Vimal Gordhanbhai Pipalia · P52100004993
For Urja Cornerstone Building 1 (P52100004993), 2 of 98 entries were marked unsold in the MahaRERA home list dated 18 July 2026 (saved-file date).
MahaRERA · per-home inventory · saved-file date 18 July 2026
For Urja Cornerstone Building 1, ₹4,140 per sq ft of carpet area is the median rate across 81 sold or booked entries with prices in the MahaRERA home list dated 18 July 2026 (saved-file date). These are historical agreement values, not current asking prices.
MahaRERA · per-home inventory · saved-file date 18 July 2026
These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.
Builder’s completion target
This target date has passed. The record shown here does not confirm whether the project is complete or has received more time.
Status shown on RERA
This is the status shown on RERA. It does not confirm an occupancy certificate or today’s construction progress.
Prices reported to RERA
₹4,140/ sq ft carpet area
Across 81 sold or booked entries with reported prices. The middle 80% of rates fall between ₹1,962 and ₹4,978.
MahaRERA · per-home inventory · saved-file date 18 July 2026
For each sold or booked entry, we divide the reported agreement value by its carpet area in square feet. The median is the middle rate when these rates are put in order. We show it only when at least five entries have prices. We exclude valuations of unsold homes and government reference rates. The figures may include different sizes and property types. They are historical agreement values, not current asking prices or the total cost including extra charges.
Sales Report
Compare reported agreement values by building, size and floor. See which homes were marked unsold on the date shown.
Inside this registered phase
98 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.
MahaRERA · per-home inventory · saved-file date 18 July 2026
Scroll sideways to see all columns.
| Filed building | Entries | Sold | Booked | Marked unsold | Other / unstated status | Recorded carpet-area range |
|---|---|---|---|---|---|---|
| Urja Cornerstone Building 1 | 98 | 81 | 0 | 2 | 15 | 40.94–66.54 sq m≈ 441–716 sq ft |
Different sizes are not necessarily different bedroom types. How we read and summarise the filing →
Unit Report
Understand its light, privacy, layout and surroundings. See how it compares with similar homes and other options in this project.
Didn’t help you decide? Full refund — no questions asked.
The same home number may appear in more than one building. Check both before choosing.
MahaRERA · per-home inventory · saved-file date 18 July 2026
| Home / building | Floor in the record | Carpet area | Reported status | Agreement value | Assess |
|---|---|---|---|---|---|
| A Wing 110Urja Cornerstone Building 1 | 1 | 57.3 sq m≈ 617 sq ft | Sold | ₹2,595,800 | |
| A Wing 111Urja Cornerstone Building 1 | 1 | 56.4 sq m≈ 607 sq ft | Sold | ₹2,348,200 | |
| A Wing 112Urja Cornerstone Building 1 | 1 | 56.39 sq m≈ 607 sq ft | Sold | ₹2,475,000 | |
| A Wing 114Urja Cornerstone Building 1 | 1 | 41.28 sq m≈ 444 sq ft | Sold | ₹1,687,800 | |
| A Wing 109Urja Cornerstone Building 1 | 1 | 41.25 sq m≈ 444 sq ft | Sold | ₹1,941,900 | |
| A Wing 209Urja Cornerstone Building 1 | 2 | 41.33 sq m≈ 445 sq ft | Sold | ₹1,830,150 | |
| A Wing 210Urja Cornerstone Building 1 | 2 | 57.38 sq m≈ 618 sq ft | Sold | ₹3,100,000 | |
| A Wing 211Urja Cornerstone Building 1 | 2 | 66.54 sq m≈ 716 sq ft | Sold | ₹2,730,000 | |
| A Wing 212Urja Cornerstone Building 1 | 2 | 51.2 sq m≈ 551 sq ft | Sold | ₹2,200,000 | |
| A Wing 214Urja Cornerstone Building 1 | 2 | 41.36 sq m≈ 445 sq ft | Sold | ₹1,850,000 | |
| A Wing 309Urja Cornerstone Building 1 | 3 | 41.25 sq m≈ 444 sq ft | Sold | ₹1,971,000 | |
| A Wing 312Urja Cornerstone Building 1 | 3 | 56.39 sq m≈ 607 sq ft | Sold | ₹2,293,200 |
Read every entry in one table: Read the complete saved home list.
Choose the home you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.
