The builder’s RERA record, explained

Godrej Aqua Vista

Oxford Realty LLP · PM1260002500389

MahaRERA · registration record · read 12 July 2026

Choose a report ↓

What does the RERA record show?

For Godrej Aqua Vista (PM1260002500389), 1329 of 1582 entries were marked unsold in the MahaRERA home list dated 18 July 2026 (saved-file date).

MahaRERA · per-home inventory · saved-file date 18 July 2026

For Godrej Aqua Vista, ₹11,431 per sq ft of carpet area is the median rate across 253 sold or booked entries with prices in the MahaRERA home list dated 18 July 2026 (saved-file date). These are historical agreement values, not current asking prices.

MahaRERA · per-home inventory · saved-file date 18 July 2026

These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.

What would help you decide?

Buyer’s Report

Understand this project

Find homes to consider, with advice on light, layout, privacy and surroundings.

₹4,999

Unit Report

Check a particular home

See its advantages, drawbacks and how it compares with other homes in this project.

₹3,999

Project Comparison Report

Choose between projects

Compare two or three projects and get recommended homes in order, with reasons for each choice.

From ₹7,999

Choose projects →

Project status and completion date.

Prices reported to RERA

What prices have been reported?

₹11,431/ sq ft carpet area

Across 253 sold or booked entries with reported prices. The middle 80% of rates fall between ₹10,893 and ₹12,360.

MahaRERA · per-home inventory · saved-file date 18 July 2026

How is this calculated?

For each sold or booked entry, we divide the reported agreement value by its carpet area in square feet. The median is the middle rate when these rates are put in order. We show it only when at least five entries have prices. We exclude valuations of unsold homes and government reference rates. The figures may include different sizes and property types. They are historical agreement values, not current asking prices or the total cost including extra charges.

Sales Report

What did similar homes sell for?

Compare reported agreement values by building, size and floor. See which homes were marked unsold on the date shown.

₹2,999 · delivered on payment

Inside this registered phase

How do the buildings compare in the record?

1582 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.

MahaRERA · per-home inventory · saved-file date 18 July 2026

Scroll sideways to see all columns.

Building names, sale status and carpet areas — not current availability
Filed buildingEntriesSoldBookedMarked unsoldOther / unstated statusRecorded carpet-area range
Tower 1213300133020.54–115.66 sq m≈ 221–1,245 sq ft
Tower 1326000260020.55–95.92 sq m≈ 221–1,032 sq ft
Tower 1426500265021.93–95.72 sq m≈ 236–1,030 sq ft
Tower 1523600236028.12–120.09 sq m≈ 303–1,293 sq ft
Tower 162191011999067.45–115.23 sq m≈ 726–1,240 sq ft
Tower 1724710429114025.09–115.23 sq m≈ 270–1,240 sq ft
Tower 1822200222025.01–115.23 sq m≈ 269–1,240 sq ft

Different sizes are not necessarily different bedroom types. How we read and summarise the filing →

Unit Report

Is this the right
home for you?

Understand its light, privacy, layout and surroundings. See how it compares with similar homes and other options in this project.

₹3,999 · 1 working day

Didn’t help you decide? Full refund — no questions asked.

Find your home in the RERA list.

The same home number may appear in more than one building. Check both before choosing.

1582 listed entries

MahaRERA · per-home inventory · saved-file date 18 July 2026

RERA home list, not current availability
Home / buildingFloor in the recordCarpet areaReported statusAgreement valueAssess
GAVT12010201Tower 12136.44 sq m≈ 392 sq ftMarked unsoldNot stated
GAVT12010202Tower 12124.89 sq m≈ 268 sq ftMarked unsoldNot stated
GAVT12010203Tower 12124.88 sq m≈ 268 sq ftMarked unsoldNot stated
GAVT12010204Tower 12131.92 sq m≈ 344 sq ftMarked unsoldNot stated
GAVT12010205Tower 12140.28 sq m≈ 434 sq ftMarked unsoldNot stated
GAVT12010206Tower 12134.41 sq m≈ 370 sq ftMarked unsoldNot stated
GAVT12010207Tower 12134.85 sq m≈ 375 sq ftMarked unsoldNot stated
GAVT12010208Tower 12128.75 sq m≈ 309 sq ftMarked unsoldNot stated
GAVT12010209Tower 12150.79 sq m≈ 547 sq ftMarked unsoldNot stated
GAVT12010210Tower 12128.49 sq m≈ 307 sq ftMarked unsoldNot stated
GAVT12010211Tower 12130.07 sq m≈ 324 sq ftMarked unsoldNot stated
GAVT12010212Tower 12129.03 sq m≈ 312 sq ftMarked unsoldNot stated

Read every entry in one table: Read the complete saved home list.

Choose the home you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.

More from the RERA documents

Construction progress and project documents.

Cost reported as incurred

₹359,480,303 of an estimated ₹7,191,559,300 was reported as incurred (5.0%). This percentage is about costs. It does not show how much construction is complete.

MahaRERA project filing · read 19 July 2026 · registration PM1260002500389

Work reported, by building

Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.

