Gagan Landmarks LLP · P52100002439
For Gagan Ela (P52100002439), 50 of 251 entries were marked unsold in the MahaRERA home list dated 18 July 2026 (saved-file date).
MahaRERA · per-home inventory · saved-file date 18 July 2026
For Gagan Ela, ₹9,139 per sq ft of carpet area is the median rate across 201 sold or booked entries with prices in the MahaRERA home list dated 18 July 2026 (saved-file date). These are historical agreement values, not current asking prices.
MahaRERA · per-home inventory · saved-file date 18 July 2026
These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.
Builder’s completion target
This target date has passed. The record shown here does not confirm whether the project is complete or has received more time.
Status shown on RERA
This is the status shown on RERA. It does not confirm an occupancy certificate or today’s construction progress.
Prices reported to RERA
₹9,139/ sq ft carpet area
Across 201 sold or booked entries with reported prices. The middle 80% of rates fall between ₹6,735 and ₹13,057.
MahaRERA · per-home inventory · saved-file date 18 July 2026
For each sold or booked entry, we divide the reported agreement value by its carpet area in square feet. The median is the middle rate when these rates are put in order. We show it only when at least five entries have prices. We exclude valuations of unsold homes and government reference rates. The figures may include different sizes and property types. They are historical agreement values, not current asking prices or the total cost including extra charges.
Sales Report
Compare reported agreement values by building, size and floor. See which homes were marked unsold on the date shown.
Inside this registered phase
251 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.
MahaRERA · per-home inventory · saved-file date 18 July 2026
Scroll sideways to see all columns.
| Filed building | Entries | Sold | Booked | Marked unsold | Other / unstated status | Recorded carpet-area range |
|---|---|---|---|---|---|---|
| A | 128 | 108 | 0 | 20 | 0 | 53.49–76.73 sq m≈ 576–826 sq ft |
| B | 64 | 42 | 0 | 22 | 0 | 78.94–124.99 sq m≈ 850–1,345 sq ft |
| Commercial and MHADA | 59 | 51 | 0 | 8 | 0 | 14.62–47.42 sq m≈ 157–510 sq ft |
Different sizes are not necessarily different bedroom types. How we read and summarise the filing →
Unit Report
Understand its light, privacy, layout and surroundings. See how it compares with similar homes and other options in this project.
Didn’t help you decide? Full refund — no questions asked.
The same home number may appear in more than one building. Check both before choosing.
MahaRERA · per-home inventory · saved-file date 18 July 2026
| Home / building | Floor in the record | Carpet area | Reported status | Agreement value | Assess |
|---|---|---|---|---|---|
| 1001A | 10 | 55.0 sq m≈ 592 sq ft | Sold | ₹5,407,000 | |
| 1002A | 10 | 56.54 sq m≈ 609 sq ft | Sold | ₹5,743,000 | |
| 1003A | 10 | 56.55 sq m≈ 609 sq ft | Sold | ₹4,910,000 | |
| 1004A | 10 | 54.55 sq m≈ 587 sq ft | Sold | ₹4,590,000 | |
| 1005A | 10 | 55.02 sq m≈ 592 sq ft | Sold | ₹6,578,754 | |
| 1006A | 10 | 61.81 sq m≈ 665 sq ft | Sold | ₹5,529,000 | |
| 1007A | 10 | 61.81 sq m≈ 665 sq ft | Sold | ₹5,938,375 | |
| 1008A | 10 | 60.51 sq m≈ 651 sq ft | Sold | ₹5,715,000 | |
| 101A | 1 | 55.06 sq m≈ 593 sq ft | Marked unsold | Not stated | |
| 102A | 1 | 56.72 sq m≈ 611 sq ft | Sold | ₹6,203,626 | |
| 103A | 1 | 56.72 sq m≈ 611 sq ft | Marked unsold | Not stated | |
| 104A | 1 | 54.6 sq m≈ 588 sq ft | Marked unsold | Not stated |
Read every entry in one table: Read the complete saved home list.
Choose the home you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.
More from the RERA documents
Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.
