The builder’s RERA record, explained

The Latitude Phase 2

Ahura Builders · PR1261012500881

MahaRERA · registration record · read 12 July 2026

Choose a report ↓

What does the RERA record show?

For The Latitude Phase 2 (PR1261012500881), 267 of 267 entries were marked unsold in the MahaRERA home list dated 18 July 2026 (saved-file date).

MahaRERA · per-home inventory · saved-file date 18 July 2026

These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.

What would help you decide?

Buyer’s Report

Understand this project

Find homes to consider, with advice on light, layout, privacy and surroundings.

₹4,999

Unit Report

Check a particular home

See its advantages, drawbacks and how it compares with other homes in this project.

₹3,999

Project Comparison Report

Choose between projects

Compare two or three projects and get recommended homes in order, with reasons for each choice.

From ₹7,999

Choose projects →

Project status and completion date.

Inside this registered phase

How do the buildings compare in the record?

267 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.

MahaRERA · per-home inventory · saved-file date 18 July 2026

Scroll sideways to see all columns.

Building names, sale status and carpet areas — not current availability
Filed buildingEntriesSoldBookedMarked unsoldOther / unstated statusRecorded carpet-area range
Wing E480048087.17–119.04 sq m≈ 938–1,281 sq ft
Wing F510051067.84–91.98 sq m≈ 730–990 sq ft
Wing G560056067.84–91.98 sq m≈ 730–990 sq ft
Wing H560056067.84–91.98 sq m≈ 730–990 sq ft
Wing I560056067.84–91.98 sq m≈ 730–990 sq ft

Different sizes are not necessarily different bedroom types. How we read and summarise the filing →

Unit Report

Is this the right
home for you?

Understand its light, privacy, layout and surroundings. See how it compares with similar homes and other options in this project.

₹3,999 · 1 working day

Didn’t help you decide? Full refund — no questions asked.

Find your home in the RERA list.

The same home number may appear in more than one building. Check both before choosing.

267 listed entries

MahaRERA · per-home inventory · saved-file date 18 July 2026

RERA home list, not current availability
Home / buildingFloor in the recordCarpet areaReported statusAgreement valueAssess
Flat No. 1001Wing E10118.9 sq m≈ 1,280 sq ftMarked unsoldNot stated
Flat No. 1002Wing E1087.17 sq m≈ 938 sq ftMarked unsoldNot stated
Flat No. 1003Wing E1091.98 sq m≈ 990 sq ftMarked unsoldNot stated
Flat No. 1004Wing E10119.04 sq m≈ 1,281 sq ftMarked unsoldNot stated
Flat No. 101Wing E1118.9 sq m≈ 1,280 sq ftMarked unsoldNot stated
Flat No. 102Wing E187.17 sq m≈ 938 sq ftMarked unsoldNot stated
Flat No. 103Wing E191.98 sq m≈ 990 sq ftMarked unsoldNot stated
Flat No. 104Wing E1119.04 sq m≈ 1,281 sq ftMarked unsoldNot stated
Flat No. 1101Wing E11118.9 sq m≈ 1,280 sq ftMarked unsoldNot stated
Flat No. 1102Wing E1187.17 sq m≈ 938 sq ftMarked unsoldNot stated
Flat No. 1103Wing E1191.98 sq m≈ 990 sq ftMarked unsoldNot stated
Flat No. 1104Wing E11119.04 sq m≈ 1,281 sq ftMarked unsoldNot stated

Read every entry in one table: Read the complete saved home list.

Choose the home you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.

More from the RERA documents

Construction progress and project documents.

Cost reported as incurred

₹7,346,581,900 of an estimated ₹31,000,000,000 was reported as incurred (23.7%). This percentage is about costs. It does not show how much construction is complete.

MahaRERA project filing · read 19 July 2026 · registration PR1261012500881

Work reported, by building

Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.

