The builder’s RERA record, explained

Godrej Evergreen Square

Godrej Projects Development Limited · P52100078240

MahaRERA · registration record · read 12 July 2026

Choose a report ↓

What does the RERA record show?

For Godrej Evergreen Square (P52100078240), 503 of 2476 entries were marked unsold in the MahaRERA home list dated 18 July 2026 (saved-file date).

MahaRERA · per-home inventory · saved-file date 18 July 2026

For Godrej Evergreen Square, ₹11,471 per sq ft of carpet area is the median rate across 1973 sold or booked entries with prices in the MahaRERA home list dated 18 July 2026 (saved-file date). These are historical agreement values, not current asking prices.

MahaRERA · per-home inventory · saved-file date 18 July 2026

These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.

What would help you decide?

Buyer’s Report

Understand this project

Find homes to consider, with advice on light, layout, privacy and surroundings.

₹4,999

Unit Report

Check a particular home

See its advantages, drawbacks and how it compares with other homes in this project.

₹3,999

Project Comparison Report

Choose between projects

Compare two or three projects and get recommended homes in order, with reasons for each choice.

From ₹7,999

Choose projects →

Project status and completion date.

Prices reported to RERA

What prices have been reported?

₹11,471/ sq ft carpet area

Across 1973 sold or booked entries with reported prices. The middle 80% of rates fall between ₹10,698 and ₹13,131.

MahaRERA · per-home inventory · saved-file date 18 July 2026

How is this calculated?

For each sold or booked entry, we divide the reported agreement value by its carpet area in square feet. The median is the middle rate when these rates are put in order. We show it only when at least five entries have prices. We exclude valuations of unsold homes and government reference rates. The figures may include different sizes and property types. They are historical agreement values, not current asking prices or the total cost including extra charges.

Sales Report

What did similar homes sell for?

Compare reported agreement values by building, size and floor. See which homes were marked unsold on the date shown.

₹2,999 · delivered on payment

Inside this registered phase

How do the buildings compare in the record?

2476 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.

MahaRERA · per-home inventory · saved-file date 18 July 2026

Scroll sideways to see all columns.

Building names, sale status and carpet areas — not current availability
Filed buildingEntriesSoldBookedMarked unsoldOther / unstated statusRecorded carpet-area range
Amenity Building2210210017.45–250.56 sq m≈ 188–2,697 sq ft
Retail Shop96482622011.85–283.25 sq m≈ 128–3,049 sq ft
Tower 12506874108059.89–80.11 sq m≈ 645–862 sq ft
Tower 2378359712039.00–58.20 sq m≈ 420–626 sq ft
Tower 33783491217039.00–58.20 sq m≈ 420–626 sq ft
Tower 42501691863067.86–87.06 sq m≈ 730–937 sq ft
Tower 52642123121058.00–75.97 sq m≈ 624–818 sq ft
Tower 62602181032058.00–75.97 sq m≈ 624–818 sq ft
Tower 72522239191067.86–87.58 sq m≈ 730–943 sq ft
Tower 8326291827057.32–59.83 sq m≈ 617–644 sq ft

Different sizes are not necessarily different bedroom types. How we read and summarise the filing →

Unit Report

Is this the right
home for you?

Understand its light, privacy, layout and surroundings. See how it compares with similar homes and other options in this project.

₹3,999 · 1 working day

Didn’t help you decide? Full refund — no questions asked.

Find your home in the RERA list.

The same home number may appear in more than one building. Check both before choosing.

