homeonpaper.

Builder’s RERA records,
explained for buyers.

The builder’s RERA record, explained

Palladio Presidential Suites Balewadi RiverFront

Vilas Javdekar Eco Housing Private Limited · PR1260002502961

MahaRERA · registration record · read 2 July 2026

Choose a report ↓

What does the RERA record show?

For Palladio Presidential Suites Balewadi RiverFront (PR1260002502961), 115 of 356 entries were marked unsold in the MahaRERA home list dated 18 July 2026 (saved-file date).

MahaRERA · per-home inventory · saved-file date 18 July 2026

For Palladio Presidential Suites Balewadi RiverFront, ₹14,067 per sq ft of carpet area is the median rate across 169 sold or booked entries with prices in the MahaRERA home list dated 18 July 2026 (saved-file date). These are historical agreement values, not current asking prices.

MahaRERA · per-home inventory · saved-file date 18 July 2026

These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.

What would help you decide?

Buyer’s Report

Understand this project

Find homes to consider, with advice on light, layout, privacy and surroundings.

₹4,999

Unit Report

Check a particular home

See its advantages, drawbacks and how it compares with other homes in this project.

₹3,999

Project Comparison Report

Choose between projects

Compare two or three projects and get recommended homes in order, with reasons for each choice.

From ₹7,999

Choose projects →

Project status and completion date.

Prices reported to RERA

What prices have been reported?

₹14,067/ sq ft carpet area

Across 169 sold or booked entries with reported prices. The middle 80% of rates fall between ₹13,593 and ₹15,145.

MahaRERA · per-home inventory · saved-file date 18 July 2026

How is this calculated?

For each sold or booked entry, we divide the reported agreement value by its carpet area in square feet. The median is the middle rate when these rates are put in order. We show it only when at least five entries have prices. We exclude valuations of unsold homes and government reference rates. The figures may include different sizes and property types. They are historical agreement values, not current asking prices or the total cost including extra charges.

Sales Report

What did similar homes sell for?

Compare reported agreement values by building, size and floor. See which homes were marked unsold on the date shown.

₹2,999 · delivered on payment

Inside this registered phase

How do the buildings compare in the record?

356 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.

MahaRERA · per-home inventory · saved-file date 18 July 2026

Scroll sideways to see all columns.

Building names, sale status and carpet areas — not current availability
Filed buildingEntriesSoldBookedMarked unsoldOther / unstated statusRecorded carpet-area range
Tower 1100010025.50–199.47 sq m≈ 274–2,147 sq ft
Tower 28008091.95–313.20 sq m≈ 990–3,371 sq ft
Tower 38008091.95–199.47 sq m≈ 990–2,147 sq ft
Tower 41628310353492.25–128.95 sq m≈ 993–1,388 sq ft
Tower 5168724543892.46–132.70 sq m≈ 995–1,428 sq ft

Different sizes are not necessarily different bedroom types. How we read and summarise the filing →

Unit Report

Is this the right
home for you?

Understand its light, privacy, layout and surroundings. See how it compares with similar homes and other options in this project.

₹3,999 · 1 working day

Didn’t help you decide? Full refund — no questions asked.

Find your home in the RERA list.

The same home number may appear in more than one building. Check both before choosing.

356 listed entries

MahaRERA · per-home inventory · saved-file date 18 July 2026

RERA home list, not current availability
Home / buildingFloor in the recordCarpet areaReported statusAgreement valueAssess
101Tower 11100.37 sq m≈ 1,080 sq ftMarked unsoldNot stated
102Tower 1192.41 sq m≈ 995 sq ftMarked unsoldNot stated
103Tower 1192.23 sq m≈ 993 sq ftMarked unsoldNot stated
104Tower 11101.14 sq m≈ 1,089 sq ftMarked unsoldNot stated
105Tower 11109.55 sq m≈ 1,179 sq ftMarked unsoldNot stated
106Tower 11128.95 sq m≈ 1,388 sq ftMarked unsoldNot stated
Business centreTower 1202199.47 sq m≈ 2,147 sq ftMarked unsoldNot stated
Guest suitesTower 1202102.32 sq m≈ 1,101 sq ftMarked unsoldNot stated
Multi-purpose hall Tower 1205199.47 sq m≈ 2,147 sq ftMarked unsoldNot stated
Waiting loungeTower 120525.5 sq m≈ 274 sq ftMarked unsoldNot stated
101Tower 21101.13 sq m≈ 1,089 sq ftMarked unsoldNot stated
102Tower 21109.4 sq m≈ 1,178 sq ftMarked unsoldNot stated

Read every entry in one table: Read the complete saved home list.

Choose the home you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.

More from the RERA documents

Construction progress and project documents.