| Building | Activity | Reported |
|---|---|---|
| A | Excavation | 100.0% |
| A | Basement (if any) | 100.0% |
| A | Podiums (if any) | 100.0% |
| A | Plinth | 100.0% |
| A | Stilt Floor | 100.0% |
| A | Slabs of Super Structure | 100.0% |
| A | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 63.0% |
| A | Sanitary Fittings within the flats / premises | 0.0% |
| A | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 88.0% |
| A | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 72.0% |
| A | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 18.0% |
| B | Excavation | 100.0% |
| B | Basement (if any) | 100.0% |
| B | Podiums (if any) | 100.0% |
| B | Plinth | 100.0% |
| B | Stilt Floor | 100.0% |
| B | Slabs of Super Structure | 100.0% |
| B | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 34.0% |
| B | Sanitary Fittings within the flats / premises | 0.0% |
| B | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 85.0% |
| B | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 42.0% |
| B | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 15.0% |
| Commercial and MHADA | Excavation | 100.0% |
| Commercial and MHADA | Basement (if any) | 100.0% |
| Commercial and MHADA | Podiums (if any) | 0.0% |
| Commercial and MHADA | Plinth | 100.0% |
| Commercial and MHADA | Stilt Floor | 0.0% |
| Commercial and MHADA | Slabs of Super Structure | 100.0% |
| Commercial and MHADA | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100.0% |
| Commercial and MHADA | Sanitary Fittings within the flats / premises | 100.0% |
| Commercial and MHADA | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100.0% |
| Commercial and MHADA | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100.0% |
| Commercial and MHADA | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 98.0% |
MahaRERA project filing · read 18 July 2026 · registration P52100002439
| Revised target | Reason given by the builder |
|---|---|
| 30 December 2021 | 1) We are the Promoters of the Real Estate Project known as “GAGAN ELA” under implementation by us on land out of Survey No.23, Village Mohammedwadi within the Registration Sub-District of Taluka Haveli, District Pune. You were kind enough to grant Registration of the said Project vide your Registration Certificate No. P52100002439 dated 01/08/2017. 2) In anticipation that we would complete the said Project on or before 31/12/2020, in our Application to you for Registration of our Project, we had mentioned the date of Completion as 31/12/2020. However, due to unforeseen and unexpected delays in the Municipal Corporation of Pune sanctioning the revised Building Plans in respect of the said Project and the very severe adverse market conditions, we anticipate that we will not able to complete the Project beyond the stipulated date. 3) We have therefore to request you to grant Extension of One Year for completion by us of the said Project and to issue an Extension Certificate to us accordingly. |
| 30 June 2023 | 1) We are the Promoters of the Real Estate Project known as “GAGAN ELA” under implementation by us on land out of Survey No. 23 Hissa No. 7/1, 7/2 and 7/3, Village Mohammedwadi within the Registration Sub-District of Taluka Haveli, District Pune. You were kind enough to grant Registration of the said Project vide your Registration Certificate No. P52100002439 dated 01/08/2017. 2) In anticipation that we would complete the said Project on or before 30/12/2022, in our application to you for Registration of our Project, we had mentioned the date of Completion as 30/12/2022. However, due to unforeseen and unexpected delays in the Municipal Corporation of Pune sanctioning the revised Building Plans in respect of the said Project and the very severe adverse market conditions, we anticipate that we will not able to complete the Project beyond the stipulated date. 3) We have therefore to request you to grant Extension of Six Month for completion by us of the said Project and to issue an Extension Certificate to us accordingly. |
| 31 March 2024 | 1) We are the Promoters of the Real Estate Project known as “GAGAN ELA” under implementation by us on land out of Survey No. 23 Hissa No. 7/1, 7/2 and 7/3, Village Mohammedwadi within the Registration Sub-District of Taluka Haveli, District Pune. You were kind enough to grant Registration of the said Project vide your Registration Certificate No. P52100002439 dated 01/08/2017. 2) In anticipation that we would complete the said Project on or before 30/06/2023, in our application to you for Registration of our Project, we had mentioned the date of Completion as 30/06/2023. However, due to unforeseen and unexpected delays in the Municipal Corporation of Pune sanctioning the revised Building Plans in respect of the said Project and the very severe adverse market conditions, we anticipate that we will not able to complete the Project beyond the stipulated date. 3) We have therefore to request you to grant Extension of Nine Month for completion by us of the said Project and to issue an Extension Certificate to us accordingly. |
| 30 June 2025 | 1. As per the latest QPR the Construction of the project GAGAN ELA is approximately 90% completed. 2. The proposed completion date for the project was 30.12.2022 but in view of Second wave of COVID-19 pandemic around April 2021, construction workplace came to stand still due to consequent nationwide lockdown. |
MahaRERA project filing · read 18 July 2026 · registration P52100002439
RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.
| Filing | Own funds | Borrowing | Payments from buyers | Total |
|---|---|---|---|---|
| Estimated plan | ₹0 | ₹350,000,000 | ₹893,744,903 | ₹1,443,744,903 |
| Actual raised | ₹0 | ₹0 | ₹245,367,687 | ₹245,367,687 |
MahaRERA project filing · read 18 July 2026 · registration P52100002439
32 elapsed quarterly periods in the captured compliance schedule. Active default was recorded for FY 2025-2026.
MahaRERA project filing · read 18 July 2026 · registration P52100002439
A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.
MahaRERA project filing · read 18 July 2026 · registration P52100002439
Builder and past records
Projects registered under this company
3Pune registrations
These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.
MahaRERA Pune registration records · read 12 July 2026
Past records of sales and unsold homes
21 September 2026
50 marked unsold · 201 sold · 0 booked.
Saved MahaRERA home list
13 September 2026
50 marked unsold · 201 sold · 0 booked.
Saved MahaRERA home list
4 September 2026
50 marked unsold · 201 sold · 0 booked.
Saved MahaRERA home list
18 July 2026
50 marked unsold · 201 sold · 0 booked.
Saved MahaRERA home list
These dates show when the records were saved, not when homes were sold. Sales may have changed since then, even if the saved counts are the same.
More projects to explore
These projects list the same locality. They may differ in exact location, home type and price.
Mohammadwadi · Pune
P52100045561
11 of 162 entries marked unsold
MahaRERA · per-home inventory · read 9 September 2026
View project details →Mohammadwadi · Pune
P52100079657
93 of 93 entries marked unsold
MahaRERA · per-home inventory · saved-file date 18 July 2026
View project details →Mohammadwadi · Pune
P52100003050
31 of 92 entries marked unsold
MahaRERA · per-home inventory · saved-file date 18 July 2026
View project details →Project Comparison Report
Compare up to three projects. We read their plans and RERA documents, recommend homes in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.
2 projects · ₹7,999
3 projects · ₹9,999
Within 1 working day
Didn’t help you decide? Full refund — no questions asked.
Compare project details for free →MahaRERA · registration record · read 12 July 2026
MahaRERA · per-home inventory · saved-file date 18 July 2026
This is a past RERA home list, not current availability. It does not give the date each home was sold.
The home-list date is based on the saved file’s details.
Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.