More from the RERA documents
Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.
| Building | Activity | Reported |
|---|---|---|
| Urja Cornerstone Building 1 | Excavation | 100.0% |
| Urja Cornerstone Building 1 | Basement (if any) | 100.0% |
| Urja Cornerstone Building 1 | Podiums (if any) | 0.0% |
| Urja Cornerstone Building 1 | Plinth | 100.0% |
| Urja Cornerstone Building 1 | Stilt Floor | 100.0% |
| Urja Cornerstone Building 1 | Slabs of Super Structure | 100.0% |
| Urja Cornerstone Building 1 | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100.0% |
| Urja Cornerstone Building 1 | Sanitary Fittings within the flats / premises | 100.0% |
| Urja Cornerstone Building 1 | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100.0% |
| Urja Cornerstone Building 1 | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100.0% |
| Urja Cornerstone Building 1 | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100.0% |
MahaRERA project filing · read 18 July 2026 · registration P52100004993
| Revised target | Reason given by the builder |
|---|---|
| 30 April 2020 | Urja Cornerstone Building no. 1 is completed 99% in all aspects and we will apply for OC as soon as remaining work completed, we expect OC within six months. |
| 30 April 2020 | Our project "Urja Cornerstone Building 1", RCC work completed 100% as per Architect Certificate. Project is delayed due to material, labour and other unavoidable reasons. we will try to complete our project by December 2019. |
| 31 December 2024 | To, Maharashtra Real Estate Regulatory Authority (MAHA RERA), BKC, HousefinBhavan, Near RBI, E Block, Bandra Kurla Complex, Bandra East, Mumbai, Maharashtra 400051 Subject:- Extension of Project Date for Project “Urja Cornerstone Building 1” Dear Sir, Madam, We have registered our project “UrjaCornerstone Building 1” Located at Bearing / CTS / Survey /Final PlotNo.: Gut No.2440/1 Village Chakan Taluka Khedat Chakan (CT),Khed, Pune, 410501 vide MAHA RERA No. P52100004993 with RERA authority in the month of Aug 2017, due to COVID – 19 Pandemic scenario and overall MarketScenario has badly impacted our project. Since this delay is beyond our control we make a request for the Project Delivery date to be extended till 31st Dec 2024. Appreciated it if this matter is looked into the earliest possible date. Thanking You, |
MahaRERA project filing · read 18 July 2026 · registration P52100004993
RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.
| Filing | Own funds | Borrowing | Payments from buyers | Total |
|---|---|---|---|---|
| Estimated plan | ₹10,000,000 | ₹0 | ₹161,517,489 | ₹234,580,063 |
| Actual raised | ₹5,000,000 | ₹0 | ₹138,345,681 | ₹240,383,905 |
MahaRERA project filing · read 18 July 2026 · registration P52100004993
32 elapsed quarterly periods in the captured compliance schedule. Active default was recorded for FY 2025-2026.
MahaRERA project filing · read 18 July 2026 · registration P52100004993
A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.
MahaRERA project filing · read 18 July 2026 · registration P52100004993
Builder and past records
Projects registered under this company
3Pune registrations
These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.
MahaRERA Pune registration records · read 12 July 2026
Past records of sales and unsold homes
21 September 2026
2 marked unsold · 81 sold · 0 booked.
Saved MahaRERA home list
13 September 2026
2 marked unsold · 81 sold · 0 booked.
Saved MahaRERA home list
4 September 2026
2 marked unsold · 81 sold · 0 booked.
Saved MahaRERA home list
18 July 2026
2 marked unsold · 81 sold · 0 booked.
Saved MahaRERA home list
These dates show when the records were saved, not when homes were sold. Sales may have changed since then, even if the saved counts are the same.
More projects to explore
These projects list the same locality. They may differ in exact location, home type and price.
Grampanchayat · Pune
P52100006381
39 of 98 entries marked unsold
MahaRERA · per-home inventory · saved-file date 18 July 2026
View project details →Project Comparison Report
Compare up to three projects. We read their plans and RERA documents, recommend homes in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.
2 projects · ₹7,999
3 projects · ₹9,999
Within 1 working day
Didn’t help you decide? Full refund — no questions asked.
Compare project details for free →MahaRERA · registration record · read 12 July 2026
MahaRERA · per-home inventory · saved-file date 18 July 2026
This is a past RERA home list, not current availability. It does not give the date each home was sold.
The home-list date is based on the saved file’s details.
Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.
Open MahaRERA · search P52100004993 ↗