2476 listed entries

MahaRERA · per-home inventory · saved-file date 18 July 2026

RERA home list, not current availability
Home / buildingFloor in the recordCarpet areaReported statusAgreement valueAssess
GESRA001Amenity Building20578.3 sq m≈ 843 sq ftSold₹38,552,000
GESRA002Amenity Building20537.0 sq m≈ 398 sq ftSold₹18,818,890
GESRA003Amenity Building20539.67 sq m≈ 427 sq ftSold₹20,176,669
GESRA004Amenity Building20557.47 sq m≈ 619 sq ftSold₹28,226,400
GESRA005Amenity Building20558.2 sq m≈ 626 sq ftSold₹28,077,920
GESRA006Amenity Building20558.2 sq m≈ 626 sq ftSold₹29,600,216
GESRA007Amenity Building20564.38 sq m≈ 693 sq ftSold₹31,185,000
GESRA008Amenity Building20517.45 sq m≈ 188 sq ftSold₹9,588,000
GESRA009Amenity Building20521.74 sq m≈ 234 sq ftSold₹10,705,500
GESRA101Amenity Building1138.61 sq m≈ 1,492 sq ftMarked unsoldNot stated
GESRA102Amenity Building156.93 sq m≈ 613 sq ftMarked unsoldNot stated
GESRA103Amenity Building156.93 sq m≈ 613 sq ftMarked unsoldNot stated

Read every entry in one table: Read the complete saved home list.

Choose the home you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.

More from the RERA documents

Construction progress and project documents.

Cost reported as incurred

₹1,005,079,885 of an estimated ₹11,767,599,999 was reported as incurred (8.5%). This percentage is about costs. It does not show how much construction is complete.

MahaRERA project filing · read 19 July 2026 · registration P52100078240

Work reported, by building

Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.

See all reported activities
BuildingActivityReported
Retail ShopExcavation100.0%
Retail ShopBasement (if any)0.0%
Retail ShopPodiums (if any) 0.0%
Retail ShopPlinth75.0%
Retail ShopStilt Floor 0.0%
Retail ShopSlabs of Super Structure20.0%
Retail ShopInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
Retail ShopSanitary Fittings within the flats / premises0.0%
Retail ShopStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
Retail ShopExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Retail ShopInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
Tower 2Excavation100.0%
Tower 2Basement (if any)0.0%
Tower 2Podiums (if any) 0.0%
Tower 2Plinth100.0%
Tower 2Stilt Floor 0.0%
Tower 2Slabs of Super Structure1.0%
Tower 2Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
Tower 2Sanitary Fittings within the flats / premises0.0%
Tower 2Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
Tower 2External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Tower 2Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
Tower 3Excavation100.0%
Tower 3Basement (if any)0.0%
Tower 3Podiums (if any) 0.0%
Tower 3Plinth100.0%
Tower 3Stilt Floor 0.0%
Tower 3Slabs of Super Structure3.0%
Tower 3Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
Tower 3Sanitary Fittings within the flats / premises0.0%
Tower 3Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
Tower 3External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Tower 3Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
Tower 4Excavation100.0%
Tower 4Basement (if any)0.0%
Tower 4Podiums (if any) 0.0%
Tower 4Plinth100.0%
Tower 4Stilt Floor 0.0%
Tower 4Slabs of Super Structure3.0%
Tower 4Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
Tower 4Sanitary Fittings within the flats / premises0.0%
Tower 4Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
Tower 4External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Tower 4Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
Tower 5Excavation100.0%
Tower 5Basement (if any)0.0%
Tower 5Podiums (if any) 0.0%
Tower 5Plinth100.0%
Tower 5Stilt Floor 0.0%
Tower 5Slabs of Super Structure1.0%
Tower 5Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
Tower 5Sanitary Fittings within the flats / premises0.0%
Tower 5Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
Tower 5External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Tower 5Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
Tower 6Excavation100.0%
Tower 6Basement (if any)0.0%
Tower 6Podiums (if any) 0.0%
Tower 6Plinth100.0%
Tower 6Stilt Floor 0.0%
Tower 6Slabs of Super Structure1.0%
Tower 6Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
Tower 6Sanitary Fittings within the flats / premises0.0%
Tower 6Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
Tower 6External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Tower 6Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
Tower 7Excavation100.0%
Tower 7Basement (if any)0.0%
Tower 7Podiums (if any) 0.0%
Tower 7Plinth100.0%
Tower 7Stilt Floor 0.0%
Tower 7Slabs of Super Structure1.0%
Tower 7Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
Tower 7Sanitary Fittings within the flats / premises0.0%
Tower 7Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
Tower 7External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Tower 7Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
Tower 8Excavation100.0%
Tower 8Basement (if any)0.0%
Tower 8Podiums (if any) 0.0%
Tower 8Plinth100.0%
Tower 8Stilt Floor 0.0%
Tower 8Slabs of Super Structure1.0%
Tower 8Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
Tower 8Sanitary Fittings within the flats / premises0.0%
Tower 8Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
Tower 8External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Tower 8Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
Amenity BuildingExcavation0.0%
Amenity BuildingBasement (if any)0.0%
Amenity BuildingPodiums (if any) 0.0%
Amenity BuildingPlinth0.0%
Amenity BuildingStilt Floor 0.0%
Amenity BuildingSlabs of Super Structure0.0%
Amenity BuildingInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
Amenity BuildingSanitary Fittings within the flats / premises0.0%
Amenity BuildingStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
Amenity BuildingExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Amenity BuildingInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
Tower 1Excavation100.0%
Tower 1Podiums (if any) 0.0%
Tower 1Plinth50.0%
Tower 1Stilt Floor 0.0%
Tower 1Slabs of Super Structure0.0%
Tower 1Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
Tower 1Sanitary Fittings within the flats / premises0.0%
Tower 1Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
Tower 1External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Tower 1Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%