See all reported activities
BuildingActivityReported
Tower 12Excavation0.0%
Tower 12Basement (if any)0.0%
Tower 12Podiums (if any) 0.0%
Tower 12Plinth0.0%
Tower 12Stilt Floor 0.0%
Tower 12Slabs of Super Structure0.0%
Tower 12Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
Tower 12Sanitary Fittings within the flats / premises0.0%
Tower 12Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
Tower 12External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Tower 12Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
Tower 13Excavation0.0%
Tower 13Basement (if any)0.0%
Tower 13Podiums (if any) 0.0%
Tower 13Plinth0.0%
Tower 13Stilt Floor 0.0%
Tower 13Slabs of Super Structure0.0%
Tower 13Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
Tower 13Sanitary Fittings within the flats / premises0.0%
Tower 13Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
Tower 13External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Tower 13Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
Tower 14Excavation0.0%
Tower 14Basement (if any)0.0%
Tower 14Podiums (if any) 0.0%
Tower 14Plinth0.0%
Tower 14Stilt Floor 0.0%
Tower 14Slabs of Super Structure0.0%
Tower 14Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
Tower 14Sanitary Fittings within the flats / premises0.0%
Tower 14Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
Tower 14External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Tower 14Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
Tower 15Excavation0.0%
Tower 15Basement (if any)0.0%
Tower 15Podiums (if any) 0.0%
Tower 15Plinth0.0%
Tower 15Stilt Floor 0.0%
Tower 15Slabs of Super Structure0.0%
Tower 15Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
Tower 15Sanitary Fittings within the flats / premises0.0%
Tower 15Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
Tower 15External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Tower 15Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
Tower 16Excavation100.0%
Tower 16Basement (if any)0.0%
Tower 16Podiums (if any) 0.0%
Tower 16Plinth50.0%
Tower 16Stilt Floor 0.0%
Tower 16Slabs of Super Structure0.0%
Tower 16Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
Tower 16Sanitary Fittings within the flats / premises0.0%
Tower 16Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
Tower 16External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Tower 16Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
Tower 17Excavation100.0%
Tower 17Basement (if any)0.0%
Tower 17Podiums (if any) 0.0%
Tower 17Plinth20.0%
Tower 17Stilt Floor 0.0%
Tower 17Slabs of Super Structure0.0%
Tower 17Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
Tower 17Sanitary Fittings within the flats / premises0.0%
Tower 17Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
Tower 17External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Tower 17Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
Tower 18Excavation100.0%
Tower 18Basement (if any)0.0%
Tower 18Podiums (if any) 0.0%
Tower 18Plinth0.0%
Tower 18Stilt Floor 0.0%
Tower 18Slabs of Super Structure0.0%
Tower 18Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
Tower 18Sanitary Fittings within the flats / premises0.0%
Tower 18Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
Tower 18External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Tower 18Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%

MahaRERA project filing · read 19 July 2026 · registration PM1260002500389

Where the project funding comes from

RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.

FilingOwn fundsBorrowingPayments from buyersTotal
Estimated plan₹2,149,580,024₹0₹7,253,452,579₹9,403,032,603
Actual raised₹1,567,960,473₹0₹429,895,678₹1,997,856,151

MahaRERA project filing · read 19 July 2026 · registration PM1260002500389

Quarterly filing record

3 elapsed quarterly periods in the captured compliance schedule. No active quarterly default was recorded in this snapshot.

MahaRERA project filing · read 19 July 2026 · registration PM1260002500389

Documents named in the filing

  • Title / search report · 1 listed
  • Commencement certificate · 7 listed
  • Promoter PAN · 3 listed
  • Form B — Promoter declaration · 2 listed
  • Sanctioned layout plan · 1 listed
  • Occupancy / completion certificate · 6 listed
  • Sanctioned building plan · 45 listed
  • Form 3 — CA certificate · 1 listed
  • Form 1 — Architect's certificate · 1 listed
  • Form 2 — Engineer's certificate · 1 listed

A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.

MahaRERA project filing · read 19 July 2026 · registration PM1260002500389

Builder and past records

What else does the record show?

Projects registered under this company

Oxford Realty LLP

1Pune registrations

These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.

MahaRERA Pune registration records · read 12 July 2026

Explore other registrations

    Past records of sales and unsold homes

    1. 20 September 2026

      1329 marked unsold · 205 sold · 48 booked.

      Saved MahaRERA home list

    2. 11 September 2026

      1329 marked unsold · 205 sold · 48 booked.

      Saved MahaRERA home list

    3. 19 July 2026

      1329 marked unsold · 205 sold · 48 booked.

      Saved MahaRERA home list

    4. 18 July 2026

      1329 marked unsold · 205 sold · 48 booked.

      Saved MahaRERA home list, date based on the saved file

    These dates show when the records were saved, not when homes were sold. Sales may have changed since then, even if the saved counts are the same.

    Project Comparison Report

    Which project should you buy in?
    And which home?

    Compare up to three projects. We read their plans and RERA documents, recommend homes in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.

    Create my Comparison Report →

    2 projects · ₹7,999
    3 projects · ₹9,999

    Within 1 working day

    Didn’t help you decide? Full refund — no questions asked.

    Compare project details for free →

    Sources and dates.

    MahaRERA · registration record · read 12 July 2026

    MahaRERA · per-home inventory · saved-file date 18 July 2026

    This is a past RERA home list, not current availability. It does not give the date each home was sold.

    The home-list date is based on the saved file’s details.

    Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.

    Open MahaRERA · search PM1260002500389 ↗