Cost reported as incurred

₹71,900,000 of an estimated ₹2,573,600,000 was reported as incurred (2.8%). This percentage is about costs. It does not show how much construction is complete.

MahaRERA project filing · read 18 July 2026 · registration PR1260002502961

Work reported, by building

Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.

See all reported activities
BuildingActivityReported
Tower 1Excavation0.0%
Tower 1Basement (if any)0.0%
Tower 1Plinth0.0%
Tower 1Stilt Floor 0.0%
Tower 1Slabs of Super Structure0.0%
Tower 1Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
Tower 1Sanitary Fittings within the flats / premises0.0%
Tower 1Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
Tower 1External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Tower 1Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
Tower 2Excavation90.0%
Tower 2Basement (if any)0.0%
Tower 2Plinth0.0%
Tower 2Stilt Floor 0.0%
Tower 2Slabs of Super Structure0.0%
Tower 2Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
Tower 2Sanitary Fittings within the flats / premises0.0%
Tower 2Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
Tower 2External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Tower 2Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
Tower 3Excavation100.0%
Tower 3Basement (if any)0.0%
Tower 3Plinth0.0%
Tower 3Stilt Floor 0.0%
Tower 3Slabs of Super Structure0.0%
Tower 3Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
Tower 3Sanitary Fittings within the flats / premises0.0%
Tower 3Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
Tower 3External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Tower 3Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
Tower 4Excavation100.0%
Tower 4Basement (if any)0.0%
Tower 4Plinth0.0%
Tower 4Stilt Floor 0.0%
Tower 4Slabs of Super Structure0.0%
Tower 4Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
Tower 4Sanitary Fittings within the flats / premises0.0%
Tower 4Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
Tower 4External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Tower 4Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
Tower 5Excavation90.0%
Tower 5Basement (if any)0.0%
Tower 5Plinth0.0%
Tower 5Stilt Floor 0.0%
Tower 5Slabs of Super Structure0.0%
Tower 5Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
Tower 5Sanitary Fittings within the flats / premises0.0%
Tower 5Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
Tower 5External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Tower 5Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%

MahaRERA project filing · read 18 July 2026 · registration PR1260002502961

Where the project funding comes from

RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.

FilingOwn fundsBorrowingPayments from buyersTotal
Estimated plan₹0₹1,350,000,000₹5,230,543,027₹6,580,543,027
Actual raised₹1,414,487,519₹565,251,678₹289,901,716₹2,269,640,913

MahaRERA project filing · read 18 July 2026 · registration PR1260002502961

Quarterly filing record

2 elapsed quarterly periods in the captured compliance schedule. No active quarterly default was recorded in this snapshot.

MahaRERA project filing · read 18 July 2026 · registration PR1260002502961

Documents named in the filing

  • Promoter PAN · 6 listed
  • Form B — Promoter declaration · 1 listed
  • Commencement certificate · 5 listed
  • Sanctioned building plan · 21 listed
  • Title / search report · 9 listed
  • Sanctioned layout plan · 1 listed
  • Occupancy / completion certificate · 4 listed
  • Form 3 — CA certificate · 1 listed
  • Form 1 — Architect's certificate · 1 listed
  • Form 2 — Engineer's certificate · 1 listed

A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.

MahaRERA project filing · read 18 July 2026 · registration PR1260002502961

Builder and past records

What else does the record show?

Projects registered under this company

Vilas Javdekar Eco Housing Private Limited

4Pune registrations

These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.

MahaRERA Pune registration records · read 2 July 2026 – 12 July 2026

Explore other registrations

Past records of sales and unsold homes

  1. 21 September 2026

    115 marked unsold · 155 sold · 14 booked.

    Saved MahaRERA home list

  2. 12 September 2026

    115 marked unsold · 155 sold · 14 booked.

    Saved MahaRERA home list

  3. 4 September 2026

    115 marked unsold · 155 sold · 14 booked.

    Saved MahaRERA home list

  4. 18 July 2026

    115 marked unsold · 155 sold · 14 booked.

    Saved MahaRERA home list

These dates show when the records were saved, not when homes were sold. Sales may have changed since then, even if the saved counts are the same.

More projects to explore

Other projects in this locality.

These projects list the same locality. They may differ in exact location, home type and price.

Project Comparison Report

Which project should you buy in?
And which home?

Compare up to three projects. We read their plans and RERA documents, recommend homes in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.

Create my Comparison Report →

2 projects · ₹7,999
3 projects · ₹9,999

Within 1 working day

Didn’t help you decide? Full refund — no questions asked.

Compare project details for free →

Sources and dates.

MahaRERA · registration record · read 2 July 2026

MahaRERA · per-home inventory · saved-file date 18 July 2026

This is a past RERA home list, not current availability. It does not give the date each home was sold.

The home-list date is based on the saved file’s details.

Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.

Open MahaRERA · search PR1260002502961 ↗
homeonpaper