MahaRERA project filing · read 19 July 2026 · registration P52100078240

Where the project funding comes from

RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.

FilingOwn fundsBorrowingPayments from buyersTotal
Estimated plan₹6,564,848,522₹0₹6,431,064,360₹15,410,857,110
Actual raised₹0₹0₹3,168,981,896₹5,103,413,587

MahaRERA project filing · read 19 July 2026 · registration P52100078240

Quarterly filing record

6 elapsed quarterly periods in the captured compliance schedule. No active quarterly default was recorded in this snapshot.

MahaRERA project filing · read 19 July 2026 · registration P52100078240

Documents named in the filing

  • Sanctioned building plan · 53 listed
  • Sanctioned layout plan · 4 listed
  • Form B — Promoter declaration · 1 listed
  • Title / search report · 1 listed
  • Occupancy / completion certificate · 2 listed
  • Commencement certificate · 4 listed
  • Promoter PAN · 1 listed
  • Form 2 — Engineer's certificate · 4 listed
  • Form 3 — CA certificate · 4 listed
  • Form 1 — Architect's certificate · 3 listed

A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.

MahaRERA project filing · read 19 July 2026 · registration P52100078240

Builder and past records

What else does the record show?

Projects registered under this company

Godrej Projects Development Limited

1Pune registrations

These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.

MahaRERA Pune registration records · read 12 July 2026

Explore other registrations

    Past records of sales and unsold homes

    1. 28 September 2026

      503 marked unsold · 1746 sold · 227 booked.

      Saved MahaRERA home list

    2. 20 September 2026

      503 marked unsold · 1746 sold · 227 booked.

      Saved MahaRERA home list

    3. 11 September 2026

      503 marked unsold · 1746 sold · 227 booked.

      Saved MahaRERA home list

    4. 19 July 2026

      503 marked unsold · 1746 sold · 227 booked.

      Saved MahaRERA home list

    These dates show when the records were saved, not when homes were sold. Sales may have changed since then, even if the saved counts are the same.

    Project Comparison Report

    Which project should you buy in?
    And which home?

    Compare up to three projects. We read their plans and RERA documents, recommend homes in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.

    Create my Comparison Report →

    2 projects · ₹7,999
    3 projects · ₹9,999

    Within 1 working day

    Didn’t help you decide? Full refund — no questions asked.

    Compare project details for free →

    Sources and dates.

    MahaRERA · registration record · read 12 July 2026

    MahaRERA · per-home inventory · saved-file date 18 July 2026

    This is a past RERA home list, not current availability. It does not give the date each home was sold.

    The home-list date is based on the saved file’s details.

    Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.