Buyer’s Report
Understand this project
Find homes to consider, with advice on light, layout, privacy and surroundings.
₹4,999
Builder’s RERA records,
explained for buyers.
The builder’s RERA record, explained
AMRUTKALASH PROPERTIES · P52100004921
For AMRUTKALASH (P52100004921), 101 of 164 entries were marked unsold in the MahaRERA home list read 4 September 2026.
For AMRUTKALASH, ₹3,946 per sq ft of carpet area is the median rate across 63 sold or booked entries with prices in the MahaRERA home list read 4 September 2026. These are historical agreement values, not current asking prices.
These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.
Builder’s completion target
The builder reported this target date. It is not a confirmed handover date.
Status shown on RERA
This is the status shown on RERA. It does not confirm an occupancy certificate or today’s construction progress.
Prices reported to RERA
₹3,946/ sq ft carpet area
Across 63 sold or booked entries with reported prices. The middle 80% of rates fall between ₹3,197 and ₹5,533.
MahaRERA · per-home inventory · read 4 September 2026
For each sold or booked entry, we divide the reported agreement value by its carpet area in square feet. The median is the middle rate when these rates are put in order. We show it only when at least five entries have prices. We exclude valuations of unsold homes and government reference rates. The figures may include different sizes and property types. They are historical agreement values, not current asking prices or the total cost including extra charges.
Sales Report
Compare reported agreement values by building, size and floor. See which homes were marked unsold on the date shown.
Inside this registered phase
164 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.
MahaRERA · per-home inventory · read 4 September 2026
Scroll sideways to see all columns.
| Filed building | Entries | Sold | Booked | Marked unsold | Other / unstated status | Recorded carpet-area range |
|---|---|---|---|---|---|---|
| A | 52 | 0 | 0 | 52 | 0 | 35.55–51.66 sq m≈ 383–556 sq ft |
| B | 56 | 56 | 0 | 0 | 0 | 35.57–49.74 sq m≈ 383–535 sq ft |
| C | 56 | 7 | 0 | 49 | 0 | 35.55–51.66 sq m≈ 383–556 sq ft |
Different sizes are not necessarily different bedroom types. How we read and summarise the filing →
Unit Report
Understand its light, privacy, layout and surroundings. See how it compares with similar homes and other options in this project.
Didn’t help you decide? Full refund — no questions asked.
The same home number may appear in more than one building. Check both before choosing.
MahaRERA · per-home inventory · read 4 September 2026
| Home / building | Floor in the record | Carpet area | Reported status | Agreement value | Assess |
|---|---|---|---|---|---|
| 101A | 1 | 51.66 sq m≈ 556 sq ft | Marked unsold | Not stated | |
| 102A | 1 | 37.75 sq m≈ 406 sq ft | Marked unsold | Not stated | |
| 103A | 1 | 37.75 sq m≈ 406 sq ft | Marked unsold | Not stated | |
| 104A | 1 | 51.66 sq m≈ 556 sq ft | Marked unsold | Not stated | |
| 105A | 1 | 49.64 sq m≈ 534 sq ft | Marked unsold | Not stated | |
| 106A | 1 | 35.55 sq m≈ 383 sq ft | Marked unsold | Not stated | |
| 107A | 1 | 35.55 sq m≈ 383 sq ft | Marked unsold | Not stated | |
| 108A | 1 | 49.64 sq m≈ 534 sq ft | Marked unsold | Not stated | |
| 201A | 2 | 51.66 sq m≈ 556 sq ft | Marked unsold | Not stated | |
| 202A | 2 | 37.75 sq m≈ 406 sq ft | Marked unsold | Not stated | |
| 203A | 2 | 37.75 sq m≈ 406 sq ft | Marked unsold | Not stated | |
| 204A | 2 | 51.66 sq m≈ 556 sq ft | Marked unsold | Not stated |
Read every entry in one table: Read the complete saved home list.
Choose the home you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.
More from the RERA documents
₹98,529,010 of an estimated ₹173,250,000 was reported as incurred (56.9%). This percentage is about costs. It does not show how much construction is complete.
MahaRERA project filing · read 18 July 2026 · registration P52100004921
Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.
