The builder’s RERA record, explained

AMBROSIA GALAXY

DIVYASPARSH INFRA LLP · P52100027363

MahaRERA · registration record · read 12 July 2026

Choose a report ↓

What does the RERA record show?

For AMBROSIA GALAXY (P52100027363), 17 of 181 entries were marked unsold in the MahaRERA home list dated 18 July 2026 (saved-file date).

MahaRERA · per-home inventory · saved-file date 18 July 2026

For AMBROSIA GALAXY, ₹12,907 per sq ft of carpet area is the median rate across 103 sold or booked entries with prices in the MahaRERA home list dated 18 July 2026 (saved-file date). These are historical agreement values, not current asking prices.

MahaRERA · per-home inventory · saved-file date 18 July 2026

These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.

What would help you decide?

Buyer’s Report

Understand this project

Find homes to consider, with advice on light, layout, privacy and surroundings.

₹4,999

Unit Report

Check a particular home

See its advantages, drawbacks and how it compares with other homes in this project.

₹3,999

Project Comparison Report

Choose between projects

Compare two or three projects and get recommended homes in order, with reasons for each choice.

From ₹7,999

Choose projects →

Project status and completion date.

Prices reported to RERA

What prices have been reported?

₹12,907/ sq ft carpet area

Across 103 sold or booked entries with reported prices. The middle 80% of rates fall between ₹9,565 and ₹18,309.

MahaRERA · per-home inventory · saved-file date 18 July 2026

How is this calculated?

For each sold or booked entry, we divide the reported agreement value by its carpet area in square feet. The median is the middle rate when these rates are put in order. We show it only when at least five entries have prices. We exclude valuations of unsold homes and government reference rates. The figures may include different sizes and property types. They are historical agreement values, not current asking prices or the total cost including extra charges.

Sales Report

What did similar homes sell for?

Compare reported agreement values by building, size and floor. See which homes were marked unsold on the date shown.

₹2,999 · delivered on payment

Inside this registered phase

How do the buildings compare in the record?

181 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.

MahaRERA · per-home inventory · saved-file date 18 July 2026

Scroll sideways to see all columns.

Building names, sale status and carpet areas — not current availability
Filed buildingEntriesSoldBookedMarked unsoldOther / unstated statusRecorded carpet-area range
AMBROSIA GALAXY1811030176129.14–991.65 sq m≈ 314–10,674 sq ft

Different sizes are not necessarily different bedroom types. How we read and summarise the filing →

Unit Report

Is this the right
home for you?

Understand its light, privacy, layout and surroundings. See how it compares with similar homes and other options in this project.

₹3,999 · 1 working day

Didn’t help you decide? Full refund — no questions asked.

Find your home in the RERA list.

The same home number may appear in more than one building. Check both before choosing.

181 listed entries

MahaRERA · per-home inventory · saved-file date 18 July 2026

RERA home list, not current availability
Home / buildingFloor in the recordCarpet areaReported statusAgreement valueAssess
1001AMBROSIA GALAXY1075.45 sq m≈ 812 sq ftOwner investorNot stated
1002AMBROSIA GALAXY1060.39 sq m≈ 650 sq ftOwner investorNot stated
1003AMBROSIA GALAXY1053.05 sq m≈ 571 sq ftOwner investorNot stated
1004AMBROSIA GALAXY1052.81 sq m≈ 568 sq ftOwner investorNot stated
1005AMBROSIA GALAXY1063.14 sq m≈ 680 sq ftOwner investorNot stated
1006AMBROSIA GALAXY1063.15 sq m≈ 680 sq ftOwner investorNot stated
1007AMBROSIA GALAXY1052.79 sq m≈ 568 sq ftOwner investorNot stated
1008AMBROSIA GALAXY10128.8 sq m≈ 1,386 sq ftOwner investorNot stated
1011AMBROSIA GALAXY1099.56 sq m≈ 1,072 sq ftOwner investorNot stated
1012AMBROSIA GALAXY1045.0 sq m≈ 484 sq ftOwner investorNot stated
1013AMBROSIA GALAXY1042.43 sq m≈ 457 sq ftOwner investorNot stated
1014AMBROSIA GALAXY1039.03 sq m≈ 420 sq ftOwner investorNot stated

Read every entry in one table: Read the complete saved home list.

Choose the home you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.

More from the RERA documents

Construction progress and project documents.

