The builder’s RERA record, explained

Construction of 24 LIG, 768 MIG and commercial building on S.No. 126 127/1 Tathawade, Pune. Phase-II

Pune Housing & Area Development Board · P52100078654

MahaRERA · registration record · read 12 July 2026

Choose a report ↓

What does the RERA record show?

For Construction of 24 LIG, 768 MIG and commercial building on S.No. 126 127/1 Tathawade, Pune. Phase-II (P52100078654), 1388 of 1388 entries were marked unsold in the MahaRERA home list dated 18 July 2026 (saved-file date).

MahaRERA · per-home inventory · saved-file date 18 July 2026

These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.

What would help you decide?

Buyer’s Report

Understand this project

Find homes to consider, with advice on light, layout, privacy and surroundings.

₹4,999

Unit Report

Check a particular home

See its advantages, drawbacks and how it compares with other homes in this project.

₹3,999

Project Comparison Report

Choose between projects

Compare two or three projects and get recommended homes in order, with reasons for each choice.

From ₹7,999

Choose projects →

Project status and completion date.

Inside this registered phase

How do the buildings compare in the record?

1388 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.

MahaRERA · per-home inventory · saved-file date 18 July 2026

Scroll sideways to see all columns.

Building names, sale status and carpet areas — not current availability
Filed buildingEntriesSoldBookedMarked unsoldOther / unstated statusRecorded carpet-area range
A1 Building26400264053.51–60.78 sq m≈ 576–654 sq ft
A2 Building26400264053.51–60.78 sq m≈ 576–654 sq ft
A3 Building26400264053.51–60.78 sq m≈ 576–654 sq ft
Commercial Building59600596016.82–1,749.40 sq m≈ 181–18,830 sq ft

Different sizes are not necessarily different bedroom types. How we read and summarise the filing →

Unit Report

Is this the right
home for you?

Understand its light, privacy, layout and surroundings. See how it compares with similar homes and other options in this project.

₹3,999 · 1 working day

Didn’t help you decide? Full refund — no questions asked.

Find your home in the RERA list.

The same home number may appear in more than one building. Check both before choosing.

1388 listed entries

MahaRERA · per-home inventory · saved-file date 18 July 2026

RERA home list, not current availability
Home / buildingFloor in the recordCarpet areaReported statusAgreement valueAssess
1001A1 Building1060.78 sq m≈ 654 sq ftMarked unsoldNot stated
1002A1 Building1060.58 sq m≈ 652 sq ftMarked unsoldNot stated
1003A1 Building1060.78 sq m≈ 654 sq ftMarked unsoldNot stated
1004A1 Building1060.78 sq m≈ 654 sq ftMarked unsoldNot stated
1005A1 Building1060.58 sq m≈ 652 sq ftMarked unsoldNot stated
1006A1 Building1060.78 sq m≈ 654 sq ftMarked unsoldNot stated
1007A1 Building1060.78 sq m≈ 654 sq ftMarked unsoldNot stated
1008A1 Building1060.58 sq m≈ 652 sq ftMarked unsoldNot stated
1009A1 Building1060.78 sq m≈ 654 sq ftMarked unsoldNot stated
101A1 Building160.78 sq m≈ 654 sq ftMarked unsoldNot stated
1010A1 Building1060.78 sq m≈ 654 sq ftMarked unsoldNot stated
1011A1 Building1060.58 sq m≈ 652 sq ftMarked unsoldNot stated

Read every entry in one table: Read the complete saved home list.

Choose the home you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.

More from the RERA documents

Construction progress and project documents.

Cost reported as incurred

₹6,700,448,380 of an estimated ₹8,087,340,299 was reported as incurred (82.9%). This percentage is about costs. It does not show how much construction is complete.

MahaRERA project filing · read 19 July 2026 · registration P52100078654

Work reported, by building

Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.