| Building | Activity | Reported |
|---|---|---|
| C | Excavation | 100.0% |
| C | Basement (if any) | 100.0% |
| C | Podiums (if any) | 0.0% |
| C | Plinth | 0.0% |
| C | Stilt Floor | 0.0% |
| C | Slabs of Super Structure | 70.0% |
| C | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 45.0% |
| C | Sanitary Fittings within the flats / premises | 0.0% |
| C | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 50.0% |
| C | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0.0% |
| C | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0.0% |
| B | Excavation | 100.0% |
| B | Basement (if any) | 100.0% |
| B | Podiums (if any) | 0.0% |
| B | Plinth | 100.0% |
| B | Stilt Floor | 0.0% |
| B | Slabs of Super Structure | 100.0% |
| B | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100.0% |
| B | Sanitary Fittings within the flats / premises | 100.0% |
| B | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 98.0% |
| B | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100.0% |
| B | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 70.0% |
| A | Excavation | 100.0% |
| A | Basement (if any) | 0.0% |
| A | Podiums (if any) | 0.0% |
| A | Plinth | 0.0% |
| A | Stilt Floor | 0.0% |
| A | Slabs of Super Structure | 0.0% |
| A | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0.0% |
| A | Sanitary Fittings within the flats / premises | 0.0% |
| A | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0.0% |
| A | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0.0% |
| A | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0.0% |
MahaRERA project filing · read 18 July 2026 · registration P52100004921
| Revised target | Reason given by the builder |
|---|---|
| 31 December 2025 | Amrutkalash Properties project was Registered with Rera No.P52100004921 the said project sanctioned by PMRDA on 11.07. 2017 due to post demonetization. The construction was started in 2018. There was slow booking hence, only one building i.e. 'B' Building (56 Flats ) started and it is now under completion. Building 'A' (52flats)and building 'C' (56flats) construction not started and also booking not taken for 'A' and 'C' building. Due to Covid 2019 and because of labour problem construction could not done in 2019- 2020 for building B. Now, we require extension for 'A' and 'C' building till March 2025.and for under construction building B till MARCH 2023. We have obtained consent of 53% Flat purchasers (31 out of 38 sold flats in 'B' building. Kindly consider our extension request. |
| 31 December 2027 | The Project Registration Certificate was obtained in 2017, due to post demonetization Booking of the Units were slow and same was continued in Covid-19 and post pandemic till 2020-2021 as the Project is in Rural / Suburban Area in Pune. Unfortunately, one of the Partner died in November 2021 and due to financial difficulties, the project construction work was slowed down. That as on date we have completed 90 percent work for Building B in the Project and we are also in process of obtaining Completion Certificate for B Building from the Local Authority i.e. Pune Metropolitan Region Development Authority (PMRDA). The construction work for C Building has been commenced from 2023 and more than 50 percent work of said Building is completed. The A Building is also under construction and we will complete it by the proposed Extension Date of Completion i.e. 31st December 2027. Therefore we Request you to consider our Date for Project Extension Request and grant us Project Extension Certificate for Completion of the Project. |
MahaRERA project filing · read 18 July 2026 · registration P52100004921
RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.
| Filing | Own funds | Borrowing | Payments from buyers | Total |
|---|---|---|---|---|
| Estimated plan | ₹64,280,000 | ₹24,000,000 | ₹120,000,000 | ₹223,280,000 |
| Actual raised | ₹56,921,440 | ₹0 | ₹79,383,087 | ₹136,304,527 |
MahaRERA project filing · read 18 July 2026 · registration P52100004921
38 elapsed quarterly periods in the captured compliance schedule. Active default was recorded for FY 2025-2026.
MahaRERA project filing · read 18 July 2026 · registration P52100004921
A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.
MahaRERA project filing · read 18 July 2026 · registration P52100004921
Builder and past records
Projects registered under this company
1Pune registrations
These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.
MahaRERA Pune registration records · read 12 July 2026
Past records of sales and unsold homes
22 September 2026
101 marked unsold · 63 sold · 0 booked.
Saved MahaRERA home list
13 September 2026
101 marked unsold · 63 sold · 0 booked.
Saved MahaRERA home list
4 September 2026
101 marked unsold · 63 sold · 0 booked.
Saved MahaRERA home list
18 July 2026
104 marked unsold · 60 sold · 0 booked.
Saved MahaRERA home list
These dates show when the records were saved, not when homes were sold. Sales may have changed since then, even if the saved counts are the same.
More projects to explore
These projects list the same locality. They may differ in exact location, home type and price.
Pune · Pune
P52100077822
204 of 264 entries marked unsold
MahaRERA · per-home inventory · read 28 September 2026
View project details →Pune · Pune
P52100050290
88 of 128 entries marked unsold
MahaRERA · per-home inventory · read 10 September 2026
View project details →Pune · Pune
P52100027363
17 of 181 entries marked unsold
MahaRERA · per-home inventory · saved-file date 18 July 2026
View project details →Project Comparison Report
Compare up to three projects. We read their plans and RERA documents, recommend homes in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.
2 projects · ₹7,999
3 projects · ₹9,999
Within 1 working day
Didn’t help you decide? Full refund — no questions asked.
Compare project details for free →MahaRERA · registration record · read 12 July 2026
MahaRERA · per-home inventory · read 4 September 2026
This is a past RERA home list, not current availability. It does not give the date each home was sold.
Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.
Open MahaRERA · search P52100004921 ↗