See all reported activities
BuildingActivityReported
Wing EExcavation58.0%
Wing EBasement (if any)0.0%
Wing EPodiums (if any) 0.0%
Wing EPlinth0.0%
Wing EStilt Floor 0.0%
Wing ESlabs of Super Structure0.0%
Wing EInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
Wing ESanitary Fittings within the flats / premises0.0%
Wing EStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
Wing EExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Wing EInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
Wing FExcavation58.0%
Wing FBasement (if any)0.0%
Wing FPodiums (if any) 0.0%
Wing FPlinth0.0%
Wing FStilt Floor 0.0%
Wing FSlabs of Super Structure0.0%
Wing FInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
Wing FSanitary Fittings within the flats / premises0.0%
Wing FStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
Wing FExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Wing FInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
Wing GExcavation58.0%
Wing GBasement (if any)0.0%
Wing GPodiums (if any) 0.0%
Wing GPlinth0.0%
Wing GStilt Floor 0.0%
Wing GSlabs of Super Structure0.0%
Wing GInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
Wing GSanitary Fittings within the flats / premises0.0%
Wing GStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
Wing GExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Wing GInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
Wing HExcavation58.0%
Wing HBasement (if any)0.0%
Wing HPodiums (if any) 0.0%
Wing HPlinth0.0%
Wing HStilt Floor 0.0%
Wing HSlabs of Super Structure0.0%
Wing HInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
Wing HSanitary Fittings within the flats / premises0.0%
Wing HStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
Wing HExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Wing HInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
Wing IExcavation58.0%
Wing IBasement (if any)0.0%
Wing IPodiums (if any) 0.0%
Wing IPlinth0.0%
Wing IStilt Floor 0.0%
Wing ISlabs of Super Structure0.0%
Wing IInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
Wing ISanitary Fittings within the flats / premises0.0%
Wing IStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
Wing IExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Wing IInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%

MahaRERA project filing · read 19 July 2026 · registration PR1261012500881

Where the project funding comes from

RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.

FilingOwn fundsBorrowingPayments from buyersTotal
Estimated plan₹1,385,271,265₹0₹550,418,290₹1,935,689,555
Actual raised₹231,725,453₹0₹43,730,549₹275,456,002

MahaRERA project filing · read 19 July 2026 · registration PR1261012500881

Documents named in the filing

  • Title / search report · 1 listed
  • Commencement certificate · 1 listed
  • Sanctioned building plan · 12 listed
  • Form 3 — CA certificate · 1 listed
  • Promoter PAN · 1 listed
  • Form B — Promoter declaration · 1 listed
  • Sanctioned layout plan · 1 listed
  • Occupancy / completion certificate · 2 listed
  • Form 1 — Architect's certificate · 1 listed
  • Form 2 — Engineer's certificate · 1 listed

A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.

MahaRERA project filing · read 19 July 2026 · registration PR1261012500881

Builder and past records

What else does the record show?

Projects registered under this company

Ahura Builders

1Pune registrations

These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.

MahaRERA Pune registration records · read 12 July 2026

Explore other registrations

    Past records of sales and unsold homes

    1. 20 September 2026

      267 marked unsold · 0 sold · 0 booked.

      Saved MahaRERA home list

    2. 11 September 2026

      267 marked unsold · 0 sold · 0 booked.

      Saved MahaRERA home list

    3. 19 July 2026

      267 marked unsold · 0 sold · 0 booked.

      Saved MahaRERA home list

    4. 18 July 2026

      267 marked unsold · 0 sold · 0 booked.

      Saved MahaRERA home list, date based on the saved file

    These dates show when the records were saved, not when homes were sold. Sales may have changed since then, even if the saved counts are the same.

    More projects to explore

    Other projects in this locality.

    These projects list the same locality. They may differ in exact location, home type and price.

    Project Comparison Report

    Which project should you buy in?
    And which home?

    Compare up to three projects. We read their plans and RERA documents, recommend homes in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.

    Create my Comparison Report →

    2 projects · ₹7,999
    3 projects · ₹9,999

    Within 1 working day

    Didn’t help you decide? Full refund — no questions asked.

    Compare project details for free →

    Sources and dates.

    MahaRERA · registration record · read 12 July 2026

    MahaRERA · per-home inventory · saved-file date 18 July 2026

    This is a past RERA home list, not current availability. It does not give the date each home was sold.

    The home-list date is based on the saved file’s details.

    Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.

    Open MahaRERA · search PR1261012500881 ↗