The builder’s RERA record, explained
SHREE VISION · P52100005128
For VISION 7 - PHASE I (P52100005128), 110 of 203 entries were marked unsold in the MahaRERA home list dated 18 July 2026 (saved-file date).
MahaRERA · per-home inventory · saved-file date 18 July 2026
For VISION 7 - PHASE I, ₹16,930 per sq ft of carpet area is the median rate across 93 sold or booked entries with prices in the MahaRERA home list dated 18 July 2026 (saved-file date). These are historical agreement values, not current asking prices.
MahaRERA · per-home inventory · saved-file date 18 July 2026
These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.
Builder’s completion target
The builder reported this target date. It is not a confirmed handover date.
Status shown on RERA
This is the status shown on RERA. It does not confirm an occupancy certificate or today’s construction progress.
Prices reported to RERA
₹16,930/ sq ft carpet area
Across 93 sold or booked entries with reported prices. The middle 80% of rates fall between ₹13,040 and ₹28,674.
MahaRERA · per-home inventory · saved-file date 18 July 2026
For each sold or booked entry, we divide the reported agreement value by its carpet area in square feet. The median is the middle rate when these rates are put in order. We show it only when at least five entries have prices. We exclude valuations of unsold homes and government reference rates. The figures may include different sizes and property types. They are historical agreement values, not current asking prices or the total cost including extra charges.
Sales Report
Compare reported agreement values by building, size and floor. See which homes were marked unsold on the date shown.
Inside this registered phase
203 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.
MahaRERA · per-home inventory · saved-file date 18 July 2026
Scroll sideways to see all columns.
| Filed building | Entries | Sold | Booked | Marked unsold | Other / unstated status | Recorded carpet-area range |
|---|---|---|---|---|---|---|
| Vision 7 - Phase I | 203 | 93 | 0 | 110 | 0 | 7.30–173.17 sq m≈ 79–1,864 sq ft |
Different sizes are not necessarily different bedroom types. How we read and summarise the filing →
Unit Report
Understand its light, privacy, layout and surroundings. See how it compares with similar homes and other options in this project.
Didn’t help you decide? Full refund — no questions asked.
The same home number may appear in more than one building. Check both before choosing.
MahaRERA · per-home inventory · saved-file date 18 July 2026
| Home / building | Floor in the record | Carpet area | Reported status | Agreement value | Assess |
|---|---|---|---|---|---|
| AUDI-1Vision 7 - Phase I | 4 | 173.17 sq m≈ 1,864 sq ft | Marked unsold | Not stated | |
| AUDI-2Vision 7 - Phase I | 4 | 99.35 sq m≈ 1,069 sq ft | Marked unsold | Not stated | |
| SHOP- 101CVision 7 - Phase I | 1 | 40.27 sq m≈ 433 sq ft | Marked unsold | Not stated | |
| SHOP- 101bVision 7 - Phase I | 1 | 40.27 sq m≈ 433 sq ft | Marked unsold | Not stated | |
| SHOP- 114CVision 7 - Phase I | 1 | 62.17 sq m≈ 669 sq ft | Marked unsold | Not stated | |
| SHOP- 19AVision 7 - Phase I | 205 | 23.19 sq m≈ 250 sq ft | Marked unsold | Not stated | |
| SHOP- 201 EVision 7 - Phase I | 2 | 27.31 sq m≈ 294 sq ft | Marked unsold | Not stated | |
| SHOP- 201AVision 7 - Phase I | 2 | 35.79 sq m≈ 385 sq ft | Marked unsold | Not stated | |
| SHOP- 201CVision 7 - Phase I | 2 | 35.79 sq m≈ 385 sq ft | Marked unsold | Not stated | |
| SHOP- 214CVision 7 - Phase I | 2 | 65.74 sq m≈ 708 sq ft | Marked unsold | Not stated | |
| SHOP- 223AVision 7 - Phase I | 2 | 8.54 sq m≈ 92 sq ft | Marked unsold | Not stated | |
| SHOP-01AVision 7 - Phase I | 205 | 89.58 sq m≈ 964 sq ft | Sold | ₹15,000,000 |
Read every entry in one table: Read the complete saved home list.
Choose the home you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.