See all reported activities
BuildingActivityReported
Commercial BuildingExcavation100.0%
Commercial BuildingBasement (if any)100.0%
Commercial BuildingPodiums (if any) 0.0%
Commercial BuildingPlinth100.0%
Commercial BuildingStilt Floor 100.0%
Commercial BuildingSlabs of Super Structure100.0%
Commercial BuildingInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises35.0%
Commercial BuildingSanitary Fittings within the flats / premises0.0%
Commercial BuildingStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100.0%
Commercial BuildingExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.34.0%
Commercial BuildingInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.24.0%
A3 BuildingExcavation100.0%
A3 BuildingBasement (if any)100.0%
A3 BuildingPodiums (if any) 100.0%
A3 BuildingPlinth100.0%
A3 BuildingStilt Floor 100.0%
A3 BuildingSlabs of Super Structure95.0%
A3 BuildingInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises30.0%
A3 BuildingSanitary Fittings within the flats / premises0.0%
A3 BuildingStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks48.0%
A3 BuildingExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.9.0%
A3 BuildingInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.21.0%
A2 BuildingExcavation100.0%
A2 BuildingBasement (if any)100.0%
A2 BuildingPodiums (if any) 100.0%
A2 BuildingPlinth100.0%
A2 BuildingStilt Floor 100.0%
A2 BuildingSlabs of Super Structure95.0%
A2 BuildingInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises61.0%
A2 BuildingSanitary Fittings within the flats / premises0.0%
A2 BuildingStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks48.0%
A2 BuildingExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.6.0%
A2 BuildingInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.21.0%
A1 BuildingExcavation100.0%
A1 BuildingBasement (if any)100.0%
A1 BuildingPodiums (if any) 100.0%
A1 BuildingPlinth100.0%
A1 BuildingStilt Floor 100.0%
A1 BuildingSlabs of Super Structure95.0%
A1 BuildingInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises64.0%
A1 BuildingSanitary Fittings within the flats / premises0.0%
A1 BuildingStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks68.0%
A1 BuildingExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.15.0%
A1 BuildingInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.24.0%

MahaRERA project filing · read 19 July 2026 · registration P52100078654

Reported deadline extensions

Revised targetReason given by the builder
31 December 2028due to certain mitigating circumstances beyond control of the promoter

MahaRERA project filing · read 19 July 2026 · registration P52100078654

Where the project funding comes from

RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.

FilingOwn fundsBorrowingPayments from buyersTotal
Estimated plan₹8,087,340,298₹0₹0₹8,087,340,298
Actual raised₹8,087,340,298₹0₹0₹8,087,340,298

MahaRERA project filing · read 19 July 2026 · registration P52100078654

Quarterly filing record

5 elapsed quarterly periods in the captured compliance schedule. No active quarterly default was recorded in this snapshot.

MahaRERA project filing · read 19 July 2026 · registration P52100078654

Documents named in the filing

  • Sanctioned building plan · 19 listed
  • Sanctioned layout plan · 1 listed
  • Form B — Promoter declaration · 1 listed
  • Title / search report · 1 listed
  • Occupancy / completion certificate · 5 listed
  • Promoter PAN · 1 listed
  • Form 2 — Engineer's certificate · 1 listed
  • Form 3 — CA certificate · 1 listed
  • Form 1 — Architect's certificate · 1 listed

A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.

MahaRERA project filing · read 19 July 2026 · registration P52100078654

Builder and past records

What else does the record show?

Projects registered under this company

Pune Housing & Area Development Board

5Pune registrations

These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.

MahaRERA Pune registration records · read 12 July 2026

Explore other registrations

Past records of sales and unsold homes

  1. 28 September 2026

    1388 marked unsold · 0 sold · 0 booked.

    Saved MahaRERA home list

  2. 20 September 2026

    1388 marked unsold · 0 sold · 0 booked.

    Saved MahaRERA home list

  3. 11 September 2026

    1388 marked unsold · 0 sold · 0 booked.

    Saved MahaRERA home list

  4. 19 July 2026

    1388 marked unsold · 0 sold · 0 booked.

    Saved MahaRERA home list

These dates show when the records were saved, not when homes were sold. Sales may have changed since then, even if the saved counts are the same.

Project Comparison Report

Which project should you buy in?
And which home?

Compare up to three projects. We read their plans and RERA documents, recommend homes in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.

Create my Comparison Report →

2 projects · ₹7,999
3 projects · ₹9,999

Within 1 working day

Didn’t help you decide? Full refund — no questions asked.

Compare project details for free →

Sources and dates.

MahaRERA · registration record · read 12 July 2026

MahaRERA · per-home inventory · saved-file date 18 July 2026

This is a past RERA home list, not current availability. It does not give the date each home was sold.

The home-list date is based on the saved file’s details.

Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.