Cost reported as incurred

₹842,582,453 of an estimated ₹842,582,453 was reported as incurred (100.0%). This percentage is about costs. It does not show how much construction is complete.

MahaRERA project filing · read 19 July 2026 · registration P52100027363

Work reported, by building

Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.

See all reported activities
BuildingActivityReported
AMBROSIA GALAXYExcavation100.0%
AMBROSIA GALAXYBasement (if any)100.0%
AMBROSIA GALAXYPodiums (if any) 100.0%
AMBROSIA GALAXYPlinth100.0%
AMBROSIA GALAXYStilt Floor 100.0%
AMBROSIA GALAXYSlabs of Super Structure65.0%
AMBROSIA GALAXYInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50.0%
AMBROSIA GALAXYSanitary Fittings within the flats / premises0.0%
AMBROSIA GALAXYStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
AMBROSIA GALAXYExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
AMBROSIA GALAXYInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%

MahaRERA project filing · read 19 July 2026 · registration P52100027363

Reported deadline extensions

Revised targetReason given by the builder
30 April 2025completion Certificate not received from municipal corporation
30 November 2025The delay in obtaining the necessary water line and MSEB (Maharashtra State Electricity Board)line connections is beyond our control and has significantly impacted the progress of the project. Despite our repeated follow-ups and submissions, the concerned authorities have not yet provided the required approvals or completed the necessary installations, which has led to an unforeseen delay in the project timeline. These utility connections are crucial for the proper functioning of the development, and the delay is directly affecting our ability to proceed with the construction as scheduled. As a result, we are seeking an extension from RERA to account for this unavoidable delay and ensure that we can complete the project in compliance with all necessary regulations and requirements.

MahaRERA project filing · read 19 July 2026 · registration P52100027363

Where the project funding comes from

RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.

FilingOwn fundsBorrowingPayments from buyersTotal
Estimated plan₹362,690,259₹550,000,000₹209,212,261₹1,121,902,520
Actual raised₹622,195,665₹230,233,152₹209,212,261₹1,061,641,078

MahaRERA project filing · read 19 July 2026 · registration P52100027363

Quarterly filing record

21 elapsed quarterly periods in the captured compliance schedule. Active default was recorded for FY 2025-2026.

MahaRERA project filing · read 19 July 2026 · registration P52100027363

Documents named in the filing

  • Promoter PAN · 2 listed
  • Form 1 — Architect's certificate · 5 listed
  • Form 3 — CA certificate · 12 listed
  • Form 2 — Engineer's certificate · 13 listed
  • Title / search report · 1 listed
  • Form B — Promoter declaration · 1 listed
  • Sanctioned building plan · 19 listed
  • Sanctioned layout plan · 13 listed
  • Occupancy / completion certificate · 2 listed

A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.

MahaRERA project filing · read 19 July 2026 · registration P52100027363

Builder and past records

What else does the record show?

Projects registered under this company

DIVYASPARSH INFRA LLP

1Pune registrations

These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.

MahaRERA Pune registration records · read 12 July 2026

Explore other registrations

    Past records of sales and unsold homes

    1. 26 September 2026

      17 marked unsold · 103 sold · 0 booked.

      Saved MahaRERA home list

    2. 17 September 2026

      17 marked unsold · 103 sold · 0 booked.

      Saved MahaRERA home list

    3. 9 September 2026

      17 marked unsold · 103 sold · 0 booked.

      Saved MahaRERA home list

    4. 19 July 2026

      17 marked unsold · 103 sold · 0 booked.

      Saved MahaRERA home list

    These dates show when the records were saved, not when homes were sold. Sales may have changed since then, even if the saved counts are the same.

    More projects to explore

    Other projects in this locality.

    These projects list the same locality. They may differ in exact location, home type and price.

    Project Comparison Report

    Which project should you buy in?
    And which home?

    Compare up to three projects. We read their plans and RERA documents, recommend homes in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.

    Create my Comparison Report →

    2 projects · ₹7,999
    3 projects · ₹9,999

    Within 1 working day

    Didn’t help you decide? Full refund — no questions asked.

    Compare project details for free →

    Sources and dates.

    MahaRERA · registration record · read 12 July 2026

    MahaRERA · per-home inventory · saved-file date 18 July 2026

    This is a past RERA home list, not current availability. It does not give the date each home was sold.

    The home-list date is based on the saved file’s details.

    Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.

    Open MahaRERA · search P52100027363 ↗