More from the RERA documents
Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.
| Building | Activity | Reported |
|---|---|---|
| Vision 7 - Phase I | Excavation | 100.0% |
| Vision 7 - Phase I | Basement (if any) | 100.0% |
| Vision 7 - Phase I | Podiums (if any) | 0.0% |
| Vision 7 - Phase I | Plinth | 100.0% |
| Vision 7 - Phase I | Stilt Floor | 100.0% |
| Vision 7 - Phase I | Slabs of Super Structure | 90.0% |
| Vision 7 - Phase I | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 90.0% |
| Vision 7 - Phase I | Sanitary Fittings within the flats / premises | 90.0% |
| Vision 7 - Phase I | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 70.0% |
| Vision 7 - Phase I | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 80.0% |
| Vision 7 - Phase I | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 73.0% |
MahaRERA project filing · read 18 July 2026 · registration P52100005128
| Revised target | Reason given by the builder |
|---|---|
| 30 July 2020 | Constructions of the project is almost complete but common area and facilities are under development which we will complete within 12 months. |
| 29 January 2023 | Project is completed to the tune of 75%, almost 73% of the allottees have given their consent for extension of the project. |
| 30 January 2025 | We have already completed the floors which we have sold/allotted to allottee(s)/Customer(s), we have already in-warded the application for NOC(s) from Drainage and Fire in respective departments and once we receive such NOC(s), we will inward the file for Occupancy Certificate from Local Authorities for this Phase. The Upper Floor of this Phase (Third Floor) for which construction is on going but we have not yet sold a single unit located on this floor(Third Floor). In order to get the OC from local authorities (For This Phase), for the floors which we have sold and for the Third floor which we have not yet sold to any one, we will require time time till 30/01/2025. Required consent has been obtained from allottees |
| 30 January 2027 | The project has encountered unforeseen challenges that have significantly impacted its timeline and progress. These challenges include: 1. Severe Labor Shortage: o The project has been critically affected by a shortage of skilled labour, which is essential for maintaining the desired quality and pace of construction. o The labour shortage has been exacerbated by external factors, including market-wide labour demand, seasonal migrations, and economic disruptions. This has led to a delay in completing key milestones. 2. Impact on Contractor's Performance: o The labour shortage has directly impacted the contractor's ability to deploy adequate resources, leading to inefficiencies in task execution and prolonged timelines for specific activities. o Furthermore, the reduced availability of skilled workers has resulted in compromises in workmanship quality, necessitating rework and additional supervision to meet the required standards. 3. Ensuring Quality and Compliance: o To deliver the project within the promised quality and safety standards, additional time is essential. Proceeding with limited resources could jeopardize structural integrity and compliance with statutory norms, which is unacceptable for the project and stakeholders. 4. Mitigating Risks and Ensuring Stability: o An extension will provide the project team with the necessary flexibility to resolve workforce constraints, enhance contractor performance, and address inefficiencies without compromising on quality or safety. o This approach aligns with the project's commitment to delivering a robust and sustainable structure while safeguarding the interests of all stakeholders. |
MahaRERA project filing · read 18 July 2026 · registration P52100005128
RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.
| Filing | Own funds | Borrowing | Payments from buyers | Total |
|---|---|---|---|---|
| Estimated plan | ₹90,000,000 | ₹0 | ₹125,959,010 | ₹215,959,010 |
| Actual raised | ₹35,168,902 | ₹0 | ₹180,790,108 | ₹215,959,010 |
MahaRERA project filing · read 18 July 2026 · registration P52100005128
36 elapsed quarterly periods in the captured compliance schedule. Active default was recorded for FY 2025-2026.
MahaRERA project filing · read 18 July 2026 · registration P52100005128
A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.
MahaRERA project filing · read 18 July 2026 · registration P52100005128
Builder and past records
Projects registered under this company
1Pune registrations
These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.
MahaRERA Pune registration records · read 12 July 2026
Past records of sales and unsold homes
21 September 2026
110 marked unsold · 93 sold · 0 booked.
Saved MahaRERA home list
13 September 2026
110 marked unsold · 93 sold · 0 booked.
Saved MahaRERA home list
4 September 2026
110 marked unsold · 93 sold · 0 booked.
Saved MahaRERA home list
18 July 2026
110 marked unsold · 93 sold · 0 booked.
Saved MahaRERA home list
These dates show when the records were saved, not when homes were sold. Sales may have changed since then, even if the saved counts are the same.
More projects to explore
These projects list the same locality. They may differ in exact location, home type and price.
Pune · Pune
P52100077822
204 of 264 entries marked unsold
MahaRERA · per-home inventory · read 28 September 2026
View project details →Pune · Pune
P52100050290
88 of 128 entries marked unsold
MahaRERA · per-home inventory · read 10 September 2026
View project details →Pune · Pune
P52100027363
17 of 181 entries marked unsold
MahaRERA · per-home inventory · saved-file date 18 July 2026
View project details →Project Comparison Report
Compare up to three projects. We read their plans and RERA documents, recommend homes in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.
2 projects · ₹7,999
3 projects · ₹9,999
Within 1 working day
Didn’t help you decide? Full refund — no questions asked.
Compare project details for free →MahaRERA · registration record · read 12 July 2026
MahaRERA · per-home inventory · saved-file date 18 July 2026
This is a past RERA home list, not current availability. It does not give the date each home was sold.