittings within the flats / premises0.0%
A WINGStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100.0%
A WINGExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100.0%
A WINGInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80.0%
B WINGExcavation100.0%
B WINGBasement (if any)0.0%
B WINGPodiums (if any) 0.0%
B WINGPlinth50.0%
B WINGStilt Floor 0.0%
B WINGSlabs of Super Structure0.0%
B WINGInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
B WINGSanitary Fittings within the flats / premises0.0%
B WINGStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
B WINGExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
B WINGInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
C WINGExcavation100.0%
C WINGBasement (if any)0.0%
C WINGPodiums (if any) 0.0%
C WINGPlinth100.0%
C WINGStilt Floor 0.0%
C WINGSlabs of Super Structure50.0%
C WINGInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
C WINGSanitary Fittings within the flats / premises0.0%
C WINGStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
C WINGExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
C WINGInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
D WINGExcavation100.0%
D WINGBasement (if any)0.0%
D WINGPodiums (if any) 0.0%
D WINGPlinth100.0%
D WINGStilt Floor 0.0%
D WINGSlabs of Super Structure50.0%
D WINGInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
D WINGSanitary Fittings within the flats / premises0.0%
D WINGStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
D WINGExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
D WINGInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
E WINGExcavation100.0%
E WINGBasement (if any)0.0%
E WINGPodiums (if any) 0.0%
E WINGPlinth100.0%
E WINGStilt Floor 0.0%
E WINGSlabs of Super Structure55.0%
E WINGInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
E WINGSanitary Fittings within the flats / premises0.0%
E WINGStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
E WINGExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
E WINGInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
F WINGExcavation0.0%
F WINGBasement (if any)0.0%
F WINGPodiums (if any) 0.0%
F WINGPlinth0.0%
F WINGStilt Floor 0.0%
F WINGSlabs of Super Structure0.0%
F WINGInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
F WINGSanitary Fittings within the flats / premises0.0%
F WINGStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
F WINGExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
F WINGInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
G WINGExcavation0.0%
G WINGBasement (if any)0.0%
G WINGPodiums (if any) 0.0%
G WINGPlinth0.0%
G WINGStilt Floor 0.0%
G WINGSlabs of Super Structure0.0%
G WINGInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
G WINGSanitary Fittings within the flats / premises0.0%
G WINGStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
G WINGExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
G WINGInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
H WINGExcavation0.0%
H WINGBasement (if any)0.0%
H WINGPodiums (if any) 0.0%
H WINGPlinth0.0%
H WINGStilt Floor 0.0%
H WINGSlabs of Super Structure0.0%
H WINGInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
H WINGSanitary Fittings within the flats / premises0.0%
H WINGStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
H WINGExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
H WINGInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%

MahaRERA project filing · read 19 July 2026 · registration P52100054982

Where the project funding comes from

RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.

FilingOwn fundsBorrowingPayments from buyersTotal
Estimated plan₹58,331,329₹0₹168,638,822₹226,970,151
Actual raised₹23,164,786₹0₹41,608,442₹64,773,228

MahaRERA project filing · read 19 July 2026 · registration P52100054982

Quarterly filing record

8 elapsed quarterly periods in the captured compliance schedule. No active quarterly default was recorded in this snapshot.

MahaRERA project filing · read 19 July 2026 · registration P52100054982

Documents named in the filing

  • Promoter PAN · 1 listed
  • Occupancy / completion certificate · 3 listed
  • Commencement certificate · 1 listed
  • Form 1 — Architect's certificate · 4 listed
  • Form 3 — CA certificate · 4 listed
  • Form 2 — Engineer's certificate · 4 listed
  • Form B — Promoter declaration · 1 listed
  • Title / search report · 1 listed
  • Sanctioned layout plan · 1 listed
  • Sanctioned building plan · 22 listed

A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.

MahaRERA project filing · read 19 July 2026 · registration P52100054982

Builder and past records

What else does the record show?

Projects registered under this company

OZONE INFRASTRUCTURE

1Pune registrations

These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.

MahaRERA Pune registration records · read 12 July 2026

Explore other registrations

    Past records of sales and unsold homes

    1. 27 September 2026

      240 marked unsold · 35 sold · 0 booked.

      Saved MahaRERA home list

    2. 19 September 2026

      240 marked unsold · 35 sold · 0 booked.

      Saved MahaRERA home list

    3. 11 September 2026

      240 marked unsold · 35 sold · 0 booked.

      Saved MahaRERA home list

    4. 19 July 2026

      244 marked unsold · 31 sold · 0 booked.

      Saved MahaRERA home list

    These dates show when the records were saved, not when homes were sold. Sales may have changed since then, even if the saved counts are the same.

    Project Comparison Report

    Which project should you buy in?
    And which home?

    Compare up to three projects. We read their plans and RERA documents, recommend homes in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.

    Create my Comparison Report →

    2 projects · ₹7,999
    3 projects · ₹9,999

    Within 1 working day

    Didn’t help you decide? Full refund — no questions asked.

    Compare project details for free →

    Sources and dates.

    MahaRERA · registration record · read 12 July 2026

    MahaRERA · per-home inventory · read 11 September 2026

    This is a past RERA home list, not current availability. It does not give the date each home was sold.

    Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.

    Open MahaRERA · search P52100054982 ↗
    homeonpaper